    SUMMARY:

    The Environmental Protection Agency (EPA or “Agency”) is taking final action to determine that the deficiency that formed the basis for a disapproval of the contingency measures submitted for the San Joaquin Valley nonattainment area for the 1997 fine particulate matter (PM2.5) national ambient air quality standards (NAAQS) has been corrected. The effect of this action is to permanently stop the sanctions clocks triggered by the disapproval.

    DATES:

    This final rule is effective December 14, 2017.

    ADDRESSES:

    The EPA has established a docket for this action under Docket No. EPA-R09-OAR-2017-0580. All documents in the docket are listed on the https://www.regulations.gov website. Although listed on the website, some information is not publicly available, e.g., Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the internet and will be publicly available only in hard copy form. Publicly available docket materials are available through https://www.regulations.gov,, or please contact the person identified in the FOR FURTHER INFORMATION CONTACT section for additional availability information.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Rory Mays, EPA Region IX, (415) 972-3227, mays.rory@epa.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Throughout this document, whenever “we,” “us,” or “our” is used, we mean the EPA.

    Table of Contents

    I. Proposed Action

    II. Public Comments and EPA Responses

    III. Final Action

    IV. Statutory and Executive Order Reviews

    I. Proposed Action

    On October 23, 2017 (82 FR 48944) (herein “proposed rule”), we proposed to determine that the deficiency that formed the basis for a disapproval of the contingency measures submitted for the San Joaquin Valley [1] nonattainment area for the 1997 PM2.5 NAAQS (“1997 PM2.5 standards”) [2] has been corrected. We did so based on the Agency's approval of California regulations establishing standards and other requirements relating to the control of emissions from new on-road and new and in-use off-road vehicles and engines (herein, “waiver measures”) into the California State Implementation Plan (SIP), and a finding that the purposes of the contingency measure requirement, as applicable to the San Joaquin Valley based on its initial designation as a nonattainment area for the 1997 PM2.5 standards, have been fulfilled.

    Our proposed rule provides a detailed background section that describes the relevant NAAQS, area designations, the relevant SIP submittal requirements, and the relevant SIP revisions submitted and either approved or disapproved by the EPA under Clean Air Act (CAA or “Act”) section 110.

    In short, under CAA section 172(c)(9), SIPs for areas designated as nonattainment for a NAAQS must be revised to provide for the implementation of specific measures (“contingency measures”) to take effect if the area fails to make reasonable further progress (RFP) or fails to attain by the applicable attainment date. The EPA disapproved the contingency measure element of a set of SIP revisions collectively referred to as the “2008 PM2.5 Plan,” which was developed and submitted by California to address SIP requirements triggered by the designation of the San Joaquin Valley as a nonattainment area for the 1997 PM2.5 NAAQS.[3]

    In response to the EPA's disapproval of the contingency measure element of the 2008 PM2.5 Plan, California submitted a SIP revision referred to as the “2013 Contingency Measure SIP.” The 2013 Contingency Measure SIP primarily relied upon California's waiver measures, i.e., California mobile source regulations that had been waived or authorized by the EPA under CAA section 209, to provide post-attainment year emissions reductions equivalent to one year's worth of RFP.[4]

    The EPA approved,[5] but later disapproved,[6] the 2013 Contingency Measure SIP in the wake of a court decision [7] that undermined the basis for the EPA's approval. The court decision at issue held that waiver measures must be approved into the SIP if California relies upon them to meet CAA SIP requirements, thereby rejecting the EPA's longstanding practice allowing California SIP credit for waiver measures notwithstanding their absence from the SIP. Our disapproval of the 2013 Contingency Measure SIP became effective on June 13, 2016, and started a sanctions clock for imposition of offset sanctions 18 months after June 13, 2016, and highway sanctions 6 months later, pursuant to CAA section 179 and our regulations at 40 CFR 52.31, unless the State submits and the EPA approves, prior to the implementation of the sanctions, a SIP submission that corrects the deficiencies identified in the disapproval action.[8]

