99-351. ECK Generating, S.R.O., et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 64, Number 5 (Friday, January 8, 1999)]
    [Notices]
    [Pages 1193-1197]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-351]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. EG99-14-000, et al.]
    
    
    ECK Generating, S.R.O., et al.; Electric Rate and Corporate 
    Regulation Filings
    
    December 31, 1998.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. ECK Generating, S.R.O.
    
    [Docket No. EG99-14-000]
    
        Take notice that on December 18, 1998, ECK Generating, S.R.O. 
    (Applicant), with its principal offices at Kladno, Dubska, Teplarna 272 
    03, filed with the Federal Energy Regulatory Commission (the 
    Commission) an amended application for determination of exempt 
    wholesale generator status pursuant to Part 365 of the Commission's 
    Regulations. The Amendment supplements the Application filed on October 
    23, 1998, to provide additional information.
        The Application and Amendment state that the Applicant is a limit 
    liability company organized under the laws of the Czech Republic that 
    will own a portion of and lease a portion of a 344 MW generating plant 
    near the City of Kladno in the Czech Republic. Applicant states that it 
    will be engaged directly, or indirectly through one or more affiliates, 
    as defined in Section 2(a)(11)(B) of PUHCA, and exclusively in the 
    business of owning and or/operating, an undivided interest in this 
    facility and selling electric energy at wholesale and making permitted 
    foreign retail electric sales.
        Comment date: January 25, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy of the application.
    
    2. Little Bay Power Corporation
    
    [Docket No. EG99-49-000]
    
        Take notice that on December 22, 1998, Little Bay Power 
    Corporation, a corporation organized under the laws of the State of New 
    Hampshire, tendered for filing with the Federal Energy Regulatory 
    Commission (Commission) an application for determination of exempt 
    wholesale generator status pursuant to Part 365 of the Commission's 
    Regulations.
        The Applicant states that it is engaged directly and exclusively in 
    the business of owning a 2.9 percent undivided interest (the Seabrook 
    Interest) in the Seabrook Nuclear Power Plant (the Seabrook Plant) and 
    selling at wholesale its entitlement to a pro rata share of the 
    capacity and energy from the Seabrook Plant. The Seabrook Plant is a 
    nuclear-fueled electricity generating plant located in Seabrook, New 
    Hampshire, consisting of a pressurized water reactor with a rated 
    capacity of 1,150 megawatts. The Seabrook Plant includes 
    interconnecting transmission facilities that interconnect the Seabrook 
    Plant with the transmission facilities of Public Service Company of New 
    Hampshire. The Applicant requests a determination that, the Applicant 
    will be an exempt wholesale generator under Section 32(a)(1) of the 
    Public Utility Holding Company Act of 1935.
        The Applicant further states that copies of the application were 
    served upon the Securities and Exchange Commission and the New 
    Hampshire Public Utilities Commission.
        Comment date: January 22, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy of the application.
    
    3. Zhengzhou Huadeng Power Company Ltd.
    
    [Docket No. EG99-50-000]
    
        Take notice that on December 23, 1998, Zhengzhou Huadeng Power 
    Company Ltd. (Huadeng), a Chinese
    
    [[Page 1194]]
    
    cooperative joint venture, tendered for filing with the Federal Energy 
    Regulatory Commission an application for determination of exempt 
    wholesale generator status pursuant to Part 365 of the Commission's 
    Regulations.
        Huadeng is a company established for the purpose of owning a 55 MW 
    coal-fired power project in Dengfeng Municipality, Henan Province 
    (Project) for the generation and sales of wholesale electric power to 
    utilities and retail electric power to industrial end users in the 
    People's Republic of China. The sponsors of the Project and their 
    respective interests are as follows: Henan Dengfeng Power Group Company 
    Limited (Power Group) (51%) and Western Resources International Limited 
    (49%).
        Comment date: January 22, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy of the application.
    
