96-146. Commonwealth Edison Co., (Zion Nuclear Power Station, Unit Nos. 1 and 2); Exemption  

  • [Federal Register Volume 61, Number 4 (Friday, January 5, 1996)]
    [Notices]
    [Pages 416-419]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-146]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-295 and 50-304]
    
    
    Commonwealth Edison Co., (Zion Nuclear Power Station, Unit Nos. 1 
    and 2); Exemption
    
    I
        Commonwealth Edison Company (ComEd or the licensee) is the holder 
    of Facility Operating License Nos. DPR-39 and DPR-48, which authorize 
    operation of the Zion Nuclear Power Station, Unit Nos. 1 and 2, at a 
    steady-state reactor power level not in excess of 3250 megawatts 
    thermal. The facilities are pressurized water reactors located at the 
    licensee's site in Lake County, Illinois. The licenses provide, among 
    other things, that the Zion Nuclear Power Station is subject to all 
    rules, regulations, and Orders of the U.S. Nuclear Regulatory 
    Commission (the Commission or NRC) now or hereafter in effect.
    II
        Sections III.C and III.D.3 of 10 CFR part 50, appendix J, option A, 
    require that Type C local leakage rate periodic tests shall be 
    performed during reactor shutdown for refueling, or other convenient 
    intervals, but in no case at intervals greater than 2 years. These 
    requirements are reflected in the Zion Technical Specifications (TS) as 
    requirements to perform Type C containment leakage rate testing in 
    accordance with 10 CFR part 50, appendix J, and approved exemptions.
    III
        The licensee has determined that certain containment isolation 
    pathways have not been locally leakage rate tested (Type C tests) as 
    required by option A of appendix J to 10 CFR part 50. In a letter dated 
    August 16, 1995, the licensee requested relief from the requirement to 
    perform the Type C containment leakage rate tests of certain 
    penetrations and valves in these pathways in accordance with the 
    requirements of sections III.C and III.D of 10 CFR part 50, appendix J, 
    option A. On August 16, 1995, the staff authorized in writing, 
    continued operation of the Zion units in a notice of enforcement 
    discretion (NOED) until such time as the 
    
    [[Page 417]]
    staff acted on the exemption requests. In a letter dated November 20, 
    1995, the staff granted the schedular exemptions requested in the 
    licensee's letter of August 16, 1995, and granted schedular exemptions 
    for the permanent exemption requests to allow time for additional staff 
    review and until final staff action could be taken. In its letter of 
    November 28, 1995, and supplemented on December 6, 1995, the licensee 
    requested, in part, that certain schedular exemption requests be 
    granted as permanent exemptions. As requested, the staff granted 
    permanent exemptions for the containment isolation valves in 
    containment penetrations P-70 and P-99 by letter dated December 11, 
    1995.
        The licensee's letter of November 28, 1995, also requested that the 
    following permanent exemption requests be changed to schedular 
    exemption requests.
        Units 1 and 2: P-77, 1(2)PP0101, 1(2)PP0102, 1(2)PP0103, 
    1(2)PP0104, Penetration Pressurization to Containment Valve Stations; 
    and P-102, 1(2)AOV-RC8029, Primary Water to the Pressurizer Relief 
    Tank.
        For Unit 1, the penetrations would be tested during the refueling 
    outage in the fall of 1995, and for unit 2, they would be tested during 
    the next cold shutdown of sufficient duration, and subsequently 
    thereafter as required. For P-77 and P-102, the staff's letter of 
    November 20, 1995, granted schedular exemptions until December 31, 
    1995. The final action for these penetrations is addressed below.
        The licensee's letter of November 28, 1995, also requested that the 
    staff grant a schedular exemption for penetration P-44. In a letter 
    dated December 6, 1995, the licensee withdrew the request because it 
    had recently tested the penetration for both units 1 and 2 and intends 
    to continue to test the penetration in accordance with the requirements 
    of 10 CFR part 50, appendix J, option A.
        The final resolution of the remaining issues is provided below.
    
