02-2020. In the Matter of Earthline Technologies (Previously RMI Environmental Services), Ashtabula, OH; Order Imposing Civil Monetary Penalty  

  • Start Preamble

    I

    Earthline Technologies (previously RMI Environmental Services) was the holder of Materials License No. SMB-00602, issued by the Nuclear Regulatory Commission (NRC or Commission) on June 8, 1962. The license authorized the Licensee, in part, to conduct Start Printed Page 3918decontamination and decommissioning activities in accordance with the conditions specified therein.

    II

    An investigation of the Licensee's activities was completed on September 29, 1999. The results of this investigation indicated that the Licensee had not conducted its activities in full compliance with NRC requirements. A written Notice of Violation and Proposed Imposition of Civil Penalty (Notice) was served upon the Licensee by letter dated September 24, 2001. The Notice states the nature of the violation, the provision of the NRC's requirements that the Licensee had violated, and the amount of the civil penalty proposed for the violation.

    The Licensee responded to the Notice in a letter dated October 17, 2001. In its response, the Licensee denied the violation and protested the civil penalty. The Licensee claimed the employment action was taken for legitimate business reasons, the manager was unaware that the complainant had contacted the NRC, and the complainant did not have a material loss of benefits because he was placed on paid medical leave.

    III

    After consideration of the Licensee's response and the statements of fact, explanation, and argument for mitigation contained therein, the NRC staff has determined, that the violation occurred as stated and that the penalty proposed for the violation designated in the Notice should be imposed.

    IV

    In view of the foregoing and pursuant to Section 234 of the Atomic Energy Act of 1954, as amended (Act), 42 U.S.C. 2282, and 10 CFR 2.205, it is hereby ordered that:

    The Licensee pay a civil penalty in the amount of $17,600 within 30 days of the date of this Order, in accordance with NUREG/BR-0254. In addition, at the time of making the payment, the Licensee shall submit a statement indicating when and by what method payment was made, to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, One White Flint North, 11555 Rockville Pike, Rockville, MD 20852-2738.

    V

    The Licensee may request a hearing within 30 days of the date of this Order. Where good cause is shown, consideration will be given to extending the time to request a hearing. A request for extension of time must be made in writing to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555, and include a statement of good cause for the extension. A request for a hearing should be clearly marked as a “Request for an Enforcement Hearing” and shall be submitted to the Secretary, U.S. Nuclear Regulatory Commission, ATTN: Rulemakings and Adjudications Staff, Washington, DC 20555. Copies also shall be sent to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555, to the Assistant General Counsel for Materials Litigation and Enforcement at the same address, and to the Regional Administrator, NRC Region III, 801 Warrenville Road, Lisle, IL 60532-4351.

    If a hearing is requested, the Commission will issue an Order designating the time and place of the hearing. If the Licensee fails to request a hearing within 30 days of the date of this Order (or if written approval of an extension of time in which to request a hearing has not been granted), the provisions of this Order shall be effective without further proceedings. If payment has not been made by that time, the matter may be referred to the Attorney General for collection.

    In the event the Licensee requests a hearing as provided above, the issues to be considered at such hearing shall be:

    (a) Whether the Licensee was in violation of the Commission's requirements as set forth in the Notice referenced in Section II above, and

    (b) Whether, on the basis of such violation, this Order should be sustained.

    Start Signature

    Dated this 15th day of January 2002.

    For the Nuclear Regulatory Commission.

    Carl J. Paperiello,

    Deputy Executive Director for Materials, Research and State Programs.

    End Signature End Preamble

    [FR Doc. 02-2020 Filed 1-25-02; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Published:
01/28/2002
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
02-2020
Pages:
3917-3918 (2 pages)
Docket Numbers:
Docket No. 040-02384, License No. SMB-00602 EA-99-290
PDF File:
02-2020.pdf