99-758. Carolina Power & Light; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing  

  • [Federal Register Volume 64, Number 8 (Wednesday, January 13, 1999)]
    [Notices]
    [Pages 2237-2241]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-758]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    UNITED STATES NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-400]
    
    
    Carolina Power & Light; Notice of Consideration of Issuance of 
    Amendment to Facility Operating License, Proposed No Significant 
    Hazards Consideration Determination, and Opportunity for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License No. 
    NPF-63 issued to Carolina Power & Light (CP&L or the licensee) for 
    operation of the Shearon Harris Nuclear Power Plant
    
    [[Page 2238]]
    
    located in Wake and Chatham Counties, North Carolina.
        The proposed amendment would support a modification to the plant to 
    increase the spent fuel storage capacity by adding rack modules to 
    spent fuel pools (SFPs) ``C'' and ``D'' and placing the pools in 
    service. In order to activate the pools, CP&L requests that the NRC 
    review and approve the following:
        i. Revised Technical Specification 5.6 to identify PWR burnup 
    restrictions, BWR enrichment limits, pool capacities, heat load 
    limitations and nominal center-to-center distances between fuel 
    assemblies in the racks to be installed in SFPs `C' and `D.'
        ii. 10 CFR 50.55a Alternative Plan to demonstrate acceptable level 
    of quality and safety in the completion of the component cooling water 
    (CCW) and SFP `C' and `D' cooling and cleanup system piping.
        The cooling system for SFPs `C' and `D' cannot be N stamped in 
    accordance with ASME Section III since some installation records are 
    not available, a partial turnover was not performed when construction 
    was halted following the cancellation of Unit 2 and CP&L's N 
    certificate program was discontinued following completion of Unit 1.
        iii. Unreviewed safety question for additional heat load on the CCW 
    system. The acceptability of the 1.0 MBtu/hr heat load from SFPs `C' 
    and `D' was demonstrated by the use of thermal-hydraulic analyses of 
    the CCW system under various operating scenarios. The dynamic modeling 
    used in the thermal-hydraulic analyses identified a decrease in the 
    minimum required CCW system flow rate to the residual heat removal heat 
    exchangers. This change has not been previously reviewed by the NRC and 
    is deemed to constitute an unreviewed safety question.
        Before issuance of the proposed license amendment, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        The Commission has made a proposed determination that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendment would not (1) 
    involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
        1. Involve a significant increase in the probability or 
    consequences of an accident previously evaluated.
        In the analysis of the safety issues concerning the expanded 
    pool storage capacity within Harris' Fuel Handling Building, the 
    following previously postulated accident scenarios have been 
    considered:
        a. A spent fuel assembly drop in a Spent Fuel Pool.
        b. Loss of Spent Fuel Pool cooling flow.
        c. A seismic event.
        d. Misloaded fuel assembly.
        The probability that any of the accidents in the above list can 
    occur is not significantly increased by the activity itself. The 
    probabilities of a seismic event or loss of Spent Fuel Pool cooling 
    flow are not influenced by the proposed changes. The probabilities 
    of accidental fuel assembly drops or misloadings are primarily 
    influenced by the methods used to lift and move these loads. The 
    method of handling loads during normal plant operations is not 
    significantly changed, since the same equipment (i.e., Spent Fuel 
    Handling Machine and tools) and procedures as those in current use 
    in pools `A' and `B' will be used in pools `C' and `D'. Since the 
    methods used to move loads during normal operations remain nearly 
    the same as those used previously, there is no significant increase 
    in the probability of an accident. Current shipping activities at 
    the Harris Nuclear Plant will continue as previously licensed. The 
    consequences of an accident involving shipping activities [are] not 
    changed and there is no significant increase in the probability of 
    an accident.
        During rack installation, all work in the pool area will be 
    controlled and performed in strict accordance with specific written 
    procedures. Any movement of fuel assemblies which is required to be 