    Pathways Listed in Licensee's Letter Dated August 16, 1995
    
        Attachment 2 of the licensee's letter of August 16, 1995, requested 
    permanent exemptions for components in the following containment 
    penetrations:
        Units 1 and 2: P-14, Valve 1(2) FCV-SA01A, Service Air Supply to 
    Containment; P-19, Valve 1(2) MOV-CC9413A, Component Cooling Water 
    Supply to the Reactor Coolant Pumps; P-34, Valve 1(2) DW0030, 
    Demineralized Flushing Water to Containment; P-43, Valve 1(2) LCV-
    DT1003, Reactor Coolant Drain Tank Pump Discharge; P-75, Valves 1(2) 
    VC8402A, 1920HCV-VC182, 1(2) VC8402B, 1(2) VC8403, Chemical and Volume 
    Control to Regenerative Heat Exchanger; P-76, Valve 1(2) VC8480A, 
    Reactor Coolant Loop Fill Header; P-77, Valves 1(2) PP0101, 1(2) 
    PP0102, 1(2) PP0103, 1(2) PP0104, Penetration Pressurization to 
    Containment Valve Stations; P-88, Valve 1(2) FCV-RV112, Containment Hot 
    Water Supply; and P-102, Valve 1(2) AOV-RC8029, Primary Water to the 
    Pressurizer Relief Tank.
        Unit 1 only: P-16, Compression Fittings on Five Reactor Vessel Leak 
    Detection System Lines.
        As stated above, the requests for P-77 and P-102 were changed from 
    permanent to schedular exemptions.
        Also, in attachment 3 of the licensee's letter of August 16, 1995, 
    the licensee requested staff concurrence concerning certain 
    clarifications for the testing of P-23, P-44, and P-66.
    
    Schedular Exemptions
    
        As requested, penetrations P-77 and P-102 will receive extensions 
    of the schedular exemptions granted on November 20, 1995, rather than 
    permanent exemptions. For Unit 1, the penetrations were tested during 
    the refueling outage which concluded on December 17, 1995, and will be 
    tested hereafter as required by Appendix J, Option A, so no further 
    exemption is needed. For Unit 2, they will be tested during the next 
    cold shutdown of sufficient duration (no later than the next refueling 
    outage), and subsequently thereafter as required. The staff's review 
    and justification for the schedular exemptions granted for these 
    penetrations on November 20, 1995, remains valid and will not be 
    repeated here. The staff finds that, on the basis stated in the 
    November 20, 1995, exemption, it is acceptable to delay the testing of 
    P-77 and P-102 until the next cold shutdown of sufficient duration, but 
    no later than the next refueling outage, for Unit 2. The next Unit 2 
    refueling outage is currently scheduled for September 1996. Further, 
    the staff finds that the special circumstances required by 10 CFR 
    50.12(a)(2)(v) are present as described in the November 20, 1995 
    exemption, namely, that the requested exemptions provide only temporary 
    relief and the licensee made good faith efforts to comply.
    
    Permanent Exemptions
    
        The licensee has requested permanent exemptions for several 
    penetrations because it is not possible to perform the required testing 
    with the current hardware configurations, such as the absence of test 
    taps or block valves that would be needed to perform the tests. In each 
    case, the relief is not from testing through-valve leakage paths, but 
    rather leakage paths out of containment isolation valves through valve 
    packing, diaphragms, or compression fittings. The permanent exemption 
    requests may be divided into three groups, as follows:
        1. P-14: The licensee proposes to test the valve packing by 
    pressurizing it with air to a pressure greater than or equal to Pa 
    and performing a soap bubble test on the packing, with an acceptance 
    criterion of zero observed bubbles. This will be done at the normal 
    Type B and C testing frequency; further, the test was performed and 
    passed during the recent Unit 1 refueling outage and during January 
    1995 for Unit 2. Generally, a soap bubble test cannot be used to 
    quantify a leakage rate, which is required by the regulation, but when 
    the observed leakage is zero (no bubbles being produced), then the 
    leakage rate is also zero. Therefore, the proposed testing method in 
    fact complies with the requirements of Appendix J, Option A, and no 
    exemption is required.
        2. P-19, P-34, P-43, P-75, P-76, P-88: In each case, the licensee 
    proposes to test the valve packing (or, in the case of P-43, the valve 
    diaphragm) by pressurizing it with water to a pressure greater than or 
    equal to 1.1 Pa and then visually examining the packing or 
    diaphragm for water leakage, with an acceptance criterion of zero 
    observed leakage. This will be done at the normal Type B and C testing 
    frequency. The significant difference between these penetrations and P-
    14 is the use of water instead of air as the test medium. The proposed 
    test, with water as the test medium and with a zero leakage acceptance 
    criterion, is conservative enough to provide reasonable assurance of no 
    significant increase in risk to health and safety of the public when 
    compared to testing with air, especially when considering the nature of 
    the potential leakage paths. The leakage pathways do not consist of 
    through-valve leakage paths, but rather leakage paths out of 
    containment isolation valves through valve packing or diaphragms. The 
    potential leakage paths are small or restrictive, through packing 
    openings or through cracks or tears in valve diaphragms. The leakage 
    path for a significant leak to occur also requires a sequence of events 
    for which the probability of occurrence is low, as detailed in the 
    licensee's letter of August 16, 1995. In addition, for some of the 
    systems, seismic support and the isolation valve seal water system 
    provide additional assurance that the risk of a significant leak is 
    minimal. 
    
