99-173. Environmental Impact Statement: Hinds and Rankin Counties, Mississippi  

  • [Federal Register Volume 64, Number 12 (Wednesday, January 20, 1999)]
    [Notices]
    [Page 3147]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-173]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF TRANSPORTATION
    
    Federal Highway Administration
    
    
    Environmental Impact Statement: Hinds and Rankin Counties, 
    Mississippi
    
    AGENCY: Federal Highway Administration (FHWA), DOT.
    
    ACTION: Notice of intent.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The FHWA is issuing this notice to advise the public that an 
    environmental impact statement will be prepared for the Pearl River 
    Bridge and Jackson International Airport Parkway/Mississippi 25 
    Connectors between Interstate 55, the Jackson International Airport, 
    and Mississippi Highway 25 in the vicinity of Jackson, Flowood, and 
    Pearl, Mississippi.
    
    FOR FURTHER INFORMATION CONTACT: Cecil Vick, Reality Officer/
    Environmental Coordinator, Federal Highway Administration, 666 North 
    Street, Suite 105, Jackson MS 29202-3199, Telephone: (601) 965-4217. 
    Contacts at the State and local level, respectively are: Mr. Billie 
    Barton, Environmental/Location Division Engineer, Mississippi 
    Department of Transportation, P.O. Box 1850, Jackson, MS, 39215-1850, 
    telephone: (601) 359-7920; and Mr. William Hillman, District Engineer, 
    Mississippi Department of Transportation, 7759 Highway 80 W., Newton 
    MS, 39345, telephone (601) 683-3341.
    
    SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the 
    Mississippi Department of Transportation (MDOT) will prepare an 
    Environmental Impact Statement (EIS) on the proposed Pearl River Bridge 
    and Jackson International Airport Parkway/Mississippi 25 Connectors in 
    Hinds and Rankin Counties, Mississippi. The proposed connectors would 
    begin at Interstate 55 at or near High Street in Jackson, Mississippi 
    and extend eastward across the Pearl River to connect with Mississippi 
    Highway 475 south of the Jackson International Airport and with 
    Mississippi Highway 25 north of the Jackson International Airport. The 
    proposal is for a full control of access facility, and interchanges 
    will be studied at various locations. The estimated length of the 
    project is 14.9 kilometers (9.3 miles).
        State and Federal legislation authorized studies of the bridge and 
    connectors and the Intermodeal Surface Transportation Efficiency Act of 
    1998, authorized partial funding for design, right of way, or 
    construction. Alternatives under consideration include (1) taking no 
    action and (2) build alternative.
        Initial environmental studies for the proposed project began as an 
    Environmental Assessment. As part of the Environmental Assessment 
    Process, the FHWA and MDOT sought input through the scoping process to 
    assist in determining and clarifying issues relative to this project. 
    Letters describing the proposed action and soliciting comments were 
    sent to appropriate federal, state, and local agencies, and to private 
    organizations and citizens who had previously expressed or were known 
    to have an interest in the proposal. A formal scoping meeting with 
    federal, state, and local agencies, and other interested parties was 
    held October 30, 1996. The U.S. Army Corps of Engineers, the U.S. Fish 
    and Wildlife Service, and the Mississippi Department of Wildlife 
    Fisheries and Parks became cooperating agencies. The scoping process 
    and interagency coordination is continuing and has reached the point 
    where the FHWA and MDOT have determined that completion of an EIS is 
    appropriate.
        Coordination will be continued with federal, state, and local 
    agencies, and with private organizations and citizens who express or 
    are known to have interest in this proposal. The draft EIS will be 
    available for public and agency review and comment prior to the 
    official public hearing.
        To ensure that the full range of issues relating to this proposed 
    action are addressed and all significant issues identified, comments, 
    and suggestions are invited from all interested parties. Comments or 
    questions concerning this proposed action and the EIS should be 
    directed to the FHWA at the address provided above.
    Lawrence J. Kastner,
    Assistant Division Administrator, Jackson, Mississippi.
    [FR Doc. 99-173 Filed 1-19-99; 8:45 am]
    BILLING CODE 4910-22-M
    
    
    

Document Information

Published:
01/20/1999
Department:
Federal Highway Administration
Entry Type:
Notice
Action:
Notice of intent.
Document Number:
99-173
Pages:
3147-3147 (1 pages)
PDF File:
99-173.pdf