96-534. Virginia Electric and Power Company, et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 61, Number 13 (Friday, January 19, 1996)]
    [Notices]
    [Pages 1372-1374]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-534]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. ER96-653-000, et al.]
    
    
    Virginia Electric and Power Company, et al.; Electric Rate and 
    Corporate Regulation Filings
    
    January 11, 1996.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Virginia Electric and Power Company
    
    [Docket No. ER96-653-000]
    
        Take notice that on December 21, 1995, Virginia Electric and Power 
    Company (Virginia Power), tendered for filing a Service Agreement 
    between Atlantic City Electric and Virginia Power, dated November 6, 
    1995, under the Power Sales Tariff to Eligible Purchasers dated May 27, 
    1994. Under the tendered Service Agreement Virginia Power agrees to 
    provide services to Atlantic City Electric under the rates, terms and 
    conditions of the Power Sales Tariff as agreed by the parties pursuant 
    to the terms of the applicable Service Schedules included in the Power 
    Sales Tariff.
        Copies of this filing were served upon the Virginia State 
    Corporation Commission, the North Carolina Utilities Commission and the 
    State of New Jersey Board of Public Utilities.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    2. Florida Power & Light Company
    
    [Docket No. ER96-654-000]
    
        Take notice that on December 21, 1995, Florida Power & Light 
    Company (FPL), tendered for filing a proposed Service Agreement with 
    Electric Clearinghouse, Inc. for transmission service under FPL's 
    Transmission Tariff No. 3.
        FPL requests that the proposed Service Agreement be permitted to 
    
    [[Page 1373]]
        become effective on January 1, 1996, or as soon thereafter as 
    practicable.
        FPL states that this filing is in accordance with Part 35 of the 
    Commission's Regulations.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    3. Catex Vitol Electric, L.L.C.
    
    [Docket No. ER96-656-000]
    
        Take notice that on December 21, 1995, Catex Vitol Electric, L.L.C. 
    (CVE), tendered for filing a letter from the Executive Committee of the 
    Western Systems Power Pool (WSPP) indicating that CVE had completed all 
    the steps for pool membership. CVE requests that the Commission amend 
    the WSPP Agreement to include it as a member.
        CVE requests an effective date of December 21, 1995, for the 
    proposed amendment. Accordingly, CVE requests waiver of the 
    Commission's notice requirements for good cause shown.
        Copies of the filing were served upon counsel for the WSPP and the 
    WSPP Executive Committee.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    4. Boston Edison Company
    
    [Docket No. ER96-657-000]
    
        Take notice that on December 22, 1995, Boston Edison Company 
    (Edison), filed a standstill agreement between itself and Reading 
    Municipal Lighting Department (Reading) tolling the one-year claims 
    limitation provision in Reading's Pilgrim power purchase contract with 
    regard to disputes over the 1994 true-up bill. The purpose of the 
    standstill agreement is to allow the parties to negotiate a settlement 
    agreement regarding billing disputes regarding the true-up bill for 
    1994. The standstill agreement makes no other changes to the rates, 
    terms and conditions of the contract between Reading and Edison.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    5. Boston Edison Company
    
    [Docket No. ER96-658-000]
    
        Take notice that on December 22, 1995, Boston Edison Company 
    (Boston Edison) of Boston, Massachusetts, in connection with Financial 
    Accounting Standards No. 106 recognition of Postretirement Benefits 
    Other than Pensions (PBOPs) on an accrual basis, tendered for filing a 
    1995 actuarial report and revised rate schedule supplements to its 
    following contracts for the sale of power from the Pilgrim nuclear 
    power plant.
    
