Start Preamble
Start Printed Page 60553
AGENCIES:
Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).
ACTION:
Final rule.
SUMMARY:
The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) have agreed on a final rule amending the Federal Acquisition Regulation (FAR) to implement the requirements of 10 U.S.C. 2306a(a)(7) and 41 U.S.C. 254b(a)(7). These statutes require review of the Truth in Negotiations Act threshold every 5 years, starting October 1, 1995.
DATES:
Effective Date: October 11, 2000.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
The FAR Secretariat, Room 4035, GS Building, Washington, DC, 20405, (202) 501-4755, for information pertaining to status or publication schedules. For clarification of content, contact Mr. Jeremy Olson at (202) 501-3221. Please cite FAC 97-20, FAR case 2000-300.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
A. Background
This final rule amends FAR 15.403-4 to implement the requirements of 10 U.S.C. 2306a(a)(7) and 41 U.S.C. 254b(a)(7). These statutes require review of the Truth in Negotiations Act threshold every 5 years, starting October 1, 1995. The increase of $50,000 is based on escalation of 10.22 percent from 1994 to 2000, calculated using the gross domestic product deflators from the fiscal year 2001 budget.
DoD, GSA, and NASA published a proposed rule in the Federal Register at 65 FR 41267, July 3, 2000. Two respondents submitted public comments. The Councils considered all public comments in formulation of the final rule. This final rule is the same as the proposed rule.
This is not a significant regulatory action, and therefore, was not subject to review under Section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
B. Regulatory Flexibility Act
The Department of Defense, the General Services Administration, and the National Aeronautics and Space Administration certify that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because most contracts and subcontracts with small entities do not require the submission of cost or pricing data.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the changes do not significantly change the existing information collection requirements that have been approved by the Office of Management and Budget under 44 U.S.C. 3501, et seq., under OMB Clearance Number 9000-0045.
Start List of SubjectsList of Subjects in 48 CFR Part 15
- Government procurement
Dated: October 3, 2000.
Al Matera,
Acting Director, Federal Acquisition Policy Division.
Therefore, DoD, GSA, and NASA amend 48 CFR part 15 as set forth below:
End Amendment Part Start PartPART 15—CONTRACTING BY NEGOTIATION
1. The authority citation for 48 CFR part 15 continues to read as follows:
End Part Start Amendment Part2. Amend section 15.403-4 by revising paragraph (a)(1) to read as follows:
End Amendment PartRequiring cost or pricing data (10 U.S.C. 2306a and 41 U.S.C. 254b).(a)(1) The contracting officer must obtain cost or pricing data only if the contracting officer concludes that none of the exceptions in 15.403-1(b) applies. However, if the contracting officer has sufficient information available to determine price reasonableness, then the contracting officer should consider requesting a waiver under the exception at 15.403-1(b)(4). The threshold for obtaining cost or pricing data is $550,000. Unless an exception applies, cost or pricing data are required before accomplishing any of the following actions expected to exceed the current threshold or, for existing contracts, the threshold specified in the contract:
(i) The award of any negotiated contract (except for undefinitized actions such as letter contracts).
(ii) The award of a subcontract at any tier, if the contractor and each higher-tier subcontractor were required to submit cost or pricing data (but see waivers at 15.403-1(c)(4)).
(iii) The modification of any sealed bid or negotiated contract (whether or not cost or pricing data were initially required) or any subcontract covered by paragraph (a)(1)(ii) of this subsection. Price adjustment amounts must consider both increases and decreases (e.g., a $200,000 modification resulting from a reduction of $400,000 and an increase of $200,000 is a pricing adjustment exceeding $550,000). This requirement does not apply when unrelated and separately priced changes for which cost or pricing data would not otherwise be required are included for administrative convenience in the same modification. Negotiated final pricing actions (such as termination settlements and total final price agreements for fixed-price incentive and redeterminable contracts) are contract modifications requiring cost or pricing data if—
(A) The total final price agreement for such settlements or agreements exceeds the pertinent threshold set forth at paragraph (a)(1) of this subsection; or (B) The partial termination settlement plus the estimate to complete the continued portion of the contract exceeds the pertinent threshold set forth at paragraph (a)(1) of this subsection (see 49.105(c)(15)).
* * * * *[FR Doc. 00-25875 Filed 10-10-00; 8:45 am]
BILLING CODE 6820-EP-P
Document Information
- Published:
- 10/11/2000
- Department:
- National Aeronautics and Space Administration
- Entry Type:
- Rule
- Action:
- Final rule.
- Document Number:
- 00-25875
- Pages:
- 60553-60553 (1 pages)
- Docket Numbers:
- FAC 97-20, FAR Case 2000-300, Item II
- RINs:
- 9000-AI83
- Topics:
- Government procurement
- PDF File:
- 00-25875.pdf
- CFR: (1)
- 48 CFR 15.403-4