95-31533. National Fuel Gas Supply Corporation; Notice of Request Under Blanket Authorization
[Federal Register Volume 61, Number 1 (Tuesday, January 2, 1996)]
[Notices]
[Pages 62-63]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-31533]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP96-98-000]
National Fuel Gas Supply Corporation; Notice of Request Under
Blanket Authorization
December 26, 1995.
Take notice that on December 5, 1995, National Fuel Gas Supply
Corporation (National), 10 Lafayette Square, Buffalo, New York, 14203,
filed in the above docket a request pursuant to Section 157.205 of the
Regulations under the Natural Gas Act to construct and operate a sales
tap that will render service to American Meter Company (American Meter)
under its authorization issued in Docket No. CP83-4-000 pursuant to
Section 7 of the Natural Gas Act, all as more fully set forth in the
application which is on file with the Commission and open to public
inspection.
National proposes to construct and operate a new sales tap in Erie
County, Pennsylvania, on National's Line S-55. National indicates that
this tap will provide service to American Meter pursuant to National's
Rate Schedules IAS, FT and IT. National states that the service
provided under Rate Schedule IAS will require a new receipt point so
that National can receive gas back from American Meter. This new
receipt point will be constructed pursuant to the authority granted at
157.208(a) and will be located on National's Line L, less than 100 feet
from the proposed sales tap.
The cost of construction for the sales tap is estimated to be
$60,000, for which National will be reimbursed by American Meter. The
cost of the automatically authorized receipt point is estimated to be
$4,000, for which National will be reimbursed by American Meter.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Rules of Practice and Procedure (18 CFR
385.214) a motion to intervene or notice of intervention and pursuant
to Section 157.205 of the Regulations under the Natural Gas Act (18 CFR
157.205) a protest to the request. If no protest is filed within the
time allowed therefor, the proposed activity is deemed to be authorized
effective on the day after the time allowed for filing a protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request shall be treated as
an application for
[[Page 63]]
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 95-31533 Filed 12-29-95; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 01/02/1996
- Department:
- Energy Department
- Entry Type:
- Notice
- Document Number:
- 95-31533
- Pages:
- 62-63 (2 pages)
- Docket Numbers:
- Docket No. CP96-98-000
- PDF File:
-
95-31533.pdf