2017-28284. Shell Energy North America (US), L.P.; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests  

  • Start Preamble Start Printed Page 109

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: Original major license.

    b. Project No.: 14795-002.

    c. Date filed: November 1, 2017.

    d. Applicant: Shell Energy North America (US), L.P.

    e. Name of Project: Hydro Battery Pearl Hill Pumped Storage Project.

    f. Location: On the Columbia River and Rufus Woods Lake, near Bridgeport, Douglas County, Washington. The project would be located on state lands and the lower reservoir and power generation and pumping equipment would be located on Rufus Woods Lake, a reservoir operated by the U.S. Army Corps of Engineers (Corps).

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).

    h. Applicant Contact: Kent Watt, Shell US Hosting Company, Shell Woodcreek Office, 150 North Dairy Ashford, Houston, TX 77079, (832) 337-1160, kent.watt@shell.com.

    i. FERC Contact: Ryan Hansen, 888 1st St. NE, Washington, DC 20426, (202) 502-8074, ryan.hansen@ferc.gov.

    j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice.

    The Commission strongly encourages electronic filing. Please file filing motions to intervene and protests using the Commission's eFiling system at http://www.ferc.gov/​docs-filing/​efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P-14795-002.

    The Commission's Rules of Practice and Procedures require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. This application has been accepted for filing, but is not ready for environmental analysis at this time.

    l. The proposed project would utilize the Corps' existing Rufus Woods Lake Reservoir and would consist of the following new facilities: (1) A 300-foot-diameter, 20-foot-tall lined corrugated steel tank upper reservoir with storage capacity of 26.5 acre-feet; (2) a 3-foot-diameter, 3,400-foot-long above-ground carbon steel penstock transitioning to a 3-foot-diameter, 2,700-foot-long buried carbon steel penstock; (3) a 77-foot-long, 77-foot-wide structural steel power platform housing five 2,400 horsepower vertical turbine pumps, one 5-megawatt twin-jet Pelton turbine and synchronous generator, and accompanying electrical equipment; (4) five vertical turbine pump intakes, each fitted with a 27-inch-diameter by 94-inch-long T-style fish screen; (5) a 2,500-foot-long, 24.9-kilovolt buried/affixed transmission line interconnecting to an existing non-project transmission line; (6) approximately 3,847 feet of gravel project access road; and (7) appurtenant facilities. The average annual generation is estimated to be 24 gigawatt-hours.

    m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's website at http://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice.

    A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant(s) named in this public notice.

    Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

    When the application is ready for environmental analysis, the Commission will issue a public notice requesting comments, recommendations, terms and conditions, or prescriptions.

    All filings must (1) bear in all capital letters the title PROTEST or MOTION TO INTERVENE, NOTICE OF INTENT TO FILE COMPETING APPLICATION, or COMPETING APPLICATION; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

    Start Signature

    Dated: December 26, 2017.

    Nathaniel J. Davis, Sr.,

    Deputy Secretary.

    End Signature End Preamble

    [FR Doc. 2017-28284 Filed 12-29-17; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
01/02/2018
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2017-28284
Pages:
109-109 (1 pages)
Docket Numbers:
Project No. 14795-002
PDF File:
2017-28284.Pdf