2022-21653. Air Plan Approval and Air Quality Designation; GA; Redesignation of the Atlanta, Georgia 2015 8-Hour Ozone Nonattainment Area to Attainment  

  • Start Preamble

    AGENCY:

    Environmental Protection Agency (EPA).

    ACTION:

    Final rule.

    SUMMARY:

    On February 28, 2022, the State of Georgia, through the Georgia Environmental Protection Division (GA EPD) of the Department of Natural Resources, submitted a request for the Environmental Protection Agency (EPA) to redesignate the Atlanta, Georgia 2015 8-hour ozone nonattainment area (hereinafter referred to as the “Atlanta Area” or “Area”) to attainment for the 2015 8-hour ozone National Ambient Air Quality Standards (NAAQS or standards) and to approve a State Implementation Plan (SIP) revision containing a maintenance plan for the Area. EPA is approving the State's plan for maintaining attainment of the 2015 8-hour ozone standard in the Area, including the motor vehicle emission budgets (MVEBs) for nitrogen oxides (NOX) and volatile organic compounds (VOC) for the years of 2018 and 2033 for the Area, incorporating the maintenance plan into the SIP, and redesignating the Area to attainment for the 2015 8-hour ozone NAAQS. EPA is also notifying the public of the status of EPA's adequacy determination for the MVEBs for the Area.

    DATES:

    This rule is effective November 16, 2022.

    ADDRESSES:

    EPA has established a docket for this action under Docket Identification No. EPA-R04-OAR-2022-0290. All documents in the docket are listed on the www.regulations.gov website. Although listed in the index, some information may not be publicly available, i.e., Confidential Business Information or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through www.regulations.gov or in hard copy at the Air Regulatory Management Section, Air Planning and Implementation Branch, Air and Radiation Division, U.S. Environmental Protection Agency, Start Printed Page 62734 Region 4, 61 Forsyth Street SW, Atlanta, Georgia 30303-8960. EPA requests that if at all possible, you contact the person listed in the FOR FURTHER INFORMATION CONTACT section to schedule your inspection. The Regional Office's official hours of business are Monday through Friday 8:30 a.m. to 4:30 p.m., excluding Federal holidays.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Jane Spann, Air Regulatory Management Section, Air Planning and Implementation Branch, Air and Radiation Division, Region 4, U.S. Environmental Protection Agency, 61 Forsyth Street SW, Atlanta, Georgia 30303-8960. The telephone number is (404) 562-9029. Ms. Spann can also be reached via electronic mail at spann.jane@epa.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. This Action

    EPA is taking the following separate but related actions: (1) Approving Georgia's plan for maintaining the 2015 ozone NAAQS (maintenance plan), including the associated MVEBs for the Atlanta Area, and incorporating the plan into the SIP, and (2) redesignating the Atlanta Area to attainment for the 2015 8-hour ozone NAAQS. EPA is also notifying the public of the status of EPA's adequacy determination for the MVEBs for the Atlanta Area. The Atlanta Area consists of Bartow, Clayton, Cobb, DeKalb, Fulton, Gwinnett, and Henry Counties in Georgia.

    EPA is taking final action to approve Georgia's maintenance plan for the Atlanta Area as meeting the requirements of section 175A, such approval being one of the Clean Air Act (CAA or Act) criteria for redesignation to attainment status, and incorporate it into the SIP. The maintenance plan is designed to keep the Atlanta Area in attainment of the 2015 8-hour ozone NAAQS through 2033. The maintenance plan includes 2018 and 2033 MVEBs for NOX and VOC for the Atlanta Area for transportation conformity purposes. EPA is approving these MVEBs and incorporating them into the SIP. EPA is also taking final action to determine that the Atlanta Area has met the requirements for redesignation under section 107(d)(3)(E) of the CAA.

    EPA is also notifying the public of the status of EPA's adequacy process for the MVEBs for the Atlanta Area. The Adequacy comment period began on February 11, 2022, with EPA's posting of the availability of Georgia's submission on EPA's Adequacy website ( https://www.epa.gov/​state-and-local-transportation/​state-implementation-plans-sip-submissions-currently-under-epa). The Adequacy comment period for these MVEBs closed on March 15, 2022. No comments, adverse or otherwise, were received during the Adequacy comment period.

    In summary, this final rulemaking is in response to Georgia's February 28, 2022, redesignation request and associated SIP submission that addresses the specific issues summarized above and the necessary elements described in section 107(d)(3)(E) of the CAA for redesignation of the Atlanta Area to attainment for the 2015 8-hour ozone NAAQS.