    4. Zhengzhou Huaxin Power Company Ltd.
    
    [Docket No. EG99-51-000]
    
        Take notice that on December 23, 1998, Zhengzhou Huaxin Power 
    Company Ltd. (Huaxin), a Chinese cooperative joint venture, tendered 
    for filing with the Federal Energy Regulatory Commission an application 
    for determination of exempt wholesale generator status pursuant to Part 
    365 of the Commission's Regulations.
        Huaxin is a company established for the purpose of owning a 55 MW 
    coal-fired power project in Dengfeng Municipality, Henan Province 
    (Project) for the generation and sales of wholesale electric power to 
    utilities and retail electric power to industrial end users in the 
    People's Republic of China. The sponsors of the Project and their 
    respective interests are as follows: Henan Dengfeng Power Group Company 
    Limited (Power Group) (51%) and Western Resources International Limited 
    (49%).
        Comment date: January 22, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy of the application.
    
    5. Washington Water Power Company
    
    [Docket No. ER98-3439-000]
    
        Take notice that on December 28, 1998, Washington Water Power 
    Company (WWP), amended its filing of a revision/replacement to its Rate 
    Schedule FERC No. 148 with the Federal Energy Regulatory Commission.
        WWP requests an effective date of June 22, 1998.
        A copy of this filing has been served upon The Spokane Tribe of 
    Indians, The United States Bureau of Reclamation, and the Washington 
    Utilities and Transportation Commission.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    6. New England Power Company
    
    [Docket No. ER99-597-000]
    
        Take notice that on December 28, 1998, New England Power Company 
    (NEP), tendered for filing an amendment to its November 13, 1998, 
    filing in the above-referenced docket. The November 13th filing 
    concerned the code of conduct governing the relationship between NEP 
    and its affiliates.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    7. Great Bay Power Corporation
    
    [Docket No. ER99-1042-000]
    
        Take notice that on December 28, 1998, Great Bay Power Corporation 
    (Great Bay), tendered for filing a service agreement between Select 
    Energy, Inc., and Great Bay for service under Great Bay's revised 
    Tariff for Short Term Sales. This Tariff was accepted for filing by the 
    Commission on July 24, 1998, in Docket No. ER98-3470-000.
        The service agreement is proposed to be effective December 22, 
    1998.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    8. Entergy Services, Inc.
    
    [Docket No. ER99-1043-000]
    
        Take notice that on December 28, 1998, Entergy Services, Inc. 
    (Entergy Services), on behalf of Entergy Arkansas, Inc., Entergy Gulf 
    States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and 
    Entergy New Orleans, Inc. (collectively, the Entergy Operating 
    Companies), tendered for filing a Power Purchase Agreement between 
    Entergy Services, as agent for the Entergy Operating Companies, and 
    Southern Company Services, Inc., for the sale of power under Entergy 
    Services' Rate Schedule SP.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    9. Entergy Services, Inc.
    
    [Docket No. ER99-1044-000]
    
        Take notice that on December 28, 1998, Entergy Services, Inc. 
    (Entergy Services), on behalf of Entergy Arkansas, Inc., Entergy Gulf 
    States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and 
    Entergy New Orleans, Inc. (collectively, the Entergy Operating 
    Companies), tendered for filing an amendment to its a Power and Energy 
    Agreement with Municipal Energy Agency of Mississippi, which was filed 
    in Docket No. ER99-218 in compliance with the Commission's order in 
    Clarksdale Public Utilities Commission v. Entergy Services, Inc., 85 
    FERC para. 61,268 (1998). The amendment addresses compensation for 
    losses.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    10. Entergy Services, Inc.
    
    [Docket No. ER99-1045-000]
    
        Take notice that on December 28, 1998, Entergy Services, Inc. 
    (Entergy Services), on behalf of Entergy Arkansas, Inc., Entergy Gulf 
    States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and 
    Entergy New Orleans, Inc. (collectively, the Entergy Operating 
    Companies), tendered for filing a modified form of Network Integration 
    Transmission Service Agreement with itself, to cover deliveries under 
    its Power and Energy Agreement with Municipal Energy Agency of 
    Mississippi. The Power and Energy Agreement was filed in Docket No. 
    ER99-218 in compliance with the Commission's order in Clarksdale Public 
    Utilities Commission v. Entergy Services, Inc., 85 FERC para. 61,268 
    (1998).
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    11. Entergy Services, Inc.
    
