E5-12. Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments
-
Start Preamble
December 30, 2004.
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12557-000.
c. Date Filed: November 12, 2004.
d. Applicant: SBER Royal Mills, LLC.
e. Name of Project: Royal Mills Project.
f. Location: On the South Branch Pawtuxet River, in Kent County, Rhode Island. No federal land or facilities would be used.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Paul V. Nolan, 5515 North 17th Street, Arlington, VA 22205, (703) 534-5509.
i. FERC Contact: Robert Bell, (202) 502-6062.
j. Deadline for Filing Comments, Protests, and Motions To Intervene: 60 days from the issuance date of this notice.
The Commission's Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.
k. Description of Project: The proposed project would consist of: (1) An existing 1100-foot-long, 21-foot-high granite block gravity dam, (2) an existing reservoir having a surface area of 3.8 acres with a storage capacity of 15.2 acre-feet and a maximum water surface elevation of 79.1 feet National Geographic Vertical Datum, (3) an existing power canal intake, (4) an existing 150-foot-long, 40-foot-wide power canal, (5) three proposed 66-inch diameter riveted steel penstocks 80, 110, and 120 feet long, (6) an existing powerhouse containing three proposed generating units having a total installed capacity of 200 kilowatts, (7) an existing 280-foot-long, 40-foot wide tailrace, (8) a proposed 660-foot-long, 23 kilovolt underground transmission line; and (9) appurtenant facilities. The project would have an annual generation of 1.071 gigawatt-hours that would be sold to a local utility.
l. Locations of Applications: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room, located at 888 First Street NE., Room 2A, Washington DC 20426, or by calling (202) 502-8371. This filing may also be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or TTY, contact (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h. above.
m. Individuals desiring to be included on the Commission's mailing list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit: Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36.
p. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice.
q. Proposed Scope of Studies Under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project.
r. Comments, Protests, or Motions To Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.
Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under “e-filing” link. The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title “COMMENTS”, “RECOMMENDATIONS FOR TERMS AND CONDITIONS”, “PROTEST”, OR “MOTION TO INTERVENE”, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission's regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Start Printed Page 1235A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application.
t. Agency Comments—Federal, State, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency's comments must also be sent to the Applicant's representatives.
Start SignatureMagalie R. Salas,
Secretary.
[FR Doc. E5-12 Filed 1-5-05; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 01/06/2005
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- E5-12
- Pages:
- 1234-1235 (2 pages)
- EOCitation:
- of 2004-12-30
- PDF File:
- e5-12.pdf