03-1930. Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments  

  • Start Preamble January 22, 2003.

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:

    a. Type of Application: Preliminary Permit.

    b. Project No.: 12301-000.

    c. Date filed: July 5, 2001.

    d. Applicant: Point Marion Hydro, LLC.

    e. Name of Project: Point Marion Lock Dam Project.

    f. Location: On the Monongahela River, in Fayette County, Pennsylvania. Utilizing the U.S. Army Corps of Engineers' existing Point Marion Lock and Dam.

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)—825(r).

    h. Applicant Contact: Mr. Brent L. Smith, President, Northwest Power Services, Inc., P.O. Box 535, Rigby, ID 83442, (208)745-0834.

    i. FERC Contact: Robert Bell, (202) 219-2806.

    j. Deadline for filing motions to intervene, protests and comments: 60 days from the issuance date of this notice.

    All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under the “e-Filing” link. The Commission strongly encourages electronic filings. Please include the project number (P-12301-000) on any comments or motions filed.

    The Commission's Rules of Practice and Procedure require all interveners filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. Competing Application Project No.: 12269-000, Date Filed: June 25, 2002, Date Notice Closed: October 22, 2002.

    1. Description of Project: The proposed project using the U.S. Army Corps of Engineer's Point Marion Lock and Dam and impoundment would consist of: (1) A proposed 50-foot-long, 168-inch diameter concrete penstock, (2) a proposed powerhouse containing one generating unit having an installed capacity of 3.2 MW, (3) a proposed 1-mile-long, 25 kV transmission, and (4) appurtenant facilities.

    The project would have an annual generation of 18 GWh that would be sold to a local utility. m. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “FERRIS” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1-866-208-3676 or e-mail ferconlinesupport@ferc.gov. For TTY, call (202) 502-8659. A copy is also available for inspection and reproduction at Point Marion Hydro, LLC, 975 South State Highway, Logan, UT 84321, (435) 752-2580.

    n. Competing Applications—Public notice of the filing of the initial Start Printed Page 4193preliminary permit application, which has already been given, established the due date for filing competing preliminary permit applications or notices of intent. Any competing preliminary permit or development application or notice of intent to file a competing preliminary permit or development application must be filed in response to and in compliance with the public notice of the initial preliminary permit application. No competing applications or notices of intent to file competing applications may be filed in response to this notice. A competing license application must conform with 18 CFR 4.30 (b) and 4.36.

    o. Proposed Scope of Studies under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project.

    p. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

    q. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title “COMMENTS”, “NOTICE OF INTENT TO FILE COMPETING APPLICATION”, “COMPETING APPLICATION”, “PROTEST”, “MOTION TO INTERVENE”, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission's regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application..

    r. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency's comments must also be sent to the Applicant's representatives.

    Start Signature

    Magalie R. Salas,

    Secretary.

    End Signature End Preamble

    [FR Doc. 03-1930 Filed 1-27-03; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
01/28/2003
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
03-1930
Pages:
4192-4193 (2 pages)
Docket Numbers:
Project No. 12301-000
EOCitation:
of 2003-01-22
PDF File:
03-1930.pdf