98-2139. Trunkline Gas Company, Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 63, Number 19 (Thursday, January 29, 1998)]
    [Notices]
    [Pages 4437-4438]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-2139]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-181-000]
    
    
    Trunkline Gas Company, Notice of Request Under Blanket 
    Authorization
    
    January 23, 1998.
        Take notice that on January 13, 1998, Trunkline Gas Company 
    (Trunkline), P.O. Box 1642, Houston, Texas 77251-1642, filed in Docket 
    No. CP98-181-000 a request pursuant to Secs. 157.205 and 157.211 of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.211) for authorization to construct, own and operate certain 
    facilities to be located in Harris County, Texas, under Trunkline's 
    blanket certificate issued in Docket No. CP83-84-000 pursuant to 
    Section 7 of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        Trunkline proposes to install a 2'' hot tap, check valve, 
    insulating flange and associated facilities on its 24'' Line 100-1 in 
    Harris County at milepost 1.53, and install electronic gas measurement 
    equipment (EGM) to establish a delivery point to Cypress Public 
    Service, L.P. The new interconnect will have a design capacity up to 
    2,000 Mcf/d. The estimated cost of the proposed facilities is 
    approximately $38,820.
        Trunkline states that the construction of the proposed facilities 
    will have no effect on its peak day and annual deliveries, that its 
    existing tariff does not prohibit additional facilities, that 
    deliveries will be accomplished without detriment or disadvantage to 
    its other customers and that the total volumes delivered will not 
    exceed total volumes authorized prior to this request.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Sec. 157.205 of the 
    Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the 
    request. If no protest is filed within the time allowed therefore, the 
    proposed activity shall be deemed to be authorized effective the day 
    after the time allowed for filing a protest. If a protest is filed and 
    not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for
    
    [[Page 4438]]
    
    authorization pursuant to Section 7 of the Natural Gas Act.
    David P. Boergers,
    Acting Secretary.
    [FR Doc. 98-2139 Filed 1-28-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
01/29/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-2139
Pages:
4437-4438 (2 pages)
Docket Numbers:
Docket No. CP98-181-000
PDF File:
98-2139.pdf