01-2469. Notice of Schedule Change for Preparing the Environmental Impact Statement for the Proposed Relocation of the Los Alamos National Laboratory Technical Area 18 Missions
-
Start Preamble
AGENCY:
Department of Energy, National Nuclear Security Administration.
ACTION:
Notice of schedule change.
SUMMARY:
On May 2, 2000, the Department of Energy (DOE), National Nuclear Security Administration (NNSA), published a Notice of Intent to prepare an Environmental Impact Statement (EIS) for the Proposed Relocation of the Los Alamos National Laboratory (LANL) Technical Area 18 (TA-18) (hereafter that EIS will be referred to as the TA-18 EIS) (65 FR 25472). In that notice, the NNSA indicated that the TA-18 EIS process was scheduled to be completed by January 2001. The purpose of this notification is to inform the public that the schedule for completing the TA-18 EIS has changed. The NNSA now projects that the EIS process will not be completed before September 2001.
Start Printed Page 8103ADDRESSES:
General questions concerning the TA-18 Project can be asked by calling 1-800-832-0885, ext. 6-5484, or by writing to: Mr. Jay Rose, Document Manager, TA-18 Relocation EIS, U.S. Department of Energy/NNSA, 1000 Independence Avenue, S.W., Washington, D.C. 20585.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
For general information on the NNSA National Environmental Policy Act (NEPA) process, please contact: Mr. Henry Garson, NEPA Compliance Officer for Defense Programs, U.S. Department of Energy/NNSA, 1000 Independence Avenue, SW., Washington, DC 20585; or telephone 1-800-832-0885, ext. 30470. For general information on the DOE NEPA process, please contact: Ms. Carol M. Borgstrom, Director, Office of NEPA Policy and Compliance (EH-42), U.S. Department of Energy, 1000 Independence Avenue, SW., Washington, DC 20585, telephone 202-586-4600, or leave a message at 1-800-472-2756.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
On April 11, 2000, Secretary of Energy Bill Richardson announced that the NNSA would begin preparation of an EIS on the proposed transfer to another location of TA-18's capabilities and up to approximately 2 tons of special nuclear materials. In the Notice of Intent, published on May 2, 2000, the NNSA solicited comments on the proposed scope of the TA-18 EIS from the public and conducted public scoping meetings as follows: May 18, 2000, in Albuquerque, New Mexico; May 23, 2000, in North Las Vegas, Nevada; May 25, 2000, in Idaho Falls, ID; and May 30, 2000, in Espanola, New Mexico.
Due primarily to budget constraints, funding for the TA-18 EIS was not available during the summer of 2000 and the schedule for completing the TA-18 EIS began to slip. The events associated with the Cerro Grande fire at LANL (see 65 FR 120, June 21, 2000) further disrupted TA-18 planning activities and added to the schedule slip. The revised EIS schedule is as follows:
Issue Draft EIS—May 2001
Draft EIS Public Hearings—June 2001
Issue Final EIS—August 2001
Record of Decision—September 2001
There have been no significant changes to the TA-18 EIS scope or alternatives, as described in the original TA-18 EIS Notice of Intent.
Start SignatureIssued in Washington, DC, this 18th day of January 2001.
T.J. Glauthier,
Deputy Secretary of Energy, Department of Energy.
[FR Doc. 01-2469 Filed 1-26-01; 8:45 am]
BILLING CODE 6450-01-P
Document Information
- Published:
- 01/29/2001
- Department:
- National Nuclear Security Administration
- Entry Type:
- Notice
- Action:
- Notice of schedule change.
- Document Number:
- 01-2469
- Pages:
- 8102-8103 (2 pages)
- PDF File:
- 01-2469.pdf