    performed to support this activity (e.g., installation of racks) 
    will be performed in the same manner as during normal refueling 
    operations.
        Accordingly, the proposed activity does not involve a 
    significant increase in the probability of an accident previously 
    evaluated.
        The consequences of the previously postulated scenarios for an 
    accidental drop of a fuel assembly in the Spent Fuel Pool have been 
    re-evaluated for the proposed change. The results show that such the 
    postulated accident of a fuel assembly striking the top of the 
    storage racks will not distort the racks sufficiently to impair 
    their functionality. The minimum subcriticality margin, 
    Keff less than or equal to 0.95, will be maintained. The 
    structural damage to the Fuel Handling Building, pool liner, and 
    fuel assembly resulting from a fuel assembly drop striking the pool 
    floor or another assembly located within the racks is primarily 
    dependent on the mass of the falling object and the drop height. 
    Since these two parameters are not changed by the proposed activity 
    from those considered previously, the structural damage to these 
    items remains unchanged. The radiological dose at the exclusion area 
    boundary will not be increased from those previously considered, 
    since the pertinent fuel parameters remain unchanged. These dose 
    levels remain ``well within'' the levels required by 10 CFR 100, 
    paragraph 11, as defined in Section 15.7.4.II.1 of the Standard 
    Review Plan. Thus, the results of the postulated fuel drop accidents 
    remain acceptable and do not represent a significant increase in 
    consequences from any of the same previously evaluated accidents 
    that have been reviewed and found acceptable by the NRC.
        The consequences of a loss of Spent Fuel Pool cooling have been 
    evaluated and found to have no increase. The concern with this 
    accident is a reduction of Spent Fuel Pool water inventory from bulk 
    pool boiling resulting in uncovering fuel assemblies. This situation 
    would lead to fuel failure and subsequent significant increase in 
    offsite dose. Loss of spent fuel pool cooling at Harris is mitigated 
    in the usual manner by ensuring that a sufficient time lapse exists 
    between the loss of forced cooling and uncovering fuel. This period 
    of time is compared against a reasonable period to re-establish 
    cooling or supply an alternative water source. Evaluation of this 
    accident usually includes determination of a time to boil, which in 
    the case of pools `C' and `D' is in excess of 13 hours based on a 
    consideration of end of plant life heat loads. This evaluation 
    neglects any possible cooling from the connection to pools `A' and 
    `B' through the transfer canal. The 13 hour period is much shorter 
    than the onset of any significant increase in offsite dose, since 
    once boiling begins it would have to continue unchecked until the 
    pool surface was lowered to the point of exposing active fuel. The 
    time to boil represents the onset of loss of pool water inventory 
    and is commonly used as a gauge for establishing the comparison of 
    consequences before and after a refueling project. The heatup rate 
    in the Spent Fuel Pool is a nearly linear function of the fuel decay 
    heat load. Subsequent to the proposed changes, the fuel decay heat 
    load will increase because of the increase in the number assemblies 
    from those considered from Pools `A' and `B' alone. The methodology 
    used in the thermal-hydraulic analysis determined the maximum fuel 
    decay heat loads. In the unlikely event that pool cooling is lost to 
    pools `C' and `D', sufficient time will still be available for the 
    operators to provide alternate means of cooling before the onset of 
    pool boiling. Therefore, the proposed change represents no increase 
    in the consequences of loss of pool cooling.
        The consequences of a design basis seismic event are not 
    increased. The consequences of this accident are evaluated on the 
    basis of subsequent fuel damage or compromise of the fuel storage or 
    building configurations leading to radiological or criticality 
    concerns. The new racks have been analyzed in their new 
    configuration and found safe during seismic motion. The fuel stored 
    in these racks has been determined to remain intact and the racks 
    maintain the fuel and fixed poison configurations subsequent to a 
    seismic event. The structural capability of the pool and liner will 
    not be exceeded under the appropriate combinations of dead weight, 
    thermal, and seismic loads. The Fuel
    
    [[Page 2239]]
    
