96-286. Northeast UtilitiesMillstone Nuclear Power Station, Unit 1; Issuance of Director's Decision Under 10 CFR 2.206  

  • [Federal Register Volume 61, Number 6 (Tuesday, January 9, 1996)]
    [Notices]
    [Pages 671-672]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-286]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-245]
    
    
    Northeast Utilities--Millstone Nuclear Power Station, Unit 1; 
    Issuance of Director's Decision Under 10 CFR 2.206
    
        In notice document 95-31255 beginning on page 66807, in the issue 
    of Tuesday, December 26, 1995, the complete text of the ``Director's 
    Decision Pursuant to 10 CFR 2.206'' (DD-95-23) was not included. The 
    complete text follows this correction notice.
    
        Dated at Rockville, Maryland this 3rd day of January 1996.
    
        For the Nuclear Regulatory Commission.
    James W. Andersen,
    Project Manager, Project Directorate I-3, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    
    I. Introduction
    
        On January 8, 1995, Mr. Anthony J. Ross (Petitioner) filed a 
    Petition with the Executive Director for Operations of the U.S. Nuclear 
    Regulatory Commission (NRC) pursuant to 10 CFR 2.206. In the Petition, 
    the Petitioner raised concerns regarding the site paging and site siren 
    evacuation alarm system in the Millstone Nuclear Power Station, Unit 1 
    maintenance shop.
        The Petitioner alleged that on numerous occasions since January 
    1994, his department manager had instructed the Petitioner's coworkers 
    to shut off or turn down the volume on the site paging and site siren 
    evacuation alarm system in the Millstone Unit 1 maintenance shop, and 
    the Petitioner's first-line supervisor and coworker had complied with 
    this request in violation of Technical Specification (TS) 6.8.1 and 
    NUREG-0654. The Petitioner requested that the NRC impose at least three 
    sanctions against his department manager, and impose sanctions against 
    the Petitioner's coworker and maintenance first-line supervisor for 
    engaging in deliberate misconduct in violation of 10 CFR 50.5.
        On February 23, 1995, I informed the Petitioner that the Petition 
    had been referred to me pursuant to 10 CFR 2.206 of the Commission's 
    regulations. I also informed the Petitioner that the NRC would take 
    appropriate action within a reasonable time regarding the specific 
    concerns raised in the Petition. On the basis of a review of the issues 
    raised by the Petitioner as discussed below, I have concluded that no 
    substantial health and safety issues have been raised that would 
    warrant the action requested by the Petitioner.
    
    II. Discussion
    
        In the Petition, the Petitioner raised a concern that on numerous 
    occasions since January 1994, his department manager had instructed the 
    Petitioner's coworkers to shut off or turn down the volume on the site 
    paging and site siren evacuation alarm system in the Millstone Unit 1 
    maintenance shop, and the Petitioner's first-line supervisor and 
    coworker had complied with this request in violation of TS 6.8.1 and 
    NUREG-0654.
        Licensees for nuclear power plants are required to have emergency 
    plans that meet the standards of 10 CFR 50.47(b) and the requirements 
    of 10 CFR Part 50, Appendix E. Under 10 CFR 50.47(b)(8), adequate 
    emergency facilities and equipment to support the emergency response 
    must be provided and maintained. Appendix E of Part 50 establishes 
    minimum requirements for emergency plans for use in attaining an 
    acceptable state of emergency preparedness. Section IV.E.9, in part, 
    requires at least one onsite communications system.
        NUREG-0654, ``Criteria for Preparation and Evaluation of 
    Radiological Emergency Response Plans and Preparedness in Support of 
    Nuclear Power Plants,'' provides guidance for developing radiological 
    emergency plans and improving emergency preparedness. Section II.F.1.e 
    states that each emergency plan shall include provisions for alerting 
    or activating emergency personnel in each response organization. 
    Section II.J.1 states that each licensee shall establish the means and 
    time required to warn or advise onsite individuals and individuals who 
    may be in areas controlled by the licensee. Technical Specification 
    6.8.1, in part, requires that procedures be established, implemented, 
    and maintained covering emergency plan implementation.
        The topic of this Petition was one of the maintenance-related 
    issues the NRC staff raised to Northeast Nuclear Energy Company 
    (NNECO), licensee for Millstone Unit 1, in letters dated December 5 and 
    28, 1994. In those letters, the NRC staff requested NNECO to review the 
    issues and submit a written response. Specifically, the NRC requested 
    NNECO to review the following: (1) That NNECO management had shut off 
    the site paging and site siren evacuation alarm system or directed 
    workers to shut off the system in the Unit 1 maintenance shop during 
    morning meetings, (2) that on several occasions the system was not 
    turned back on for hours, and (3) that the on/off switches for the 
    speakers in question had been installed without a work order.
        The licensee's investigation into this matter, which was described 
    in its January 26, 1995, response to the NRC request, confirmed that 
    the site paging and site siren evacuation alarm system had been 
    routinely turned off at one of the two speakers located in the 
    Millstone Unit 1 maintenance shop area during meetings, and that this 
    practice was not consistent with Emergency Preparedness Department 
    guidance and NUREG-0654.1 However, NNECO management stated that it 
    was confident that personnel could still hear the other speaker. This 
    configuration was also tested during a special test conducted by NNECO. 
    The results of the test verified that one of the two speakers had 
    sufficient capacity to support event notification in the maintenance 
    shop area. Since the single speaker could be heard, personnel in the 
    maintenance area would be alerted if an emergency existed. NNECO's 
    investigation also concluded that the on/off switches were installed 
    without a work order in 1973 consistent with work performance processes 
    at that time.
    