    ------------------------------------------------------------------------
                                             Rate schedule     Entitlement  
                    Utility                       No.           (percent)   
    ------------------------------------------------------------------------
    Commonwealth Electric Co..............              68        11.00000  
    Montaup Electric Co...................              69        11.00000  
    Boylston..............................              77          .07463  
    Holyoke...............................              79          .89552  
    Westfield.............................              81          .22388  
    Hudson................................              83          .37313  
    Littleton.............................              85          .14925  
    Marblehead............................              87          .14925  
    North Attleboro.......................              89          .14925  
    Peabody...............................              91          .22388  
    Shrewsbury............................              93          .37313  
    Templeton.............................              95          .04478  
    Wakefield.............................              97          .14925  
    West Boylston.........................              99          .07463  
    Middleborough.........................             102          .10448  
    Reading...............................             113          .7462   
    ------------------------------------------------------------------------
    
        The supplements ask the Commission for permission to use the 1995 
    actuarial study for actual 1995 billings and for estimated 1996 
    billings, and for permission to make future changes in PBOP's billings 
    by filing annual actuarial data without filing a change in rate 
    schedules. Boston Edison states that it has served the filing on each 
    affected customer and on the Massachusetts Department of Public 
    Utilities.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    6. Bonneville Fuels Management Corporation
    
    [Docket No. ER96-659-000]
    
        Take notice that on December 22, 1995, Bonneville Fuels Management 
    Corporation (BFMgt), tendered for filing an application for waivers and 
    blanket approvals under various regulations of the Commission and for 
    an order accepting its FERC Electric Rate Schedule No. 1 to be 
    effective on the date of the Commission's order accepting the Rate 
    Schedule for filing.
        BFMgt intends to engage in electric power and energy transactions 
    as a marketer. In these transactions, BFMgt proposes to charge market-
    determined rates, mutually agreed upon by the parties. All sales and 
    purchases will be arms-length transactions.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    7. Consolidated Edison Company of New York, Inc.
    
    [Docket No. ER96-660-000]
    
        Take notice that on December 22, 1995, Consolidated Edison Company 
    of New York, Inc. (Con Edison), tendered for filing an agreement to 
    provide interruptible transmission service for Koch Power Services, 
    Inc. (KPSI).
        Con Edison states that a copy of this filing has been served by 
    mail upon KPSI.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    8. The Dayton Power and Light Company
    
    [Docket No. ER96-661-000]
    
        Take notice that on December 22, 1995, The Dayton Power and Light 
    Company (Dayton), tendered for filing an executed Master Power Sales 
    Agreement between Dayton and Northern Indiana Power Service Company 
    (NIPSCO).
        Pursuant to the rate schedules attached as Exhibit B to the 
    Agreement, Dayton will provide to NIPSCO power and/or energy for 
    resale.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice. 
    
    [[Page 1374]]
    
    
    9. New England Power Company
    
    [Docket No. ER96-662-000]
    
        Take notice that on December 22, 1995, New England Power Company 
    (NEP), tendered for filing a Supplement to its Service Agreement with 
    Fitchburg Gas & Electric Light Company under NEP's FERC Electric 
    Tariff, Original Volume No. 3.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    10. The Narragansett Electric Company
    
    [Docket No. ER96-664-000]
    
        Take notice that on December 22, 1995, The Narragansett Electric 
    Company tendered for filing rate changes to its FERC Electric Tariff, 
    Original Volume No. 1 for borderline sales.
        Comment date: January 25, 1996, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    Standard Paragraph
    
        E. Any person desiring to be heard or to protest said filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in 
    accordance with Rules 211 and 214 of the Commission's Rules of Practice 
    and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such motions or 
    protests should be filed on or before the comment date. Protests will 
    be considered by the Commission in determining the appropriate action 
    to be taken, but will not serve to make protestants parties to the 
    proceeding. Any person wishing to become a party must file a motion to 
    intervene. Copies of this filing are on file with the Commission and 
    are available for public inspection.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-534 Filed 1-18-96; 8:45 am]
    BILLING CODE 6717-01-P
    
    

Document Information

Published:
01/19/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-534
Dates:
January 25, 1996, in accordance with Standard Paragraph E at the end of this notice.
Pages:
1372-1374 (3 pages)
Docket Numbers:
Docket No. ER96-653-000, et al.
PDF File:
96-534.pdf