99-1538. NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 64, Number 15 (Monday, January 25, 1999)]
[Notices]
[Page 3692]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-1538]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. GP99-150-000]
NorAm Gas Transmission Company; Notice of Request Under Blanket
Authorization
January 19, 1999.
Take notice that on January 12, 1999, NorAm Gas Transmission
Company (NGT), 1111 Louisiana, Houston, Texas 77002-5231, filed in
Docket No. CP99-150-000 a request pursuant to Sections 157.205 157.212
and 157.216 of the Commission's Regulations under the Natural Gas Act
(18 CFR 157.205, 157.212 and 157.216) for authorization to abandon,
construct, and operate certain facilities in Arkansas under NGT's
blanket certificate issued in Docket No. CP82-384-000 and CP82-384-001
pursuant to Section 7 of the Natural Gas Act, all as more fully set
forth in the request that is on file with the Commission and open to
public inspection
NGT specifically requests authority to (1) abandon a 6-inch tap and
relocate the existing skid mounted meter station located on Line LM-2
to a new location on Line BT-1; and (2) construct and operate a 2-inch
tap on Line BT-1 and 380 feet of 4-inch diameter pipe (line BT-20) to
continue to provide reliable service to Reynolds Metals Company
(Reynolds). The estimated volumes to be delivered to this tap are
approximately 442,000 Dth annually and 1,450 Dth on a peak day. The
facilities will be constructed at an estimated cost of $6,700 and
Reynolds will reimburse NGT all of the construction costs.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 99-1538 Filed 1-22-99; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 01/25/1999
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 99-1538
- Pages:
- 3692-3692 (1 pages)
- Docket Numbers:
- Docket No. GP99-150-000
- PDF File:
-
99-1538.pdf