    Since the disapproval of the 2013 Contingency Measure SIP, we have approved the waiver measures as Start Printed Page 58748revisions to the California SIP,[9] and our approval of them as part of the SIP addresses the specific deficiency that formed the basis of our May 12, 2016 disapproval of the 2013 Contingency Measure SIP. Moreover, since the 2014 attainment year (for the 2008 PM2.5 Plan), the waiver measures and related vehicle fleet turnover have achieved post-attainment year emission reductions equivalent to approximately one year's worth of RFP as calculated for the 2008 PM2.5 Plan. The waiver measures have thus provided for sufficient progress towards attainment of the 1997 PM2.5 standards while a new attainment plan is being prepared.[10] Therefore, in our proposed rule we found that the purposes of the contingency measure requirement, as applicable to the San Joaquin Valley based on the area's designation in 2005 for the 1997 PM2.5 NAAQS, have been fulfilled, and we proposed to determine that the deficiency that formed the basis for the disapproval of the 2013 Contingency Measure SIP has been corrected. We are finalizing this determination in today's action.

    For a more detailed discussion of the regulatory context and rationale for our action, please see the proposed rule.

    II. Public Comments and EPA Responses

    The EPA's proposed action provided a 30-day public comment period which ended on November 22, 2017. During this period, we received no comments.

    III. Final Action

    For the reasons given in our proposed rule and summarized herein, the EPA is making a final determination that the deficiency that formed the basis of our disapproval of the 2013 Contingency Measure SIP for the San Joaquin Valley for the 1997 PM2.5 NAAQS has been corrected by the approval of the waiver measures as a revision to the California SIP and the finding that the waiver measures have achieved post-2014 attainment year emissions reductions sufficient to fulfill the purposes of the contingency measure requirement in CAA section 172(c)(9). This final determination permanently stops the sanctions clocks triggered by our disapproval of the 2013 Contingency Measure SIP. See CAA section 179(a) and 40 CFR 52.31(d)(5).

    In accordance with 5 U.S.C. 553(d), the EPA finds there is good cause for this action to become effective immediately upon publication. This is because a delayed effective date is unnecessary due to the nature of the determination made herein that a deficiency in a previous SIP approval has been corrected. The immediate effective date for this action is authorized under both 5 U.S.C. 553(d)(1), which provides that rulemaking actions may become effective less than 30 days after publication if the rule “grants or recognizes an exemption or relieves a restriction,” and section 553(d)(3), which allows an effective date less than 30 days after publication “as otherwise provided by the agency for good cause found and published with the rule.” The purpose of the 30-day waiting period prescribed in section 553(d) is to give affected parties a reasonable time to adjust their behavior and prepare before the final rule takes effect. This rulemaking, however, does not create any new regulatory requirement such that affected parties would need time to prepare before the rule takes effect. Rather, today's rule makes a determination that has the effect of permanently stopping sanctions clocks triggered by a previous SIP disapproval action. For these reasons, the EPA finds good cause under 5 U.S.C. 553(d)(3) for this action to become effective on the date of publication of this action.

    IV. Statutory and Executive Order Reviews

    This action is a determination that a deficiency that is the basis for sanctions has been corrected and imposes no additional requirements. For that reason, this action:

    • Is not a “significant regulatory action” subject to review by the Office of Management and Budget under Executive Order 12866 (58 FR 51735, October 4, 1993);
    • Is not an Executive Order 13771 (82 FR 9339, February 2, 2017) regulatory action because SIP approvals are exempted under Executive Order 12866;
    • Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
    • Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.);
    • Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);
    • Does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999);
    • Is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);
    • Is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001);
    • Is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and
    • Does not provide the EPA with the discretionary authority to address disproportionate human health or environmental effects with practical, appropriate, and legally permissible methods under Executive Order 12898 (59 FR 7629, February 16, 1994).

    In addition, this action does not have Tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), because it will not have a substantial direct effect on one or more Indian tribes, on the relationship between the federal government and Indian tribes, or on the distribution of power and responsibilities between the federal government and Indian tribes, as specified by Executive Order 13175 (65 FR 67249, November 9, 2000).

    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. The EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a “major rule” as defined by 5 U.S.C. 804(2).

    Under section 307(b)(1) of the Clean Air Act, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by February 12, 2018. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this rule for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not Start Printed Page 58749postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements (see section 307(b)(2)).