    Handling Building structure will remain intact during a seismic 
    event and will continue to adequately support and protect the fuel 
    racks, storage array, and pool moderator/coolant. Thus, the 
    consequences of a seismic event are not increased.
        Fuel misloading and mislocation accidents were previously 
    credible occurrences, since fuel could be placed at an unintended 
    storage location or could have been lowered outside and adjacent to 
    a storage rack in Pools `A' or `B'. However, neither of these two 
    scenarios previously represented any concern because of the flux 
    trap style of the rack designs in these two pools. Similar 
    procedures, equipment and methods of fuel movement will be used for 
    Pools `C' and `D' as those used previously for Pools `A' and `B'. 
    Therefore, the proposed activity does not represent any increase in 
    the probability of occurrence. The proposed non-flux trap design 
    racks for Pools `C' and `D' require administrative controls to 
    ensure that fuel assemblies meet effective enrichment criteria prior 
    to storage. Under these conditions, misloading of a fuel assembly by 
    placement in an unintended storage cell has no significant 
    consequences. Therefore, the only remaining potential mislocation of 
    a fuel assembly is for an assembly to be lowered outside of and 
    directly adjacent to a storage rack. This accident occurring in 
    Pools `C' or `D' has been analyzed for the worst possible storage 
    configuration subsequent to the proposed activity and it has been 
    shown that the consequences remain acceptable with respect to the 
    same criteria used previously. Thus, there is no increase in 
    consequences for fuel mislocation or misloading.
        Therefore it is concluded that the proposed changes do not 
    significantly increase the probability or consequences of any 
    accident previously evaluated.
        2. Create the possibility of a new or different kind of accident 
    from any previously analyzed.
        To assess the possibility of new or different kind of accidents, 
    a list of the important parameters required to ensure safe fuel 
    storage was established. Safe fuel storage is defined here as 
    providing an environment, which would not present any significant 
    threats to workers or the general public (i.e., meeting the 
    requirements of 10 CFR 100 and 10 CFR 20). Any new events, which 
    would modify these parameters sufficiently to place them outside of 
    the boundaries analyzed for normal conditions and/or outside of the 
    boundaries previously considered for accidents would be considered 
    to create the possibility of a new or different accident. The 
    criticality and radiological safety evaluations were reviewed to 
    establish the list of important parameters. The fuel configuration 
    and the existence of the moderator/coolant were identified as the 
    only two parameters, which were important to safe fuel storage. 
    Significant modification of these two parameters represents the only 
    possibility of an unsafe storage condition. Once the two important 
    parameters were established, an additional step was taken to 
    determine what events (which were not previously considered) could 
    result in changes to the storage configuration or moderator/coolant 
    presence during or subsequent to the proposed changes.
        This process was adopted to ensure that the possibility of any 
    new or different accident scenario or event would be identified. Due 
    to the proposed activity, an accidental drop of a rack module during 
    construction activity in the pool was considered as the only event 
    which might represent a new or different kind of accident.
        A construction accident resulting in a rack drop is an unlikely 
    event. The proposed activity will utilize the defense-in-depth 
    approach for these heavy loads. The defense-in-depth approach is 
    intended to meet the requirements of NUREG-0612 and preclude the 
    possibility of a rack drop. All movements of heavy loads over the 
    pool will comply with the applicable administrative controls and 
    guidelines (i.e. plant procedures, NUREG-0612, etc.). A temporary 
    hoist and rack lifting rig will be introduced to lift and suspend 
    the racks from the bridge of the Auxiliary Crane. These items have 
    been designed in accordance with the requirements of NUREG-0612 and 
    ANSI N14.6 and will be similar to those used recently to install 
    storage rack modules in Pool `B'.
        The postulated rack drop event is commonly referred to as a 
    ``heavy load drop'' over the pools. Heavy loads will not be allowed 
    to travel over any racks containing fuel assemblies. The danger 
    represented by this event is that the racks will drop to the pool 
    floor and the pool structure will be compromised leading to loss of 
    moderator/coolant, which is one of the two important parameters 
    identified above. Although the analysis of this event has been 
    performed and shown to be acceptable, the question of a new or 
    different type of event is answered by determining whether heavy 
    load drops over the pool have been considered previously. As stated 
    above, heavy loads (storage rack modules) were recently installed in 
    Pool `B' using similar methods. Therefore, the rack drop does not 
    represent a new or different kind of accident.
        The proposed change does not alter the operating requirements of 
    the plant or of the equipment credited in the mitigation of the 
    design basis accidents. The proposed change does not affect any of 
    the important parameters required to ensure safe fuel storage. 
    Therefore, the potential for a new or previously unanalyzed accident 
    is not created.
        3. Involve a significant reduction in the margin of safety.
        The function of the Spent Fuel Pool is to store the fuel 
    assemblies in a subcritical and coolable configuration through all 
    environmental and abnormal loadings, such as an earthquake or fuel 
    assembly drop. The new rack design must meet all applicable 
    requirements for safe storage and be functionally compatible with 
    Pools `C' and `D'.
    
