2021-02356. Safety Zone; Power Plant Demolition; Grand River, Grand Haven, MI  

  • Start Preamble

    AGENCY:

    Coast Guard, DHS.

    ACTION:

    Temporary final rule.

    SUMMARY:

    The Coast Guard is establishing a temporary safety zone for all navigable waters within 1400 feet of a demolition site near the eastern bank of the Grand River in Grand Haven, MI. The safety zone is needed to protect personnel, vessels, and the marine environment from potential hazards created by the controlled implosion of the J.B. Sims power plant. Entry of vessels or persons into this zone is prohibited unless specifically authorized by the Captain of the Port Lake Michigan or a designated representative.

    DATES:

    This rule is effective from 9:30 a.m. on February 5 through 10:30 a.m. on February 19, 2021. The rule will be enforced from 9:30 a.m. to 10:30 a.m. on both February 5 and February 19, 2021.

    ADDRESSES:

    To view documents mentioned in this preamble as being available in the docket, go to https://www.regulations.gov,, type USCG-2021-0035 in the “SEARCH” box, and click “SEARCH.” Click on Open Docket Folder on the line associated with this rule.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    If you have questions on this rule, call or email Chief Petty Officer Jeromy Sherrill, Sector Lake Michigan Waterways Management Division, U.S. Coast Guard; telephone 414-747-7148, email Jeromy.N.Sherrill@uscg.mil.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Table of Abbreviations

    CFR Code of Federal Regulations

    DHS Department of Homeland Security

    FR Federal Register

    NPRM Notice of proposed rulemaking

    § Section

    U.S.C. United States Code

    II. Background Information and Regulatory History

    The Coast Guard is issuing this temporary rule without prior notice and opportunity to comment pursuant to authority under section 4(a) of the Administrative Procedure Act (APA) (5 U.S.C. 553(b)). This provision authorizes an agency to issue a rule without prior notice and opportunity to comment when the agency for good cause finds that those procedures are “impracticable, unnecessary, or contrary to the public interest.” Under 5 U.S.C. 553(b)(B), the Coast Guard finds that good cause exists for not publishing a notice of proposed rulemaking (NPRM) with respect to this rule because the Coast Guard not made aware of the intended demolition project until January 12, 2021, and immediate action is needed to mitigate potential safety hazards associated with the demolition process. Delaying the effective date of this rule to wait for a comment period to run would be impracticable and contrary to public interest by inhibiting the Coast Guard's ability to protect against the known and anticipated hazards.

    Under 5 U.S.C. 553(d)(3), the Coast Guard finds that good cause exists for making this rule effective less than 30 days after publication in the Federal Register. For the same reasons discussed in the preceding paragraph, waiting for a 30-day notice period to elapse would be impracticable because immediate action is needed to mitigate potential safety hazards associated with the controlled implosion of portion of the power plant adjancent to the Grand River.

    III. Legal Authority and Need for Rule

    The Coast Guard is issuing this rule under authority in 46 U.S.C. 70034 (previously 33 U.S.C. 1231). The Captain of the Port (COTP) Lake Michigan has determined that potential safety hazards associated with the demolition of the J.B. Sims power plant Start Printed Page 8141will be a safety concern for anyone on navigable waters within 1400 feet of the demolition site. This work is scheduled to take place on February 5 and February 19, 2021, on the Grand River in Grand Haven, MI. This rule is needed to protect personnel, vessels, and the marine environment in the navigable waters within the safety zone while the structures are imploded.

    IV. Discussion of the Rule

    This rule establishes a safety zone from 9:30 a.m. through 10:30 a.m. on February 5 and February 19, 2021. The safety zone will cover all navigable waters of the Grand River in Grand Haven, MI, within 1400 feet of the blast area located on the eastern bank of the river at coordinates 43.0705000° N, 086.2346667°. The date and time of the enforcement period will be announced by the COTP Lake Michigan by Broadcast Notice to Mariners. The duration of the zone is intended to protect personnel, vessels, and the marine environment in these navigable waters during the implosion of structures near the river. Entry into, transiting, or anchoring within the safety zone is prohibited unless authorized by the COTP or a designated representative.