    Start List of Subjects

    List of Subjects in 40 CFR Part 52

    • Environmental protection
    • Air pollution control
    • Incorporation by reference
    • Intergovernmental relations
    • Nitrogen oxides
    • Sulfur oxides
    • Particulate matter
    End List of Subjects Start Authority

    Authority: 42 U.S.C. 7401 et seq.

    End Authority Start Signature

    Dated: December 4, 2017.

    Alexis Strauss,

    Acting Regional Administrator, Region IX.

    End Signature End Supplemental Information

    Footnotes

    1.  The San Joaquin Valley PM2.5 nonattainment area is located in the southern half of California's central valley and includes all of San Joaquin, Stanislaus, Merced, Madera, Fresno, Tulare, and Kings counties, and the valley portion of Kern County. See 40 CFR 81.305.

    Back to Citation

    2.  The EPA promulgated the 1997 PM2.5 NAAQS at 62 FR 38652 (July 18, 1997).

    Back to Citation

    3.  76 FR 69896 (November 9, 2011) (final action on the 2008 PM2.5 Plan).

    Back to Citation

    4.  One year's worth of RFP is the yardstick the EPA has cited historically as the approximate quantity of emissions reductions that contingency measures should provide to satisfy CAA section 172(c)(9). See, e.g., 81 FR 58010, at 58066 (August 24, 2016) (final rule implementing the PM2.5 NAAQS).

    Back to Citation

    5.  79 FR 29327 (May 22, 2014) (final action approving the 2013 Contingency Measure SIP).

    Back to Citation

    6.  81 FR 29498 (May 12, 2016) (final action disapproving the 2013 Contingency Measure SIP).

    Back to Citation

    7.  Committee for a Better Arvin v. EPA, 786 F.3d 1169 (9th Cir. 2015) (“Committee for a Better Arvin”) (partially granting and partially denying petition for review).

    Back to Citation

    8.  The offset sanction applies to New Source Review (NSR) permits for new major stationary sources or major modifications proposed in a nonattainment area, and it increases the ratio of emissions reductions (i.e., offsets) to increased emissions from the new or modified source, which must be obtained to receive an NSR permit, to 2 to 1. The highway sanction prohibits, with certain exceptions, the U.S. Department of Transportation from approving or funding transportation projects in a nonattainment area.

    Back to Citation

    9.  81 FR 39424 (June 16, 2016) and 82 FR 14446 (March 21, 2017).

    Back to Citation

    10.  In response to the EPA's determination of failure to attain the 1997 PM2.5 NAAQS, 81 FR 84481 (November 23, 2016), the San Joaquin Valley Unified Air Pollution Control District and California Air Resources Board are preparing a new attainment plan with contingency measures for the 1997 PM2.5 NAAQS for the San Joaquin Valley.

    Back to Citation

    [FR Doc. 2017-26899 Filed 12-13-17; 8:45 am]

    BILLING CODE 6560-50-P

Document Information

Effective Date:
12/14/2017
Published:
12/14/2017
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Final rule.
Document Number:
2017-26899
Dates:
This final rule is effective December 14, 2017.
Pages:
58747-58749 (3 pages)
Docket Numbers:
EPA-R09-OAR-2017-0580, FRL-9972-02-Region 9
Topics:
Air pollution control, Environmental protection, Incorporation by reference, Intergovernmental relations, Nitrogen oxides, Particulate matter, Sulfur oxides
PDF File:
2017-26899.pdf
Supporting Documents:
» Docket Index for final determination for San Joaquin Valley 1997 PM2.5 NAAQS contingency measures
» 2016-11-23 Final SJV PM2.5 Finding of Failure to Attain (81 FR 84481)
» 2015-06-15 Medical Advocates v EPA remand order (9th Cir. 14-72219)
» 2015-05-20 Decision in Committee for Better Arvin v EPA (9th Cir. 11-73924)
» 2017-09-18 CEPAM 2016 SIP SET SJV NOx 2014-2017
» 2017-09-18 CEPAM 2016 SIP SET SJV Direct PM2.5 2014-2017
» 2013-06-20 SJV Quantification of Contingency Reductions
» 2011-05-18 CARB Progress Report Supplement Letter and Attachments
» 2011-05-18 CARB Progress Report Submittal Enclosure 1
» 2011-05-18 CARB Progress Report Submittal Letter
CFR: (1)
40 CFR 52