96-1691. NorAm Gas Transmission Co.; Notice of Request Under Blanket Authorization
[Federal Register Volume 61, Number 20 (Tuesday, January 30, 1996)]
[Notices]
[Page 3019]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-1691]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP96-149-000]
NorAm Gas Transmission Co.; Notice of Request Under Blanket
Authorization
January 24, 1996.
Take notice that on January 19, 1996, NorAm Gas Transmission
Company (NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket
No. CP96-149-000 a request pursuant to Sections 157.205 and 157.211 of
the Commission's Regulations under the Natural Gas Act (18 CFR 157.205,
157.211) for authorization to construct and operate facilities in
Sebastian County, Arkansas under NGT's blanket certificate issued in
Docket No. CP82-384-000, et al., pursuant to Section 7 of the Natural
Gas Act, all as more fully set forth in the request that is on file
with the Commission and open to public inspection.
NGT proposes to construct and operate a 2-inch tap and 1-inch
first-cut regulator on NGT's Line 0 in Section 6, Township 5 North,
Range 31 West, to deliver gas to ARKLA a distribution division of NorAm
Energy Corp. The estimated volumes to be delivered are approximately
1,150 MMBtu annually and 5 MMBtu on a peak day. The estimated cost of
construction is $3,500 and ARKLA agrees to reimburse NGT for these
costs.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 96-1691 Filed 1-29-96; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 01/30/1996
- Department:
- Energy Department
- Entry Type:
- Notice
- Document Number:
- 96-1691
- Pages:
- 3019-3019 (1 pages)
- Docket Numbers:
- Docket No. CP96-149-000
- PDF File:
-
96-1691.pdf