    CP&L has Addressed the Safety Issues Related to the Expanded Pool 
    Storage Capacity in the Following Areas:
    
        1. Material, mechanical and structural considerations. The 
    mechanical, material, and structural designs of the new racks have 
    been reviewed in accordance with the applicable provisions of the 
    NRC Guidance entitled, ``Review and Acceptance of Spent Fuel Storage 
    and Handling Applications''. The rack materials used are compatible 
    with the spent fuel assemblies and the Spent Fuel Pool environment. 
    The design of the new racks preserves the proper margin of safety 
    during normal and abnormal loads. It has been shown that such loads 
    will not invalidate the mechanical design and material selection to 
    safely store fuel in a coolable and subcritical configuration.
    
    2. Nuclear Criticality
    
        The methodology used in the criticality analysis of the expanded 
    Spent Fuel Pool meets the appropriate NRC guidelines and the ANSI 
    standards (GDC 62, NUREG 0800, Section 9.1.2, the OT Position for 
    Review and Acceptance of Spent Fuel Storage and Handling 
    Applications, Reg. Guide 1.13, and ANSI/ANS 8.17). The margin of 
    safety for subcriticality is maintained by having the neutron 
    multiplication factor equal to, or less than, 0.95 under all 
    accident conditions, including uncertainties. This criterion is the 
    same as that used previously to establish criticality safety 
    evaluation acceptance and remains satisfied for all analyzed 
    accidents.
    
    3. Thermal-hydraulic and Pool Cooling
    
        The thermal-hydraulic and cooling evaluation of the pools 
    demonstrated that the pools can be maintained below the specified 
    thermal limits under the conditions of the maximum heat load and 
    during all credible accident sequences and seismic events. The pool 
    temperature will not exceed 137 deg.F during the highest heat load 
    conditions. The maximum local water temperature in the hot channel 
    will remain below the boiling point. The fuel will not undergo any 
    significant heat up after an accidental drop of a fuel assembly on 
    top of the rack blocking the flow path. A loss of cooling to the 
    pool will allow sufficient time (>13 hours) for the operators to 
    intervene and line up alternate cooling paths and the means of 
    inventory make-up before the onset of pool boiling. The thermal 
    limits specified for the evaluations performed to support the 
    proposed activity are the same as those that were used in the 
    previous evaluations. It has also been demonstrated that adequate 
    margin exists in the Unit 1 CCW system to support near term 
    operation of the pools subject to the requirements of the proposed 
    changes to the Technical Specifications.
        Based on the preceding discussion it is concluded that this 
    activity does not involve a significant reduction in the margin of 
    safety.
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three standards of 10 CFR 50.92(c) are 
    satisfied. Therefore, the NRC staff proposes to determine that the 
    amendment request involves no significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within 30 days after the date of 
    publication of this notice will be considered in making any final 
    determination.
    
    [[Page 2240]]
    
        Normally, the Commission will not issue the amendment until the 
    expiration of the 30-day notice period. However, should circumstances 
    change during the notice period such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendment before the expiration of 
    the 30-day notice period, provided that its final determination is that 
    the amendment involves no significant hazards consideration. The final 
    determination will consider all public and State comments received. 
    Should the Commission take this action, it will publish in the Federal 
    Register a notice of issuance and provide for opportunity for a hearing 
    after issuance. The Commission expects that the need to take this 
    action will occur very infrequently.
        Written comments may be submitted by mail to the Chief, Rules and 
    Directives Branch, Division of Administrative Services, Office of 
    Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555-0001, and should cite the publication date and page number of 
    this Federal Register notice. Written comments may also be delivered to 
    Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
    Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Copies of 
    written comments received may be examined at the NRC Public Document 
    Room, the Gelman Building, 2120 L Street, NW., Washington, DC.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
    