    V. Regulatory Analyses

    We developed this rule after considering numerous statutes and Executive orders related to rulemaking. Below we summarize our analyses based on a number of these statutes and Executive orders, and we discuss First Amendment rights of protestors.

    A. Regulatory Planning and Review

    Executive Orders 12866 and 13563 direct agencies to assess the costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits. Executive Order 13771 directs agencies to control regulatory costs through a budgeting process. This rule has not been designated a “significant regulatory action,” under Executive Order 12866. Accordingly, this rule has not been reviewed by the Office of Management and Budget (OMB), and pursuant to OMB guidance, it is exempt from the requirements of Executive Order 13771.

    This regulatory action determination is based on the characteristics of the safety zone. The safety zone created by this rule will be relatively small and is designed to minimize its impact on navigable waters. This rule will prohibit entry into certain navigable waters of the Grand River in Grand Haven, MI, and is not anticipated to exceed two 2-hour periods in duration. Thus, restrictions on vessel movement within that particular area are expected to be minimal. Under certain conditions, moreover, vessels may still transit through the safety zone when permitted by the COTP Lake Michigan.

    B. Impact on Small Entities

    The Regulatory Flexibility Act of 1980, 5 U.S.C. 601-612, as amended, requires Federal agencies to consider the potential impact of regulations on small entities during rulemaking. The term “small entities” comprises small businesses, not-for-profit organizations that are independently owned and operated and are not dominant in their fields, and governmental jurisdictions with populations of less than 50,000. The Coast Guard certifies under 5 U.S.C. 605(b) that this rule will not have a significant economic impact on a substantial number of small entities.

    While some owners or operators of vessels intending to transit the safety zone may be small entities, for the reasons stated in section V.A above, this rule will not have a significant economic impact on any vessel owner or operator.

    Under section 213(a) of the Small Business Regulatory Enforcement Fairness Act of 1996 (Pub. L. 104-121), we want to assist small entities in understanding this rule. If the rule would affect your small business, organization, or governmental jurisdiction and you have questions concerning its provisions or options for compliance, please call or email the person listed in the FOR FURTHER INFORMATION CONTACT section.

    Small businesses may send comments on the actions of federal employees who enforce, or otherwise determine compliance with, federal regulations to the Small Business and Agriculture Regulatory Enforcement Ombudsman and the Regional Small Business Regulatory Fairness Boards. The Ombudsman evaluates these actions annually and rates each agency's responsiveness to small business. If you wish to comment on actions by employees of the Coast Guard, call 1-888-REG-FAIR (1-888-734-3247). The Coast Guard will not retaliate against small entities that question or complain about this rule or any policy or action of the Coast Guard.

    C. Collection of Information

    This rule will not call for a new collection of information under the Paperwork Reduction Act of 1995 (44 U.S.C. 3501-3520).

    D. Federalism and Indian Tribal Governments

    A rule has implications for federalism under Executive Order 13132, Federalism, if it has a substantial direct effect on the States, on the relationship between the National Government and the States, or on the distribution of power and responsibilities among the various levels of government. We have analyzed this rule under that Order and have determined that it is consistent with the fundamental federalism principles and preemption requirements described in Executive Order 13132.

    Also, this rule does not have tribal implications under Executive Order 13175, Consultation and Coordination with Indian Tribal Governments, because it does not have a substantial direct effect on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes. If you believe this rule has implications for federalism or Indian tribes, please contact the person listed in the FOR FURTHER INFORMATION CONTACT section above.

    E. Unfunded Mandates Reform Act

    The Unfunded Mandates Reform Act of 1995 (2 U.S.C. 1531-1538) requires Federal agencies to assess the effects of their discretionary regulatory actions. In particular, the Act addresses actions that may result in the expenditure by a state, local, or tribal government, in the aggregate, or by the private sector of $100,000,000 (adjusted for inflation) or more in any one year. Though this rule will not result in such an expenditure, we do discuss the effects of this rule elsewhere in this preamble.

    F. Environment

    We have analyzed this rule under Department of Homeland Security Directive 023-01, Rev. 1, associated implementing instructions, and Environmental Planning COMDTINST 5090.1 (series), which guide the Coast Guard in complying with the National Environmental Policy Act of 1969 (42 U.S.C. 4321-4370f), and have determined that this action is one of a category of actions that do not individually or cumulatively have a significant effect on the human environment. This rule involves a safety zone lasting for a total of 2 hours that will prohibit entry within 1400 feet of a blast area near the eastern bank of the Grand River for the demolition of sections of a power plant. It is categorically excluded from further Start Printed Page 8142review under paragraph L60(a) of Appendix A, Table 1 of DHS Instruction Manual 023-01-001-01, Rev. 1. A Record of Environmental Consideration supporting this determination is available in the docket. For instructions on locating the docket, see the ADDRESSES section of this preamble.

    G. Protest Activities

    The Coast Guard respects the First Amendment rights of protesters. Protesters are asked to call or email the person listed in the FOR FURTHER INFORMATION CONTACT section to coordinate protest activities so that your message can be received without jeopardizing the safety or security of people, places, or vessels.

    Start List of Subjects

    List of Subjects in 33 CFR Part 165

    • Harbors
    • Marine safety
    • Navigation (water)
    • Reporting and recordkeeping requirements
    • Security measures
    • Waterways
    End List of Subjects

    For the reasons discussed in the preamble, the Coast Guard amends 33 CFR part 165 as follows:

    Start Part

    PART 165—REGULATED NAVIGATION AREAS AND LIMITED ACCESS AREAS

    End Part Start Amendment Part

    1. The authority citation for part 165 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 46 U.S.C. 70034, 70051; 33 CFR 1.05-1, 6.04-1, 6.04-6, and 160.5; Department of Homeland Security Delegation No. 0170.1.

    End Authority Start Amendment Part

    2. Add § 165.T09-0035 to read as follows:

    End Amendment Part
    Safety Zone; Power Plant Demolition; Grand River, Grand Haven, MI.

    (a) Location. All navigable waters of the Grand River within 1400 feet of the blast area on the eastern bank of the river at coordinates 43.0705000° N, 086.2346667°.

    (b) Enforcement period. The regulated area described in paragraph (a) is effective from 9:30 a.m. through 10:30 a.m. on February 5 and February 19, 2021.

    (c) Regulations. (1) In accordance with the general regulations in section § 165.23, entry into, transiting, or anchoring within this safety zone is prohibited unless authorized by the Captain of the Port Lake Michigan (COTP) or a designated representative.

    (2) This safety zone is closed to all vessel traffic, except as may be permitted by the COTP or a designated representative.

    (3) The “designated representative” of the COTP is any Coast Guard commissioned, warrant, or petty officer who has been designated by the COTP to act on his or her behalf.

    (4) Persons and vessel operators desiring to enter or operate within the safety zone must contact the COTP or an on-scene representative to obtain permission to do so. The COTP or an on-scene representative may be contacted via VHF Channel 16. Vessel operators given permission to enter or operate in the safety zone must comply with all directions given to them by the COTP or an on-scene representative.

    Start Signature

    Dated: February 1, 2021.

    D.P. Montoro,

    Captain, U.S. Coast Guard, Captain of the Port Lake Michigan.

    End Signature End Supplemental Information

    [FR Doc. 2021-02356 Filed 2-3-21; 8:45 am]

    BILLING CODE 9110-04-P

Document Information

Effective Date:
2/19/2021
Published:
02/04/2021
Department:
Coast Guard
Entry Type:
Rule
Action:
Temporary final rule.
Document Number:
2021-02356
Dates:
This rule is effective from 9:30 a.m. on February 5 through 10:30 a.m. on February 19, 2021. The rule will be enforced from 9:30 a.m. to 10:30 a.m. on both February 5 and February 19, 2021.
Pages:
8140-8142 (3 pages)
Docket Numbers:
Docket Number USCG-2021-0035
RINs:
1625-AA00: Safety Zone Regulations
RIN Links:
https://www.federalregister.gov/regulations/1625-AA00/safety-zone-regulations
Topics:
Harbors, Marine safety, Navigation (water), Reporting and recordkeeping requirements, Security measures, Waterways
PDF File:
2021-02356.pdf
Supporting Documents:
» DHS Record of Environmental Consideration (REC) for Categorically Excluded Actions under NEPA
» Safety Zone: Power Plant Demolition; Grand River, Grand Haven, MI
CFR: (1)
33 CFR 165.T09-0035