99-507. Washington Public Power Supply System; Washington Nuclear Project Unit 3; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 64, Number 6 (Monday, January 11, 1999)]
    [Notices]
    [Pages 1644-1645]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-507]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-508]
    
    
    Washington Public Power Supply System; Washington Nuclear Project 
    Unit 3; Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an order terminating Construction Permit No. 
    CPPR-154, which authorized construction of the Washington Nuclear 
    Project Unit 3 (WNP-3), located at Satsop, Washington. This 
    construction permit (CP) is held by the Washington Public Power Supply 
    System (WPPSS) and includes all remaining WNP-3 structures and the 
    Washington Nuclear Plant Unit 5 (WNP-5) structures that were subsumed 
    in the WNP-3 construction permit following expiration of the WNP-5 
    Construction Permit No. CPPR-155, which was issued on April 11, 1978, 
    Docket No. 50-509.
        Termination of the CP was requested by WPPSS by letter dated August 
    8, 1996, as supplemented by letters dated June 15 and November 5, 1998. 
    In a related matter, on August 16, 1998, WPPSS filed a motion for 
    withdrawal of its application for an operating license (OL) for WNP-3 
    and for termination of the proceeding on that application before the 
    Atomic Safety and Licensing Board (ASLB). The ASLB approved the 
    withdrawal of the OL application and terminated the proceeding on 
    October 16, 1996, noting that the staff would prepare an adequate EA on 
    the CP termination and that the impacts addressed there would encompass 
    the OL termination impacts, thus obviating the need for a separate EA 
    on OL termination, 44 NRC 134 (1996).
    
    Environmental Assessment
    
    Identification of the Proposed Action
    
        The proposed action is issuance of an order that would terminate 
    Construction Permit No. CPPR-154 for WNP-3. WPPSS has decided to 
    terminate the CP of the partially completed, and previously deferred, 
    WNP-3 project. Recent changes in Washington State law (RCW 80.50.300) 
    have made it possible to transfer ownership of WNP-3 and WNP-5 to an 
    interlocal agency, the Satsop Redevelopment Project (SRP), formed by 
    Grays Harbor County, the Port of Grays Harbor, and the Grays Harbor 
    Public Utilities District. This new agency will not complete the 
    project as a nuclear power plant; rather, SRP plans to own and operate 
    the site and certain structures for economic development purposes.
        WPPSS has entered into an agreement to transfer ownership of the 
    1600-acre Satsop site to the SRP, or its successor, for conversion of 
    the site to an industrial, business, or research park. Under the 
    agreement, 22 acres (with an option to acquire an additional 20 acres) 
    are to be maintained under the ownership of WPPSS for a combustion 
    turbine energy facility project.
        The plant island area of the site includes the cooling towers, 
    reactor auxiliary buildings, reactor buildings, turbine building, and 
    the administration building for WNP-3 and WNP-5. None of these 
    structures are scheduled for demolition. The WNP-3 reactor building and 
    reactor auxiliary building will be secured by the installation of 
    permanent doors and the closure of building openings. The equipment 
    located within these buildings will be removed to the extent practical. 
    Service systems, such as lighting, communications, fire protection, and 
    electrical service, will remain operational. The partially complete 
    WNP-5 reactor auxiliary building is planned to be enclosed by the 
    completion of the grade-level floor slab. The WNP-5 reactor building 
    will be reconfigured to serve as the site's raw water supply storage 
    facility. The WNP-3 and WNP-5 turbine building will be cleared of the 
    turbine generator and related systems. Service systems within the 
    turbine building will remain operational. The disposition of the 
    cooling towers is uncertain; current plans are to keep them as they 
    are. The administration building, fire protection building, water 
    treatment facility, blowdown building area, north and south tank farms, 
    and the 230 kV electrical supply system will be retained for future 
    use. Warehouses, buildings, material storage yards, and parking lots 
    that were developed to support the construction of the plant are 
    supplied by service systems and will be retained or upgraded to support 
    future commercial development. Any temporary buildings and facilities 
    not identified for potential future use will be removed along with 
    their foundations. Developed property and laydown yards will be 
    cleared. The existing raw water well will be maintained as a source of 
    potable water and the Ranney well field will remain as a source of 
    process water for the Satsop site, including the Combustion Turbine 
    Project. The barge unloading facility will remain for use by the SRP.
        The staff inspected the Satsop site on October 27-28, 1998, to 
    determine if possession of source, byproduct, or special nuclear 
    material was controlled as authorized and if the site is being 
    maintained in a safe and stable manner, and to assess key environmental 
    aspects of the site. The inspectors observed selected portions of the 
    Ranney wells, barge slip, cooling towers, and other site buildings. The 
    inspectors also observed that erosion controls were being maintained.
        The site cannot be used as a utilization facility. No nuclear fuel 
    was ever received on site. The Satsop site is in an environmentally 
    stable condition that poses no significant hazard to persons on site, 
    and the plant cannot be operated in its present condition.
    
    Need for the Proposed Action
    
        WPPSS has terminated construction of the nuclear power plant and 
    has disabled the facility so that it cannot be operated as a 
    utilization facility. WPPSS intends to transfer the site to the SRP for 
    use as an industrial, business, or research park, with the exception of 
    22 acres and an option to acquire an additional 20 acres for use as an 
    energy facility operated by WPPSS. This action would terminate the 
    construction permit.
    
    Environmental Impacts of the Proposed Action
    
        This is a simple administrative action of terminating the 
    construction permit to reflect the fact that there are no longer 
    utilization facilities under construction at the Satsop site and that 
    the site has been adequately stabilized. This action has no 
    environmental impact.
    
    Alternatives to the Proposed Action
    
        There are no viable alternatives with respect to the proposed 
    action.
    
    [[Page 1645]]
    
    Alternative Use of Resources
    
        This action, for which there are no appropriate alternatives, does 
    not involve the use of, and therefore will not affect, available 
    resources.
    
    Agencies and Persons Consulted
    
        In accordance with its stated policy, on October 28 and November 3, 
    1998, the staff consulted with the Washington State official, Deborah 
    J. Ross of the Energy Facility Site Evaluation Council, regarding the 
    environmental impact of the proposed action. The State official had no 
    comments.
    
    Finding of No Significant Impact
    
        On the basis of the environmental assessment, the Commission 
    concludes that the proposed action will not have a significant effect 
    on the quality of the human environment. Accordingly, the Commission 
    has determined not to prepare an environmental impact statement for the 
    proposed action.
        For further details with respect to the proposed action, see the 
    licensee's request for termination of Construction Permit No. CPPR-154, 
    dated August 8, 1996, additional information submitted by letter dated 
    June 15, 1998, WPPSS's ``Satsop Power Plant Scope of Restoration'' 
    transmitted by letter dated November 5, 1998, and the NRC staff's 
    inspection report dated November 2, 1998. These documents regarding the 
    NRC staff's environmental assessment of the proposed action are 
    available for public inspection at the Commission's Public Document 
    Room, The Gelman Building, 2120 L Street, NW., Washington, DC.
    
        Dated at Rockville, Maryland, this 4th day of January 1999.
    
        For the Nuclear Regulatory Commission.
    Seymour H. Weiss,
    Director, Non-Power Reactors and Decommissioning Project Directorate, 
    Division of Reactor Program Management, Office of Nuclear Reactor 
    Regulation.
    [FR Doc. 99-507 Filed 1-8-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
01/11/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-507
Pages:
1644-1645 (2 pages)
Docket Numbers:
Docket No. 50-508
PDF File:
99-507.pdf