    II. Background

    Effective August 3, 2018, EPA designated areas as unclassifiable/attainment or nonattainment for the 2015 8-hour ozone NAAQS that was promulgated on October 1, 2015. See80 FR 65292 (October 26, 2015). The Atlanta Area was designated as nonattainment for the 2015 8-hour ozone NAAQS and classified as a marginal nonattainment area. 1 See83 FR 25776 (June 4, 2018). On February 28, 2022, Georgia requested that EPA redesignate the Atlanta Area to attainment for the 2015 8-hour ozone NAAQS and submitted a SIP revision containing the State's plan for maintaining attainment of the 2015 8-hour ozone standard in the Area, including 2018 and 2033 MVEBs for NOX and VOC for the Atlanta Area.

    In a notice of proposed rulemaking (NPRM) published on August 26, 2022, see87 FR 52487, EPA proposed to approve the maintenance plan, including the 2018 and 2033 MVEBs for NOX and VOC, and incorporate the plan into the Georgia SIP and to redesignate the Area to attainment for the 2015 8-hour ozone NAAQS. In that notice, EPA also notified the public of the status of the Agency's adequacy determination for the NOX and VOC MVEBs for the Atlanta Area. The details of Georgia's submittal and the rationale for EPA's actions are further explained in the NPRM. Comments on the August 26, 2022, NPRM were due on or before September 26, 2022. EPA did not receive any comments on the August 26, 2022, NPRM.

    III. Final Action

    EPA is approving the aforementioned changes to the SIP. EPA is taking two separate but related final actions. First, EPA is approving the maintenance plan for the Atlanta Area, including the NOX and VOC MVEBs for 2018 and 2033, and incorporating it into the Georgia SIP. The maintenance plan demonstrates that the Area will continue to maintain the 2015 8-hour ozone NAAQS and that the MVEBs meet all of the adequacy criteria contained in 40 CFR 93.118(e)(4) and (5). Second, EPA is approving Georgia's redesignation request for the 2015 8-hour ozone NAAQS for the Atlanta Area. Approval of the redesignation request changes the official designation of Bartow, Clayton, Cobb, DeKalb, Fulton, Gwinnett, and Henry Counties in in the Atlanta Area for the 2015 8-hour ozone NAAQS from nonattainment to attainment, as indicated at 40 CFR part 81. EPA is also notifying the public that EPA finds the newly established NOX and VOC MVEBs for the Atlanta Area adequate for the purpose of transportation conformity. Within 24 months from this final rule, the transportation partners for the Atlanta Area will need to demonstrate conformity to the new NOX and VOC MVEBs pursuant to 40 CFR 93.104(e).

    IV. Statutory and Executive Order Reviews

    Under the CAA, redesignation of an area to attainment and the accompanying approval of a maintenance plan under section 107(d)(3)(E) are actions that affect the status of a geographical area and do not impose any additional regulatory requirements on sources beyond those imposed by state law. A redesignation to attainment does not in and of itself create any new requirements, but rather results in the applicability of requirements contained in the CAA for areas that have been redesignated to attainment. Moreover, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable Federal regulations. See42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA's role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, these actions merely approve state law as meeting Federal requirements and do not impose additional requirements beyond those imposed by state law. For this reason, these actions:

    • Are not significant regulatory actions subject to review by the Office of Management and Budget under Executive Orders 12866 (58 FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 21, 2011);

    • Do not impose an information collection burden under the provisions Start Printed Page 62735 of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);

    • Are certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.);

    • Do not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);
    • Do not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999);
    • Are not economically significant regulatory actions based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);
    • Are not significant regulatory actions subject to Executive Order 13211 (66 FR 28355, May 22, 2001);
    • Are not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and
    • Will not have disproportionate human health or environmental effects under Executive Order 12898 (59 FR 7629, February 16, 1994).

    The SIP is not approved to apply on any Indian reservation land or in any other area where EPA or an Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the rules do not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), nor will they impose substantial direct costs on tribal governments or preempt tribal law.

    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing these actions and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rules in the Federal Register . A major rule cannot take effect until 60 days after it is published in the Federal Register . These actions are not “major rules” as defined by 5 U.S.C. 804(2).

    Under section 307(b)(1) of the CAA, petitions for judicial review of these actions must be filed in the United States Court of Appeals for the appropriate circuit by December 16, 2022. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of these actions for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed and shall not postpone the effectiveness of such rule or actions. These actions may not be challenged later in proceedings to enforce their requirements. See section 307(b)(2).