    [[Page 418]]
    Therefore, the proposed testing provides an acceptable alternative to 
    the requirements of Appendix J, Option A.
        3. P-16 (Unit 1 only): The licensee proposes to test the 
    compression fittings on five small lines by pressurizing them with air 
    to a pressure greater than or equal to Pa and performing a soap 
    bubble test on the fittings, with an acceptance criterion of zero 
    observed bubbles. However, these lines cannot be locally pressurized to 
    the test pressure, so this will be done only during Type A tests, which 
    are required at a frequency of 3 times in 10 years, instead of the Type 
    B and C testing interval (every refueling outage, but not to exceed 2 
    years). The staff will accept the proposed testing frequency because 
    Type A test history at Zion Station has shown that this type of fitting 
    has not been problematic. Further, these particular fittings have never 
    caused a Type A test failure by leaking excessively. As such, the staff 
    does not expect the lesser testing frequency to significantly impact 
    the leak-tightness of the containment boundary. However, this exemption 
    is applicable only to Option A of Appendix J. If the licensee adopts 
    Option B of Appendix J for containment leakage rate testing at Zion 
    Unit 1, the exemption for P-16 is hereby revoked and the matter will 
    have to be reexamined under the requirements of Option B.
    
    Clarifications for P-23, P-44, and P-66
    
        P-23: 1(2) MOV-CC9414, CC Return from the RPC Lube Oil Coolers.
        The licensee requested staff concurrence that this valve is a 
    single barrier and that the Type C test performed on the outboard disk 
    is adequate. As stated in the staff's Request for Additional 
    Information letter of December 11, 1995, the staff concurs with the 
    licensee.
        P-44: 1(2) PR0029, Containment Sping Return Line to the 
    Containment.
        As stated above, the licensee withdrew its request and will test 
    the penetration in accordance with Appendix J, Option A.
        P-66: Reactor Coolant Pump Seal Injection System.
        The licensee requested staff concurrence that the subject system 
    may be considered a qualified water seal system for penetration P-66. 
    In its letter of November 28, 1995, the licensee provided additional 
    details as to the procedural requirements and the time frames involved 
    in the switch over from the injection phase to cold leg recirculation 
    using the containment sump as a water supply. The additional 
    information indicates that, although there may be a brief interruption 
    in sealing water pressure during switch over, the water-sealing action 
    of the system would be essentially continuous throughout the 30-day 
    post-accident period. Therefore, the staff concurs that the subject 
    system may be considered a qualified water seal system for penetration 
    P-66.
        To justify granting an exemption to the requirements of 10 CFR Part 
    50, Appendix J, Option A, a licensee must show that the requirements of 
    10 CFR 50.12(a)(1) are met. The licensee stated that all its exemption 
    requests meet the requirements of 10 CFR 50.12(a)(1), for the following 
    reasons:
    
    Criteria for Granting Exemptions are Met Per 10 CFR 50.12(a)(1)
    
        1. The requested exemptions and the activities which would be 
    allowed thereunder are authorized by law.
        If the criteria established in 10 CFR 50.12(a) are satisfied, as 
    they are in this case, and if no other prohibition of law exists to 
    preclude the activities which would be authorized by the requested 
    exemption, and there is no such prohibition, the Commission is 
    authorized by law to grant this exemption request.
        2. The requested exemption will not present undue risk to the 
    public.
        As stated in 10 CFR 50, Appendix J, Option A, the purpose of 
    primary containment leak rate testing is to assure that leakage 
    through primary containment and systems and components penetrating 
    primary containment shall not exceed the allowable leakage rate 
    values as specified by the Technical Specifications or associated 
    bases and to ensure that the proper maintenance and repairs are made 
    during the service life of the containment and systems and 
    components penetrating primary containment. The requested exemption 
    is consistent with this intent for those penetrations in that 
    alternate means of ensuring leakage remains acceptably low will be 
    performed as proposed herein.
        3. The requested exemption will not endanger the common defense 
    and security.
        The common defense and security are not in any way compromised 
    by this exemption request.
    
        In addition, the licensee must show that at least one of the 
    special circumstances, as defined in 10 CFR 50.12(a)(2) is present. One 
    of the special circumstances that a licensee may show to exist is that 
    the application of the regulation in the particular circumstance is not 
    necessary to achieve the underlying purposes of the rule. The purposes 
    of the rule, as stated in Section I of 10 CFR 50, Appendix J, Option A, 
    are to ensure that: (1) Leakage through the primary reactor containment 
    and systems and components penetrating containment shall not exceed 
    allowable values, and (2) periodic surveillance of reactor containment 
    penetrations and isolation valves is performed so that proper 
    maintenance and repairs are made. The staff has reviewed the licensee's 
    proposal and has concluded for the reasons discussed above that the 
    proposed alternative tests will confirm the integrity of the subject 
    pathways. Therefore, application of the regulation in this particular 
    circumstance is not necessary to achieve the underlying purpose of the 
    rule.
    IV
        Sections III.C and III.D.3 of 10 CFR Part 50, Appendix J, Option A, 
    require that Type C local leak rate periodic tests shall be performed 
    during reactor shutdown for refueling, or other convenient intervals, 
    but in no case at intervals greater than 2 years.
        The licensee proposes exemptions to these sections which would 
    provide relief from the requirement to perform the Type C containment 
    leak rate tests of certain valves in accordance with the requirements 
    of Sections III.C and III.D of 10 CFR Part 50, Appendix J, Option A.
        The Commission has determined that, pursuant to 10 CFR 50.12(a)(1), 
    this exemption is authorized by law, will not present an undue risk to 
    the public health and safety, and is consistent with the common defense 
    and security. The Commission further determined that special 
    circumstances, as provided in 10 CFR 50.12(a)(2) (ii), or (v) are 
    present justifying the exemption; namely, that the application of the 
    regulation is not necessary to achieve the underlying purpose of the 
    rule; or the exemptions provide only temporary relief and the licensee 
    made good faith efforts to comply.
        Therefore the Commission hereby grants the following exemptions:
    
        The requirement of 10 CFR Part 50, Appendix J, Option A, to 
    perform Type C local leakage rate periodic tests of penetrations P-
    77 and P-102 at intervals no greater than 2 years is not required. 
    For P-77 and P-102, for Unit 1, the penetrations were tested during 
    the Unit 1 refueling outage in the fall of 1995, and for Unit 2, 
    they will be tested during the next cold shutdown of sufficient 
    duration, but no later than the next refueling outage and 
    subsequently thereafter as required.
        The requirement of 10 CFR Part 50, Appendix J, Option A, to test 
    penetrations P-19, P-34, P-43, P-75, P-76, and P-88 for Units 1 and 
    2 with air is not required. Instead, the test pressure medium may be 
    water. These tests will be performed at the normal Type B and C 
    testing frequency.
        The requirement of 10 CFR Part 50, Appendix J, Option A, to test 
    penetration P-16 for Unit 1 at intervals no greater than 2 years is 
    not required. Instead, this penetration may be tested during Type A 
    tests, which are required 3 times at approximately equal intervals 
    each 10 year 
    
    [[Page 419]]
    service period. However, if the licensee adopts 10 CFR Part 50, 
    Appendix J, Option B, for containment leakage rate testing at Zion, 
    Unit 1, with the potential for Type A test intervals of 10 years, 
    the exemption for P-16 is hereby revoked.
    
        Pursuant to 10 CFR 51.32, the Commission has determined that 
    granting these exemptions will not have a significant impact on the 
    human environment (60 FR 45499).
    
        Dated at Rockville, Maryland, this 28th day of December 1995.
    
        For the Nuclear Regulatory Commission.
    Gail Marcus,
    Acting Director, Division of Reactor Projects--III/IV, Office of 
    Nuclear Reactor Regulation.
    [FR Doc. 96-146 Filed 1-4-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
01/05/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-146
Pages:
416-419 (4 pages)
Docket Numbers:
Docket Nos. 50-295 and 50-304
PDF File:
96-146.pdf