    AGENCIES: The Department of the Interior (Department) and the Central 
    Utah Water Conservancy District (District).
    
    ACTION: Notice of availability of the Draft Environmental Impact 
    Statement: DES 96-51.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Pursuant to section 102(2)(C) of the National Environmental 
    Policy Act of 1969, as amended, the Department, and the District have 
    issued a joint Draft Environmental Impact Statement (Draft EIS) on the 
    Upalco Replacement Project (Upalco). The Draft EIS consists of a 
    proposed action and alternatives to construct a combination of features 
    that will develop water supplies for the Upalco Unit of the Central 
    Utah Project in the Unita Basin of northeastern Utah. The Draft EIS 
    evaluates the environmental impacts of water storage reservoirs, 
    improved diversion and distribution of water, water conservation, 
    stabilization of high mountain lakes, instream flows, fish and wildlife 
    mitigation and enhancement, recreation developments and land 
    retirement.
        There is a need to manage the water supply within the Upalco Unit 
    to develop resources of the Ute Indian Tribe of the Uintah and Ouray 
    Reservation, provide early and late season irrigation water, provide 
    municipal water supplies, and provide water and facilities for 
    environmental and recreation purposes. The proposed action and 
    alternatives seek to meet these needs by providing storage, improved 
    distribution of water, water conservation, municipal and industrial 
    water, instream flows, fish and wildlife enhancements, and recreation 
    developments.
        Public participation has occurred throughout the EIS process. A 
    Notice of Intent was filed in the Federal Register on December 31, 
    1992. Since that time, open houses, public meetings, and mail-outs have 
    been conducted to solicit comments and ideas. Any comments received 
    throughout the process have been considered.
    
    DATES: Written comments on the Draft EIS must be submitted or 
    postmarked no later than March 4, 1997. Comments on the Draft EIS may 
    also be presented verbally or submitted in writing at the public 
    hearings to be held at the following times and locations:
         Wednesday, February 5, 1997, 6:00 p.m., Altamont High 
    School Auditorium, Highway 87 (North Side), Altamont, Utah.
         Thursday, February 6, 1997, 6:00 p.m., Salt Lake County 
    Commission Chambers, Room N1100, 2001 South State Street, Salt Lake 
    City, Utah.
         Tuesday, February 11, 1997, 1:00 p.m., Ute Tribal 
    Auditorium, Ute Tribal Headquarters, Fort Duchesne, Utah.
        The public hearings are being held to address the Draft EIS for the 
    proposed Upalco Unit Replacement Project. In order to be included as 
    part of the hearing record, written testimony must be submitted at the 
    time of the hearing. Verbal testimony will be limited to 5 minutes. 
    Those wishing to give testimony at a hearing should submit a 
    registration form, included at the end of the Draft EIS, to the address 
    listed below by, January 31, 1997.
    
    ADDRESSES: Comments on the Draft EIS should be addressed to: Terry 
    Holzworth, Project Manager, Central Utah Water Conservancy District, 
    355 West 1300 South, Orem, Utah 84058.
    
    FOR FURTHER INFORMATION CONTACT: Additional copies of the Draft EIS, 
    copies of the resources technical reports, or information on matters 
    related to this notice can be obtained on request from: Ms. Nancy 
    Hardman, Central Utah Water Conservancy District, 355 West 1300 South, 
    Orem, Utah 84058, Telephone: (801) 226-7187, Fax: (801) 226-7150.
        Copies are also available for inspection at:
    
    Central Utah Water Conservancy District, 355 West 1300 South, Orem, 
    Utah 84058
    Department of the Interior, Natural Resource Library, Serials Branch, 
    18th and C Streets, NW, Washington, D.C. 20240
    Department of the Interior, Central Utah Project Completion Act Office, 
    302 East 1860 South, Provo, Utah 84606
    Bureau of Indian Affairs, Uintah and Ouray Agency, 988 South 7500 East, 
    Fort Duchesne, Utah 84026
    
        Dated: December 27, 1996.
    Ronald Johnston,
    CUPCA Program Director, Department of the Interior.
    [FR Doc. 96-33344 Filed 12-31-96; 8:45 am]
    BILLING CODE 4310-RK-P
    
    
    

Document Information

Published:
01/02/1997
Department:
Interior Department
Entry Type:
Notice
Action:
Notice of availability of the Draft Environmental Impact Statement: DES 96-51.
Document Number:
96-33344
Dates:
Written comments on the Draft EIS must be submitted or postmarked no later than March 4, 1997. Comments on the Draft EIS may also be presented verbally or submitted in writing at the public hearings to be held at the following times and locations:
Pages: