98-1873. Notice of Application for Preliminary Permit  

  • [Federal Register Volume 63, Number 17 (Tuesday, January 27, 1998)]
    [Notices]
    [Pages 3889-3890]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-1873]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Application for Preliminary Permit
    
    January 21, 1998.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection:
        a. Type of Application: Preliminary Permit.
        b. Project No.: 11609-000.
        c. Date filed: November 3, 1997.
        d. Applicant: South Fork Irrigation District and Hot Springs Valley 
    Irrigation District.
        e. Name of Project: West Valley Project.
        f. Location: On the Cedar Creek, in Lassen and Modoc Counties, 
    California.
        g. Filed Pursuant to: Federal Power Act, 16 U.S.C., 791(a)-825(r).
        h. Applicant Contact: Mr. Don R. Pope, 9709 W. Fairview Avenue, 
    Littleton, CO 80127-3955, (303) 973-9610.
        i. FERC Contact: Mr. Robert Bell, (202) 219-2806.
        j. Comment Date: April 7, 1998.
        k. Description of Project: The proposed pumped storage project 
    would consist of: (1) the existing 16-foot-high, 1,100-foot-long 
    earthen Moon Lake Dam; (2) the Moon Lake Reservoir, having a surface 
    area of 3,000 acres, a storage capacity of 35,000 acre-feet, and normal 
    water surface elevation of 5,500 feet msl (this will serve as the upper 
    reservoir); (3) a new 90-foot-high, 650-foot-long concrete dam; (4) a 
    new reservoir having a surface area of 184 acres, a storage capacity of 
    8,280 acre-feet, and normal water surface elevation of 4,950 feet msl 
    (this would serve as the lower reservoir); (5) a new 18,000-foot long 
    tunnel connecting the reservoirs; (6) a new powerhouse within the 
    tunnel, containing four generating units with a total installed 
    capacity of 264 MW; (7) a new 5-mile-long, 230-KV transmission line; 
    and (8) appurtenant facilities.
        This project would have an annual generation of 542,880 MWh and 
    would be sold to a local utility.
        l. This notice also consists of the following standard paragraphs: 
    A5, A7, A9, A10, B, C, and D2.
        A5. Preliminary Permit--Anyone desiring to file a competing 
    application for preliminary permit for a proposed project must submit 
    the competing application itself, or a notice of intent to file such an 
    application, to the Commission on or before the specified comment date 
    for the particular application (see 18 CFR 4.36). Submission of a 
    timely notice of intent allows an interested person to file the 
    competing preliminary permit application no later than 30 days after 
    the specified comment date for the particular application. A competing 
    preliminary permit application must conform with 18 CFR 4.30(b) and 
    4.36.
        A7. Preliminary Permit--Any qualified development applicant 
    desiring to file a competing development application must submit to the 
    Commission, on or before a specified comment date for the particular 
    application, either a competing development application or a notice of 
    intent to file such an application. Submission of a timely notice of 
    intent to file a development application allows an interested person to 
    file the competing application no later than 120 days after the 
    specified comment date for the particular application. A competing 
    license application must conform with 18 CFR 4.30(b) and 4.36.
        A9. Notice of intent--A notice of intent must specify the exact 
    name, business address, and telephone number of the prospective 
    applicant, and must include an unequivocal statement of intent to 
    submit, if such an application may be filed, either a preliminary 
    permit application or a development application (specify which type of 
    application). A notice of intent must be served on the applicant(s) 
    named in this public notice.
        A10. Proposed Scope of Studies under Permit--A preliminary permit, 
    if issued, does not authorize construction. The term of the proposed 
    preliminary permit would be 36 months. The work proposed under the 
    preliminary permit would include economic analysis, preparation of 
    preliminary engineering plans, and a study of environmental impacts. 
    Based on the results of these studies, the Applicant would decide 
    whether to proceed with the preparation of a development application to 
    construct and operate the project.
        B. Comments, Protests, or Motions to Intervene--Anyone may submit 
    comments, a protest, or a motion to intervene in accordance with the 
    requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
    .214. In determining the appropriate action to take, the Commission 
    will consider all protests or other comments filed, but only those who 
    file a motion to intervene in accordance with the Commission's Rules 
    may become a party to the proceeding. Any comments, protests, or 
    motions to intervene must be received on or before the specified 
    comment date for the particular application.
        C. Filing and Service of Responsive Documents--Any filings must 
    bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
    TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
    ``PROTEST'', ``MOTION TO INTERVENE'', as applicable, and the project 
    number of the particular application to which the filing refers. Any of 
    the above-named documents must be filed by providing the original and 
    the number of copies provided by the Commission's regulations to: The 
    Secretary, Federal Energy Regulatory Commission, 888 First Street, 
    N.E., Washington, D.C. 20426. An additional copy must be sent to 
    Director, Division of Project Review, Federal Energy Regulatory 
    Commission, at the above-mentioned address. A copy of any notice of 
    intent, competing application
    
    [[Page 3890]]
    
    or motion to intervene must also be served upon each representative of 
    the Applicant specified in the particular application.
        D2. Agency Comments--Federal, state, and local agencies are invited 
    to file comments on the described application. A copy of the 
    application may be obtained by agencies directly from the Applicant. If 
    an agency does not file comments within the time specified for filing 
    comments, it will be presumed to have no comments. One copy of an 
    agency's comments must also be sent to the Applicant's representatives.
    David P. Boergers,
    Acting Secretary.
    [FR Doc. 98-1873 Filed 1-26-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Effective Date:
4/7/1998
Published:
01/27/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-1873
Dates:
April 7, 1998.
Pages:
3889-3890 (2 pages)
PDF File:
98-1873.pdf