    [Docket No. ER99-1046-000]
    
        Take notice that on December 28, 1998, Entergy Services, Inc. 
    (Entergy Services), on behalf of Entergy Arkansas, Inc., tendered for 
    filing the Second Amendment to the Agreement for Wholesale Power 
    Service between Entergy Arkansas, Inc., and Farmers Electric 
    Cooperative Corporation.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    12. Texas-New Mexico Power Company
    
    [Docket No. ER99-1047-000]
    
        Take notice that on December 28, 1998, Texas-New Mexico Power 
    Company (TNP), tendered for filing under TNP's Market-Based Rate Tariff 
    an executed Service Agreement for Negotiated Market-Based Rates and 
    companion Power Sale Agreement with Southwestern Public Service Company 
    (SPS) as the customer.
        TNP has requested an effective date of January 1, 1999, for 
    capacity and energy
    
    [[Page 1195]]
    
    sales by TNP to SPS at market-based rates under these Agreements. 
    Service to be provided under these Agreements is for one year.
        A copy of this filing was served upon SPS.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    13. Texas-New Mexico Power Company
    
    [Docket No. ER99-1048-000]
    
        Take notice that on December 28, 1998, Texas-New Mexico Power 
    Company (TNP), tendered for filing a Network Operating Agreement and 
    companion Service Agreement for Network Integration Transmission 
    Service between TNP and Southwestern Public Service Company (SPS). By 
    these Agreements, TNP will provide continued network integration 
    network transmission service to SPS for a five-year period, starting on 
    January 1, 1999, pursuant to TNP's Open Access Transmission Tariff on 
    file with the Commission.
        TNP requests an effective date of January 1, 1999, for service to 
    commence under these Agreements. TNP requests waiver of the 
    Commission's 60-day notice period to permit these Agreements to take 
    effect on January 1.
        A copy of this filing was served upon SPS.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    14. Select Energy, Inc.
    
    [Docket No. ER99-1049-000]
    
        Take notice that on December 28, 1998, Select Energy, Inc. 
    (Select), tendered for filing, a Service Agreement with the 
    Constellation Power Source under the Select Energy, Inc., Market-Based 
    Rates, Tariff No. 1.
        Select Energy, Inc., states that a copy of this filing has been 
    mailed to the Constellation Power Source.
        NUSCO requests that the Service Agreement become effective December 
    1, 1998.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    15. Allegheny Power Service Corp., on Behalf of Monongahela Power 
    Co., the Potomac Edison Company, and West Penn Power Company 
    (Allegheny Power)
    
    [Docket No. ER99-1050-000]
    
        Take notice that on December 28, 1998, Allegheny Power Service 
    Corporation on behalf of Monongahela Power Company, The Potomac Edison 
    Company and West Penn Power Company (Allegheny Power), tendered for 
    filing Supplement No. 43, to add three (3) new Customers to the 
    Standard Generation Service Rate Schedule under which Allegheny Power 
    offers standard generation and emergency service on an hourly, daily, 
    weekly, monthly or yearly basis.
        Allegheny Power requests a waiver of notice requirements to make 
    service available as of January 1, 1999, to Monongahela Power Company, 
    The Potomac Edison Company and West Penn Power Company.
        Copies of the filing have been provided to the Public Utilities 
    Commission of Ohio, the Pennsylvania Public Utility Commission, the 
    Maryland Public Service Commission, the Virginia State Corporation 
    Commission, the West Virginia Public Service Commission, and all 
    parties of record.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    16. Washington Water Power Company
    
    [Docket No. ER99-1051-000]
    
        Take notice that on December 28, 1998, The Washington Water Power 
    Company (WWP), tendered for filing with the Federal Energy Regulatory 
    Commission an amendment to the Firm Point-to-Point Service Agreement 
    with Clearwater Power Company under WWP's Open Access Transmission 
    Tariff, Second Revised Volume No. 8.
        WWP requests an effective date of November 29, 1998.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    17. Salko Energy Services, Inc.
    
