2020-27908. Design Criteria for Dam and Lake Projects  

  • Start Preamble

    AGENCY:

    U.S. Army Corps of Engineers, Department of Defense.

    ACTION:

    Final rule.

    SUMMARY:

    This final rule removes the U.S. Army Corps of Engineers' part titled Design Criteria for Dam and Lake Projects. This part is out-of-date and otherwise covers internal agency operations that have no public compliance component or adverse public impact. Therefore, this part can be removed from the Code of Federal Regulations (CFR).

    DATES:

    This rule is effective on January 8, 2021.

    ADDRESSES:

    Department of the Army, U.S. Army Corps of Engineers, ATTN: CECW-EC (Mr. Robert Bank), 441 G Street NW, Washington, DC 20314-1000.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Mr. Robert Bank at (202) 761-5532 or by email at Robert.Bank@usace.army.mil.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    This final rule removes from the 33 CFR part 220, Design Criteria for Dam and Lake Projects providing policy, design, and report requirements for low level discharge facilities for drawdown of lakes to be impounded by Corps Civil Works projects. The rule was initially published in the Federal Register on May 8, 1975 (40 FR 20081), and amended on August 22, 1975 (40 FR 36774). While the rule applies only to Corps design criteria on Corps dam and lake projects, it was published, at that time, in the Federal Register to aid public accessibility.

    The solicitation of public comment for this removal is unnecessary because the rule is out-of-date, duplicative of existing internal agency guidance, and otherwise covers internal agency operations that have no public compliance component or adverse public impact. For current public accessibility purposes, updated internal agency policy on this topic may be found in Engineer Manual 1110-2-1602, “Hydraulic Design of Reservoir Outlet Works” (available at https://www.publications.usace.army.mil/​Portals/​76/​Publications/​EngineerManuals/​EM_​1110-2-1602.pdf). The agency policy is only applicable to field operating activities having responsibility for the design of Corps Civil Works projects and provides guidance specific to the Corps' hydraulic design analysis of reservoir outlet works facilities.

    This rule removal is being conducted to reduce confusion for the public as well as for the Corps regarding the current policy which governs the Corps' design criteria for Corps dam and lake projects. Because the regulation does not place a burden on the public, its removal does not provide a reduction in public burden or costs.

    This rule is not significant under Executive Order (E.O.) 12866, “Regulatory Planning and Review.” Therefore, the requirements of E.O. 13771, “Reducing Regulation and Controlling Regulatory Costs,” do not apply. This removal supports a recommendation of the DoD Regulatory Reform Task Force.

    Start List of Subjects

    List of Subjects in 33 CFR Part 220

    • Dams
    • Flood control
    End List of Subjects Start Part Start Printed Page 1279

    PART 220—[REMOVED]

    End Part Start Amendment Part

    Accordingly, for the reasons stated in the preamble and under the authority of 5 U.S.C. 301, the Corps removes 33 CFR part 220.

    End Amendment Part Start Signature

    R.D. James,

    Assistant Secretary of the Army (Civil Works).

    End Signature End Supplemental Information

    [FR Doc. 2020-27908 Filed 1-7-21; 8:45 am]

    BILLING CODE 3720-58-P

Document Information

Effective Date:
1/8/2021
Published:
01/08/2021
Department:
Engineers Corps
Entry Type:
Rule
Action:
Final rule.
Document Number:
2020-27908
Dates:
This rule is effective on January 8, 2021.
Pages:
1278-1279 (2 pages)
Docket Numbers:
COE-2020-0009
RINs:
0710-AA85: Design Criteria for Dam and Lake Projects
RIN Links:
https://www.federalregister.gov/regulations/0710-AA85/design-criteria-for-dam-and-lake-projects
Topics:
Dams, Flood control
PDF File:
2020-27908.pdf
Supporting Documents:
» Design Criteria for Dam and Lake Projects
CFR: (1)
33 CFR 220