[Federal Register Volume 64, Number 132 (Monday, July 12, 1999)]
[Corrections]
[Page 37582]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: C9-8939]
Federal Register / Vol. 64, No. 132 / Monday, July 12, 1999 /
Corrections
[[Page 37582]]
ENVRIONMENTAL PROTECTION AGENCY
40 CFR Part 75
[FRL-6320-8]
RIN 2060-AG46
Acid Rain Program; Continuous Emission Monitoring Rule Revisions
Correction
In rule document 99-8939 beginning on page 28564 in the issue of
Wednesday, May 26, 1999, make the following correction(s):
Sec. 75.19 [Corrected]
1. On page 28592, in the third column, in Sec. 75.19(c)(4)(ii)(A),
under ``Where:'', ``EFNNO'' should read ``EFNO''
Sec. 75.57 [Corrected]
2. On page 28610, in the second column, Sec. 75.57(c)(4)(iv), in
table 4A., in entry 4., ``NSO2'' should read
``SO2''.
Appendix A to Part 75 [Corrected]
3. On page 28637, in the second column, in appendix A, in section
3.1(b), in the 11th and 12th lines, ``|R-A-'' and in the 19th line, ``-
R-A|'' should read ``|R-A|''.
4. On page 28643, in the first column, in appendix A, in section
7.6.5(b), in the 14th and 15th lines, ``'' should read
``''.
5. On page 28645, in the first column, in appendix A, in section
1.2.4, in the 5th line, ``SO or NO2'' should read
``SO2 or NO''.
Appendix B to Part 75 [Corrected]
6. On page 28652, in the table, Figure 2 to Appendix B of part 75,
in the second column, in the fifth line, ``1.5%
H2O2'' should read ``1.5%
H2O2''.
7. On the same page, in the same table, in the footnote 3,
``NO2'' should read ``NO''.
Appendix D to Part 75 [Corrected]
8. On page 28654, in the second column, in appendix D, in section
2.1.5.2, paragraph designation ``(4)'' should read ``(b)''.
9. On page 28661, in the second column, in appendix D, in section
2.3.2.1.2(d), in the fourth line, paragraph designation ``(5)'' should
read ``(e)''.
Appendix E to Part 75 [Corrected]
10. On page 28667, in the third column, in appendix E, in section
4.3, for ``(Eq. F-13)'', under ``Where:'', in the first line, ``mass
emission,'' should read ``mass emissions, tons.''.
Appendix B to Part 75 [Corrected]
11. On page 28651, the table ``Figure 1 to Appendix B to Part 75-
Quality Assurance Text Requirements'' is corrected and set out in its
entirety below:
Figure 1 to Appendix B of Part 75--Quality Assurance Test Requirements.
----------------------------------------------------------------------------------------------------------------
QA test frequency requirements
Test --------------------------------------------------
Daily* Quarterly* Semiannual*
----------------------------------------------------------------------------------------------------------------
Calibration Error (2 pt.).................................... ............... ...............
Interference (flow).......................................... ............... ...............
Flow-to-Load Ratio........................................... ............... ...............
Leak Check (DP flow monitors)................................ ............... ...............
Linearity (3 pt.)............................................ ............... ...............
RATA (SO2, NOX, CO2, H2O)1................................... ............... ...............
RATA (flow)1,2............................................... ............... ...............
----------------------------------------------------------------------------------------------------------------
*For monitors on bypass stack/duct, ``daily'' means bypass operating days, only. ``Quarterly'' means once every
QA operating quarter. ``Semiannual'' means once every two QA operating quarters.
\1\ Conduct RATA annually (i.e., once every four QA operating quarters), if monitor meets accuracy requirements
to qualify for less frequent testing.
\2\ For flow monitors installed on peaking units and bypass stacks, conduct all RATAs at a single, normal load.
For other flow monitors, conduct annual RATAs at the two load levels used most frequently since the last
annual RATA. Alternating single-load and 2-load RATAs may be done if a monitor is on a semiannual frequency. A
single-load RATA may be done in lieu of a 2-load RATA if, since the last annual flow RATA, the unit has
operated at one load level for 85.0 percent of the time. A 3-load RATA is required at least once in
every period of five consecutive calendar years and whenever a flow monitor is re-linearized.
[FR Doc. C9-8939 Filed 7-9-99; 8:45 am]
BILLING CODE 1505-01-D