    [Docket No. ER99-1052-000]
    
        Take notice that on December 28, 1998, Salko Energy Services, Inc. 
    (SES), petitioned the Commission for acceptance of SES Rate Schedule 
    FERC No. 1; the granting of certain blanket approvals, including the 
    authority to sell electricity at market-based rates; and the waiver of 
    certain Commission regulations.
        SES intends to engage in wholesale electric power and energy 
    purchases and sales as a marketer. SES is not in the business of 
    generating or transmitting electric power. SES has no affiliates.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    18. Upper Peninsula Power Company
    
    [Docket No. ER99-1053-000]
    
        Take notice that on December 28, 1998, Upper Peninsula Power 
    Company (UPPCo), tendered for filing with the Federal Energy Regulatory 
    Commission (Commission) an amended and restated Interconnection 
    Agreement executed between UPPCo and the Marquette Board of Light and 
    Power (Board). The Interconnection Agreement is amended to reflect the 
    sale of a tie line and related facilities from UPPCo to the Board.
        UPPCO requests that the Commission accept this amended and restated 
    Interconnection Agreement for filing effective on the same date as 
    Commission approves the Application filed by UPPCo in Docket No. EC99-
    13-000 to transfer the subject transmission facilities.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    19. Public Service Company of New Mexico
    
    [Docket No. ER99-1054-000]
    
        Take notice that on December 28, 1998, Public Service Company of 
    New Mexico (PNM), tendered for filing two executed service agreements, 
    with UtiliCorp United Inc., dated December 18, 1998, (one for non-firm 
    and one for short-term firm point-to-point transmission service) under 
    the terms of PNM's Open Access Transmission Service Tariff. PNM's 
    filing is available for public inspection at its offices in 
    Albuquerque, New Mexico.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    20. Public Service Company of New Mexico
    
    [Docket No. ER99-1055-000]
    
        Take notice that on December 28, 1998, Public Service Company of 
    New Mexico (PNM), tendered for filing an executed service agreement, 
    for electric power and energy sales at negotiated rates under the terms 
    of PNM's Power and Energy Sales Tariff, with Utah Municipal Power 
    Agency (dated December 22, 1998). PNM's filing is available for public 
    inspection at its offices in Albuquerque, New Mexico.
        Copies of the filing have been sent to Utah Municipal Power Agency 
    and to the New Mexico Public Utility Commission.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    [[Page 1196]]
    
    21. Public Service Company of New Mexico
    
    [Docket No. ER99-1056-000]
    
        Take notice that on December 28, 1998, Public Service Company of 
    New Mexico (PNM), tendered for filing an executed service agreement 
    (dated December 3, 1998) with Enron Power Marketing, Inc. (Enron), for 
    short-term firm point to point transmission service under PNM's Open 
    Access Transmission Tariff; and a unilaterally executed service 
    agreement (dated December 22, 1998) with Enron for electric power and 
    energy sales at negotiated rates under the terms of PNM's Power and 
    Energy Sales Tariff. PNM's filing is available for public inspection at 
    its offices in Albuquerque, New Mexico.
        Copies of the filing have been sent to Enron and to the New Mexico 
    Public Utility Commission.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    22. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1057-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Corporation 
    (Niagara Mohawk), that effective the January 11, 1999, Rate Schedule 
    FERC No. 219, effective date June 19, 1995, and any supplements 
    thereto, and filed with the Federal Energy Regulatory Commission by 
    Niagara Mohawk Power Corporation is to be canceled.
        Notice of the proposed cancellation has been served upon CMEX 
    Energy, Inc.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    23. Niagara Mohawk Power Corp.
    
