98-193. Consumers Energy Company (Big Rock Point Nuclear Plant; Exemption  

  • [Federal Register Volume 63, Number 3 (Tuesday, January 6, 1998)]
    [Notices]
    [Pages 580-581]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-193]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-155]
    
    
    Consumers Energy Company (Big Rock Point Nuclear Plant; Exemption
    
    I
    
        Consumers Energy Company (Consumers or the licensee) is the holder 
    of Facility Operating License No. DPR-6, which authorizes the licensee 
    to possess the Big Rock Point Nuclear Plant (BRP or facility). The 
    license states, among other things, that the facility is subject to all 
    rules, regulations, and orders of the U.S. Nuclear Regulatory 
    Commission (the Commission or NRC) now or hereafter in effect. The 
    facility consists of a boiling water reactor located at the licensee's 
    site in Charlevoix County, Michigan. The facility is permanently shut 
    down and defueled and is no longer authorized to operate or place fuel 
    in the reactor vessel.
    
    II
    
        Section 50.54(q) of 10 CFR part 50 requires a power reactor 
    licensee to follow and maintain in effect emergency plans that meet the 
    standards of 10 CFR 50.47(b) and the requirements of Appendix E to 10 
    CFR part 50. Section 50.47(b) provides, in part, that the offsite 
    emergency plan must meet the standards specified in subparagraphs (1) 
    through (16) of 10 CFR 50.47(b). Appendix E, Section IV.F.2.c, of 10 
    CFR part 50 requires a licensee to exercise its offsite emergency plans 
    biennially with full participation by each authorized authority having 
    a role under the plan.
        NRC may grant exemptions from the requirements of the regulations 
    which, pursuant to 10 CFR 50.12(a), are (1) authorized by law, will not 
    present an undue risk to public health and safety, and are consistent 
    with the common defense and security and (2) present special 
    circumstances. Special circumstances exist when application of the 
    regulation in the particular circumstance would not serve the 
    underlying purpose of the rule (10 CFR 50.12(a)(2)(ii)). Special 
    circumstances also exist, in part, when the exemption would provide 
    only temporary relief from the applicable regulation (10 CFR 
    50.12(a)(2)(v)). The underlying purpose of 10 CFR part 50, Appendix E, 
    Section IV.F.2.c, is to demonstrate that the emergency plans are 
    adequate and capable of being implemented and that the state of offsite 
    emergency preparedness provides reasonable assurance that adequate 
    protective measures can and will be undertaken in the event of a 
    radiological emergency.
    
    III
    
        On July 17, 1997, the licensee requested exemption from the 
    ``annual'' emergency preparedness exercise and then on August 5, 1997, 
    submitted Revision 1 to their July 17 request to clarify that they are 
    requesting exemption from the ``biennial'' offsite emergency exercise 
    requirement of 10 CFR part 50, Appendix E, Section IV.F.2.c. In a 
    letter dated July 22, 1997, the licensee described the scope and 
    objectives for the planned offsite emergency plan exercise, involving 
    the State of Michigan and each authorized authority having a role under 
    the plan.
        On August 8, 1997, the licensee requested a schedular exemption to 
    defer the October 21, 1997, offsite exercise to June 1998 to allow 
    additional time for the BRP staff to revise the exercise scenario to 
    reflect the permanently shut down and defueled condition of the BRP 
    facility. Then, on August 22, 1997, Consumers gave notice that the 
    current offsite exercise scenario (reflecting an operating nuclear 
    power plant) will be forwarded to the NRC Region III office, as 
    required. Consumers then rescheduled the offsite exercise to December 
    16, 1997 (within the biennial time period stipulated by the regulations 
    and, thus, not requiring an exemption from NRC requirements). On 
    September 4, 1997, the licensee provided additional clarification of 
    its reasons to defer the 1997 offsite exercise until June 1998. These 
    reasons included, in part, a discussion concluding that the exercise 
    would result in ``significant resource expenditure by the company and 
    outside agencies'' and a reference to an NRC Initial Decision dated 
    August 29, 1984, regarding the licensee's amendment request to expand 
    the spent fuel storage capacity of the BRP spent fuel pool. Therefore, 
    the licensee requested only temporary relief (10 CFR 50.12(a)(2)(v)) 
    from 10 CFR part 50, Appendix E, Section IV.F.2.c.
        On September 19, 1997, Consumers submitted a number of documents 
    reflecting the permanent cessation of power operations and the defueled 
    condition of BRP, including, in part, the BRP Defueled Technical 
    Specifications and the Defueled Emergency Plan. This submittal also 
    contained a request for exemption from the requirements of 10 CFR part 
    50, Appendix E, Section IV.F.2.c, because, as Consumers asserted, there 
    are ``no design basis or other credible events that would result in 
    doses beyond the site area boundary that would exceed the EPA PAGs 
    [Environmental Protection Agency Protective Action Guides] following 68 
    days post shutdown (11/5/97).'' The September 19, 1997, exemption 
    request is still undergoing NRC staff review.
        In a letter to Federal Emergency Management Agency (FEMA) Region V, 
    dated November 25, 1997, the State of Michigan stated that ``requiring 
    the state and counties to conduct an exercise at this time, based on 
    assumptions of an operating full power reactor, would be unrealistic 
    and counter-productive to all parties involved.'' The State further 
    asserted that a ``more realistic test of local and state capabilities 
    would be to assess response to an accident once all plans and 
    procedures have been revised to reflect the new status of the plant.'' 
    The State of Michigan's position was again documented to FEMA Region V 
    in a letter dated December 5, 1997.
        By letter dated December 9, 1997, Consumers informed the Commission 
    that they have reasonable assurance that the offsite emergency plan is 
    adequate and that appropriate measures can be taken to protect the 
    health and safety of the public in the event of a radiological 
    emergency at BRP to support a postponement in the conduct of the 
    offsite exercise. The licensee based its determination on the 
    successful performance of the 1995 full-participation offsite/onsite 
    emergency exercise, the 1996 onsite emergency exercise, and the conduct 
    of emergency plan drills.
        By letter dated December 17, 1997, FEMA informed the NRC that, 
    based on its evaluation, ``the offsite radiological emergency response 
    plans and preparedness are adequate and that there is reasonable 
    assurance that they can be implemented to protect the health and safety 
    of the public in the event of an emergency'' at the BRP facility. 
    Further, FEMA supports the rescheduling of the 1997 offsite exercise to 
    a date within the first quarter of 1998 and the revision of the offsite 
    exercise
    
    [[Page 581]]
    
    scenario to reflect the permanently shut down and defueled condition of 
    the BRP facility.
        The most recent NRC Systematic Assessment of Licensee Performance 
    (SALP 13, Report No. 50-155/96001) for BRP, issued on December 6, 1996, 
    for the period May 1, 1994, through November 25, 1995, indicated that 
    the performance of the emergency preparedness program was good. NRC 
    Inspection Report No. 50-155/95010 documented NRC staff inspection of 
    the onsite portion of the August 1995 exercise and concluded that, 
    overall, there was acceptable performance with no violations of NRC 
    requirements identified. Additionally, NRC Inspection Report No. 50-
    155/97003, dated May 13, 1997, evaluated the onsite portions of the BRP 
    emergency preparedness program and concluded that the overall 
    effectiveness of emergency preparedness facilities, equipment, 
    training, and organization was very good and that the licensee had 
    conservatively implemented the emergency plan in declaring three 
    separate Unusual Events in 1996. Therefore, there is reasonable 
    assurance that onsite plans, facilities, and personnel are adequate and 
    in place to respond to a radiological emergency at BRP.
        In the permanently shut down and defueled condition, BRP is no 
    longer susceptible to any of the operating type of reactor accidents 
    and events, as described in Chapter 15 of the BRP Final Hazards Summary 
    Report. Further, by letters dated February 27, 1995, and August 5, 
    September 4 and 19, and November 12 and 20, 1997, the licensee provided 
    credible analysis of accidents and events that could possibly occur 
    during BRP decommissioning. These accidents and events included, in 
    part, those described in NUREG-0586, ``Final Generic Environmental 
    Impact Statement on decommissioning nuclear facilities,'' and NUREG/CR-
    0672, ``Technology, Safety, and Costs of Decommissioning Reference 
    Boiling Water Reactor Power Station.'' Consumers also evaluated (1) a 
    release of gap radioactive isotopes from all spent fuel, (2) gamma 
    shine resulting from a complete draindown of the spent fuel pool, and 
    (3) an airborne release of radioactive isotopes from primary system 
    chemical decontamination. Further, Consumers stated that they will not 
    perform any decommissioning activities that result in significant 
    environmental impacts not previously reviewed (10 CFR 50.82(a)(6)(ii)). 
    The licensee has also provided reasonable assurance that the 
    environmental impacts associated with the decommissioning of the BRP 
    facility are bounded by appropriate previously issued environmental 
    impact statements and that the above-mentioned accidents and events 
    would not result in offsite doses exceeding EPA PAGs.
        Based upon the aforementioned NRC and FEMA findings regarding 
    onsite and offsite preparedness, respectively, the exemption will not 
    present an undue risk to public health and safety. Additionally, the 
    schedule for future exercises will not be affected by this exemption. 
    The NRC staff is still reviewing licensee request for exemption from 
    certain 10 CFR Part 50 requirements for emergency planning (Consumers' 
    letter to the Commission dated September 19, 1997). Therefore, the 
    licensee is still required to comply with all NRC rules and regulations 
    and their current emergency plan, as approved or until revised by 
    subsequent Commission action.
    
    IV
    
        The NRC staff has completed its review of the licensee's request 
    for schedular exemption from the requirement to conduct an offsite 
    emergency preparedness exercise in calender year 1997 and FEMA's letter 
    dated December 17, 1997, stating FEMA's determination that the offsite 
    radiological emergency plans and preparedness of the State and local 
    offsite emergency preparedness staffs are adequate and that there is 
    reasonable assurance that protective measures can be implemented 
    following a radiological emergency at the BRP facility. Based on this 
    review, the NRC staff finds that the underlying purposes of the 
    regulation will not be adversely affected by delaying the 1997 offsite 
    emergency preparedness exercise for a period not to exceed 90 days 
    commencing on January 1, 1998. Thus, an offsite exercise in calendar 
    year 1997 is not necessary to achieve the underlying purpose of the 
    rule and the requested exemption, as modified herein, will not 
    adversely affect the overall state of emergency preparedness at the BRP 
    site.
        For these reasons, the Commission has determined that, pursuant to 
    10 CFR 50.12, a 90-day schedular exemption commencing on January 1, 
    1998, as discussed above, is authorized by law, will not present undue 
    risk to public health and safety, and is consistent with the common 
    defense and security. Further, special circumstances are present as set 
    forth in 10 CFR 50.12(a)(2)(ii) and (v).
        Pursuant to 10 CFR 51.32, the Commission has determined that 
    granting this exemption will have no significant impact on the 
    environment (62 FR 67667).
        This Exemption is effective upon issuance.
    
        Dated at Rockville, Maryland, this 30th day of December 1997.
        For the Nuclear Regulatory Commission.
    Samuel J. Collins,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-193 Filed 1-5-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
01/06/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-193
Pages:
580-581 (2 pages)
Docket Numbers:
Docket No. 50-155
PDF File:
98-193.pdf