        By February 12, 1999, the licensee may file a request for a hearing 
    with respect to issuance of the amendment to the subject facility 
    operating license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene. Requests for a hearing and a petition for leave to intervene 
    shall be filed in accordance with the Commission's ``Rules of Practice 
    for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
    persons should consult a current copy of 10 CFR 2.714 which is 
    available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the Cameron Village Regional Library, 1930 
    Clark Avenue, Raleigh, North Carolina 27605. If a request for a hearing 
    or petition for leave to intervene is filed by the above date, the 
    Commission or an Atomic Safety and Licensing Board, designated by the 
    Commission or by the Chairman of the Atomic Safety and Licensing Board 
    Panel, will rule on the request and/or petition; and the Secretary or 
    the designated Atomic Safety and Licensing Board will issue a notice of 
    hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) the nature of the petitioner's right under the 
    Act to be made party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue of law or fact. Contentions shall be limited to matters within 
    the scope of the amendment under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If a hearing is requested, the Commission will make a final 
    determination on the issue of no significant hazards consideration. The 
    final determination will serve to decide when the hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendment and make it immediately effective, notwithstanding the 
    request for a hearing. Any hearing held would take place after issuance 
    of the amendment.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendment.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by the above date. A copy of the petition should also be sent to the 
    Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, and to William D. Johnson, Vice President 
    and Senior Counsel, Carolina Power & Light Company, Post Office Box 
    1551, Raleigh, North Carolina 27602, attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).
        The Commission hereby provides such notice that this is a 
    proceeding on an application for a license amendment falling within the 
    scope of section 134 of the Nuclear Waste Policy Act of 1982 (NWPA), 42 
    U.S.C. 10154. Under section 134 of the NWPA, the
    
    [[Page 2241]]
    
    Commission, at the request of any party to the proceeding, must use 
    hybrid hearing procedures with respect to ``any matter which the 
    Commission determines to be in controversy among the parties.''
        The hybrid procedures in section 134 provide for oral argument on 
    matters in controversy, preceded by discovery under the Commission's 
    rules and the designation, following argument of only those factual 
    issues that involve a genuine and substantial dispute, together with 
    any remaining questions of law, to be resolved in an adjudicatory 
    hearing. Actual adjudicatory hearings are to be held on only those 
    issues found to meet the criteria of section 134 and set for hearing 
    after oral argument.
        The Commission's rules implementing section 134 of the NWPA are 
    found in 10 CFR Part 2, Subpart K, ``Hybrid Hearing Procedures for 
    Expansion of Spent Fuel Storage Capacity at Civilian Nuclear Power 
    Reactors'' (published at 50 FR 41662 dated October 15, 1985). Under 
    those rules, any party to the proceeding may invoke the hybrid hearing 
    procedures by filing with the presiding officer a written request for 
    oral argument under 10 CFR 2.1109. To be timely, the request must be 
    filed within ten (10) days of an order granting a request for hearing 
    or petition to intervene. The presiding officer must grant a timely 
    request for oral argument. The presiding officer may grant an untimely 
    request for oral argument only upon a showing of good cause by the 
    requesting party for the failure to file on time and after providing 
    the other parties an opportunity to respond to the untimely request. If 
    the presiding officer grants a request for oral argument, any hearing 
    held on the application must be conducted in accordance with the hybrid 
    hearing procedures. In essence, those procedures limit the time 
    available for discovery and require that an oral argument be held to 
    determine whether any contentions must be resolved in an adjudicatory 
    hearing. If no party to the proceeding timely requests oral argument, 
    and if all untimely requests for oral argument are denied, then the 
    usual procedures in 10 CFR Part 2, Subpart G apply.
        For further details with respect to this action, see the 
    application for amendment dated December 23, 1998, which is available 
    for public inspection at the Commission's Public Document Room, the 
    Gelman Building, 2120 L Street, NW., Washington, DC, and at the local 
    public document room located at the Cameron Village Regional Library, 
    1930 Clark Avenue, Raleigh, North Carolina 27605.
    
        Dated at Rockville, Maryland, this 7th day of January 1999.
    
        For the Nuclear Regulatory Commission.
    Scott Flanders,
    Project Manager, Project Directorate II-3, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-758 Filed 1-12-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
01/13/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-758
Pages:
2237-2241 (5 pages)
Docket Numbers:
Docket No. 50-400
PDF File:
99-758.pdf