    Start List of Subjects

    List of Subjects

    40 CFR Part 52

    • Environmental protection
    • Air pollution control
    • Incorporation by reference
    • Intergovernmental relations
    • Nitrogen dioxide
    • Ozone
    • Reporting and recordkeeping requirements
    • Volatile organic compounds

    40 CFR Part 81

    • Environmental protection
    • Air pollution control
    • Incorporation by reference
    End List of Subjects Start Signature

    Dated: September 30, 2022.

    Daniel Blackman,

    Regional Administrator, Region 4.

    End Signature

    For the reasons stated in the preamble, the EPA amends 40 CFR part 52 and part 81 as follows:

    Start Part

    PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS

    End Part Start Amendment Part

    1. The authority citation for part 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 7401 et seq.

    End Authority

    Subpart L—Georgia

    Start Amendment Part

    2. In § 52.570(e), amend the table by adding a new entry at the end of the table for “2015 8-hour Ozone Maintenance Plan for the Atlanta Area” to read as follows:

    End Amendment Part
    Identification of plan.
    * * * * *

    (e) * * *

    EPA Approved Georgia Non-Regulatory Provisions

    Name of nonregulatory SIP provisionApplicable geographic or nonattainment areaState submittal date/effective dateEPA approval dateExplanation
    *         *         *         *         *         *         *
    2015 8-hour Ozone Maintenance Plan for the Atlanta AreaBartow, Clayton, Cobb, DeKalb, Fulton, Gwinnett, and Henry Counties2/28/202210/17/2022, [Insert citation of publication]
    Start Part

    PART 81—DESIGNATION OF AREAS FOR AIR QUALITY PLANNING PURPOSES

    End Part Start Amendment Part

    3. The authority citation for part 81 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 7401 et seq.

    End Authority Start Amendment Part

    4. In § 81.311, amend the table entitled “Georgia—2015 8-Hour Ozone NAAQS [Primary and Secondary]” by revising the entry for “Atlanta, GA,” to read as follows:

    End Amendment Part
    Georgia.
    * * * * *

    Georgia—2015 8-Hour Ozone NAAQS

    [Primary and secondary]

    Designated area 1DesignationClassification
    Date 2TypeDate 2Type
    Atlanta, GA11/16/2022Attainment
    Bartow County
    Clayton County
    Start Printed Page 62736
    Cobb County
    DeKalb County
    Fulton County
    Gwinnett County
    Henry County
    *         *         *         *         *         *         *
    1  Includes any Indian country in each county or area, unless otherwise specified. EPA is not determining the boundaries of any area of Indian country in this table, including any area of Indian country located in the larger designation area. The inclusion of any Indian country in the designation area is not a determination that the state has regulatory authority under the Clean Air Act for such Indian country.
    2  This date is August 3, 2018, unless otherwise noted.
    * * * * *
    End Supplemental Information

    Footnotes

    1.  That Atlanta Area consists of Bartow, Clayton, Cobb, DeKalb, Fulton, Gwinnett, and Henry Counties in Georgia.

    Back to Citation

    [FR Doc. 2022-21653 Filed 10-14-22; 8:45 am]

    BILLING CODE 6560-50-P

Document Information

Effective Date:
11/16/2022
Published:
10/17/2022
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Final rule.
Document Number:
2022-21653
Dates:
This rule is effective November 16, 2022.
Pages:
62733-62736 (4 pages)
Docket Numbers:
EPA-R04-OAR-2022-0290, FRL-10107-02-R4
Topics:
Air pollution control, Environmental protection, Incorporation by reference, Intergovernmental relations, Nitrogen dioxide, Ozone, Reporting and recordkeeping requirements, Volatile organic compounds
PDF File:
2022-21653.pdf
Supporting Documents:
» Air Quality State Implementation Plans; Approvals and Promulgations: Georgia; Redesignation of the Atlanta, GA 2015 8-Hour Ozone Nonattainment Area to Attainment
» Memorandum - GA-184
» Air Quality State Implementation Plans; Approvals and Promulgations: Georgia; Redesignation of the Atlanta, GA 2015 8-Hour Ozone Nonattainment Area to Attainment
» ATL Summer 2021 Rainfall and Temp Analysis
» June 10 2022 email from GA EPD3
» 8_20220223 Narrative_2015 Ozone Maintenance Plan for Atlanta - Final
» 4_20220223 GovDelivery_2015 Ozone Maintenance Plan for Atlanta - Final
» 5_EPA Comment Letter on GA Prehearing Notice for Atl Redesignation Maintenance Plan
» 7_20220223 Response to Comments_2015 Ozone Maintenance Plan for Atlanta - Final
» 1_20220223 Transmittal Letter_2015 Ozone Maintenance Plan for Atlanta - Final
CFR: (2)
40 CFR 52.570
40 CFR 81.311