    [Docket No. ER99-1058-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing effective January 11, 
    1999, Rate Schedule FERC No. 244, effective date May 13, 1996, and any 
    supplements thereto, and filed with the Federal Energy Regulatory 
    Commission by Niagara Mohawk Power Corporation is to be canceled.
        Notice of the proposed cancellation has been served upon Noram 
    Energy Services.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    24. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1059-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing notice that effective 
    January 11, 1999, Rate Schedule FERC No. 246, effective date May 13, 
    1996, and any supplements thereto, and filed with the Federal Energy 
    Regulatory Commission by Niagara Mohawk Power Corporation is to be 
    canceled.
        Notice of the proposed cancellation has been served upon MidCon 
    Power Services Corporation.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    25. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1060-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing notice that effective 
    December 11, 1998, Rate Schedule FERC No. 221, effective date May 18, 
    1995, and any supplements thereto, and filed with the Federal Energy 
    Regulatory Commission by Niagara Mohawk Power Corporation is to be 
    canceled.
        Notice of the proposed cancellation has been served upon Rainbow 
    Energy Marketing Corporation.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    26. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1061-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing notice that effective 
    January 11, 1999, Rate Schedule FERC No. 217, effective date May 31, 
    1995, and any supplements thereto, and filed with the Federal Energy 
    Regulatory Commission by Niagara Mohawk Power Corporation is to be 
    canceled.
        Notice of the proposed cancellation has been served upon Utility 
    2000 Energy Corporation.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    27. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1062-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing notice that effective 
    December 11, 1998, Rate Schedule FERC No. 211, effective date February 
    22, 1995, and any supplements thereto, and filed with the Federal 
    Energy Regulatory Commission by Niagara Mohawk Power Corporation is to 
    be canceled.
        Notice of the proposed cancellation has been served upon CNG Gas 
    Services Corporation.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    28. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1063-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing notice that effective 
    the January 11, 1999, Rate Schedule FERC No. 240, effective date 
    February 12, 1996, and any supplements thereto, and filed with the 
    Federal Energy Regulatory Commission by Niagara Mohawk Power 
    Corporation is to be canceled.
        Notice of the proposed cancellation has been served upon KN 
    Marketing, Inc.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    29. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-1064-000]
    
        Take notice that on December 28, 1998, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing notice that effective 
    January 11, 1999, Rate Schedule FERC No. 239, effective date January 2, 
    1996, and any supplements thereto, and filed with the Federal Energy 
    Regulatory Commission by Niagara Mohawk Power Corporation is to be 
    canceled.
        Notice of the proposed cancellation has been served upon Koch Power 
    Services, Inc.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    30. Unitil Power Corporation
    
    [Docket No. ER99-1065-000]
    
        Take notice that on December 28, 1998, Unitil Power Corporation in 
    accordance with Section 35.3, 18 CFR 35.3, the Unitil Companies, 
    Concord Electric Company, Exeter & Hampton Electric Company and Unitil 
    Power Corp. (collectively Unitil), notified the Commission, that due to 
    developments that transpired at the state level, it will not move the 
    Amended System Agreement among Unitil Power Corp. (Amended System 
    Agreement), into effect on March 1, 1999.
    
    [[Page 1197]]
    
        Copies of the filing were served upon all parties to the underlying 
    proceeding.
        Comment date: January 19, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    Standard Paragraphs
    
        E. Any person desiring to be heard or to protest said filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
    in accordance with Rules 211 and 214 of the Commission's Rules of 
    Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
    motions or protests should be filed on or before the comment date. 
    Protests will be considered by the Commission in determining the 
    appropriate action to be taken, but will not serve to make protestants 
    parties to the proceeding. Any person wishing to become a party must 
    file a motion to intervene. Copies of these filings are on file with 
    the Commission and are available for public inspection.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-351 Filed 1-7-99; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
01/08/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-351
Dates:
January 25, 1999, in accordance with Standard Paragraph E at the end of this notice. The Commission will limit its consideration of comments to those that concern the adequacy or accuracy of the application.
Pages:
1193-1197 (5 pages)
Docket Numbers:
Docket No. EG99-14-000, et al.
PDF File: