2019-06250. Defense Federal Acquisition Regulation Supplement: Consent To Subcontract (DFARS Case 2018-D065)  

  • Start Preamble

    AGENCY:

    Defense Acquisition Regulation System, Department of Defense (DoD).

    ACTION:

    Final rule.

    SUMMARY:

    DoD is issuing a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to implement a section of the National Defense Authorization Act for Fiscal Year 2019 to require, for DoD contracts with contractors that have approved purchasing systems, that a contracting officer have written approval from the program manager prior to withholding a consent to subcontract.

    DATES:

    Effective April 1, 2019.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ms. Kimberly Bass, telephone 571-372-6174.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    DoD is issuing a final rule to amend the DFARS to implement section 824 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2019, which amends section 893 of the NDAA for FY 2011 (Pub. L. 111-383) regarding consent to subcontract requirements. Specifically, section 893 requires contracting officers to have written approval from the program manager prior to withholding consent to subcontract for DoD contracts with contractors that have approved purchasing systems, as defined in Federal Acquisition Regulation (FAR) 44.101.

    II. Discussion and Analysis

    This rule proposes to add a new paragraph (a) at DFARS 244.201-1 to include the new requirement for contracting officers to obtain written approval from the program manager prior to withholding a consent to subcontract for DoD contracts with contractors that have an approved purchasing system. Conforming changes are made to the existing text at 244.201-1, by renumbering the existing text as paragraph (S-70).Start Printed Page 12141

    III. Applicability to Contracts at or Below the Simplified Acquisition Threshold and for Commercial Items, Including Commercially Available Off-the-Shelf Items

    This rule does not create any new provisions or clauses or impact any existing provisions or clauses. The rule only impacts the internal operating procedures of the agency. As such, the rule does not impose any new requirements on contracts at or below the simplified acquisition threshold or for commercial items, including commercially available off-the-shelf items.

    IV. Publication of This Final Rule for Public Comment Is Not Required by Statute

    The statute that applies to the publication of the FAR is 41 U.S.C. 1707 entitled “Publication of Proposed Regulations.” Paragraph (a)(1) of the statute requires that a procurement policy, regulation, procedure, or form (including an amendment or modification thereof) must be published for public comment if it relates to the expenditure of appropriated funds, and has either a significant effect beyond the internal operating procedures of the agency issuing the policy, regulation, procedure, or form, or has a significant cost or administrative impact on contractors or offerors. This final rule is not required to be published for public comment, because this rule merely establishes internal Government procedures for contracting officers to obtain written approval from the program manager prior to withholding a consent to subcontract on a contract with a contractor with an approved purchasing system.

    V. Executive Order 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, or reducing costs, or harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    VI. Executive Order 13771

    This rule is not an E.O. 13771 regulatory action, because this rule is not significant under E.O. 12866.

    VII. Regulatory Flexibility Act

    Because a notice of proposed rulemaking and an opportunity for public comment are not required to be given for this rule under 41 U.S.C. 1707(a)(1) (see section IV. of this preamble), the analytical requirement of the Regulatory Flexibility Act (5 U.S.C. 601 et seq.) are not applicable. Accordingly, no regulatory flexibility analysis is required, and none has been prepared.

    VIII. Paperwork Reduction Act

    The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

    Start List of Subjects

    List of Subjects in 48 CFR Part 244

    • Government procurement
    End List of Subjects Start Signature

    Jennifer Lee Hawes,

    Regulatory Control Officer, Defense Acquisition Regulations System.

    End Signature

    Therefore, 48 CFR part 244 is amended as follows:

    Start Part

    PART 244—SUBCONTRACTING POLICIES AND PROCEDURES

    End Part Start Amendment Part

    1. The authority citation for part 244 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 41 U.S.C. 1303 and 48 CFR chapter 1.

    End Authority Start Amendment Part

    2. Amend section 244.201-1 by—

    End Amendment Part Start Amendment Part

    a. Designating the existing text as paragraph (S-70); and

    End Amendment Part Start Amendment Part

    b. Adding a paragraph (a) to start the section.

    End Amendment Part

    The addition reads as follows:

    Consent requirements.

    (a) In accordance with section 824 of the National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232), notwithstanding the requirements in FAR 44.201-1(a), the contracting officer shall not withhold consent to subcontract without the written approval of the program manager, or comparable requiring activity official exercising program management responsibilities, if the contractor has an approved purchasing system, as defined in FAR 44.101.

    * * * * *
    End Supplemental Information

    [FR Doc. 2019-06250 Filed 3-29-19; 8:45 am]

    BILLING CODE 5006-01-P

Document Information

Effective Date:
4/1/2019
Published:
04/01/2019
Department:
Defense Acquisition Regulations System
Entry Type:
Rule
Action:
Final rule.
Document Number:
2019-06250
Dates:
Effective April 1, 2019.
Pages:
12140-12141 (2 pages)
Docket Numbers:
Docket DARS-2019-0006
RINs:
0750-AK24: Consent to Subcontract and Subcontract Price (DFARS Case 2018-D065)
RIN Links:
https://www.federalregister.gov/regulations/0750-AK24/consent-to-subcontract-and-subcontract-price-dfars-case-2018-d065-
Topics:
Government procurement
PDF File:
2019-06250.pdf
CFR: (1)
48 CFR 244.201-1