        \1\ NUREG-0654, paragraph J.1, states that each licensee shall 
    establish the means and time required to warn or advise onsite 
    individuals and individuals who may be in areas controlled by the 
    licensee. Emergency Preparedness Department guidance (Emergency Plan 
    Administrative Procedure [EPAP] 1.15), at the time, required that 
    the unit services director monitor and maintain emergency 
    preparedness facilities and equipment. In Attachment 2 of EPAP 1.15, 
    the Unit 1 public announcement speakers and evacuation alarm were 
    included as emergency preparedness equipment.
    ---------------------------------------------------------------------------
    
        NNECO's corrective actions to address this concern included 
    prohibiting the use of any switch that disables any feature of the site 
    paging and site siren evacuation alarm system, removing the two speaker 
    switches, and performing a walkdown of all other system speakers to 
    verify that no other similar switches existed in the system.
        The NRC conducted a special safety inspection from May 15 through 
    June 23, 1995, at the Millstone station. During this inspection, the 
    staff reviewed a number of the concerns, the topic of this Petition 
    being one of them, and issued the findings in Inspection Report (IR) 
    50-245/95-22, 50-336/95-
    
    [[Page 672]]
    22, 50-423/95-22 (95-22), dated July 21, 1995.
        The NRC inspector reviewed the results of the monthly page and 
    siren tests, which were done in accordance with Procedure C-OP-605, and 
    the separate test conducted in the Millstone Unit 1 maintenance shop 
    area. The review of the last two monthly tests showed that the site 
    alarm was audible over ambient noise in all the tested areas. The 
    review of the separate Millstone Unit 1 maintenance shop test showed 
    that either switch, when in the off position, would not disable the 
    system and that with one of the speakers turned off, the other speaker 
    had sufficient capacity to support event notification.
        Emergency Preparedness Department guidance (EPAP 1.15) required 
    that emergency preparedness equipment be maintained. The purpose of the 
    guidance, as it related to the speakers, was to warn or advise onsite 
    individuals. Since the single speaker could still be heard, the 
    Petitioner's department manager stated in a meeting with the NRC 
    inspectors that he believed the Emergency Preparedness Department 
    guidance was still being met. Therefore, the Petitioner has not 
    supported his assertion that the department manager and, indirectly, 
    his first-line supervisor and coworker, deliberately violated Millstone 
    procedures or technical specifications, 10 CFR 50.47(b), or 10 CFR Part 
    50, Appendix E, or failed to meet the guidance in NUREG-0654.
        The inspector reviewed NNECO's corrective actions and confirmed 
    that a work order had been processed to disconnect and remove the 
    cutoff switches and that this work was completed. The inspector 
    reviewed several Millstone site daily news articles (``To the Point'') 
    that reinforced the message of not adjusting speaker volume. The 
    articles clearly stated that management expectations and emergency 
    preparedness guidance were that personnel were not to tamper with 
    emergency preparedness equipment. The inspector also discussed the 
    results of a walkdown of the entire system with a licensee 
    representative. The representative stated that one additional speaker 
    on/off switch had been found in the Unit 3 instrumentation and controls 
    area. This speaker's on/off switch was subsequently removed.
        NNECO's investigation had also concluded that the switches were 
    installed in 1973 without the use of a work order. The work control 
    process has been enhanced significantly at Millstone Unit 1 since 1973. 
    Performing modifications to equipment important to safety, such as the 
    site paging and site alarm siren evacuation system, would now require 
    engineering and operations department review. It would also require 
    consideration of relevant regulatory requirements. During these reviews 
    it would be expected that modifications of this type (i.e., done 
    without such a work order) would be rejected and not implemented. The 
    NRC inspector concluded that NNECO's current work control practices 
    would require an automated work order for this type of modification and 
    that these switches could not have been installed without such a work 
    order under the current work control procedures. Therefore, since a 
    work order for this modification was not required in 1973, no 
    enforcement action is warranted.
        The NRC inspector concluded in the Inspection Report that turning 
    off the site paging and site siren evacuation alarm system speaker was 
    in violation of the licensee's emergency preparedness plan (and thus a 
    violation of TS 6.8.1) and not in conformance with the guidance in 
    NUREG-0654. Therefore, this issue, and three others were collectively 
    cited as a Severity Level IV violation.2 However, the Inspection 
    Report stated that since the operators in the maintenance shop were 
    still able to hear information provided by the other speaker in the 
    maintenance area, this event was of low safety significance and that it 
    appeared NNECO had taken effective corrective action to correct the 
    problem.
    
        \2\  The three other issues involved violations of Millstone 
    Procedure ACP-QA-4.02B, ``Receipt, Control and Identification of QA 
    Material,'' ACP-QA-4.01A, ``System and Component Housekeeping,'' and 
    DC-1, ``Administration of Millstone Procedures and Forms.'' (NRC 
    Inspection Report 50-245/95-22, 50-336/95-22, 50-423/95-22, dated 
    July 21, 1995)
    ---------------------------------------------------------------------------
    
        The NRC staff has concluded that the enforcement action already 
    taken is sufficient in this case and, therefore, no additional 
    enforcement action is warranted. The NRC staff has also concluded that 
    although the Petitioner's department manager turned off or had the 
    Petitioner's coworkers turn off one of the speakers, the Petitioner has 
    not supported his assertion that his department manager and coworkers 
    deliberately violated NRC regulations or the Millstone Unit 1 operating 
    license and, thereby, violated the provisions of 10 CFR 50.5.
    
    III. Conclusion
    
        The institution of proceedings pursuant to 10 CFR 2.206 is 
    appropriate only if substantial health and safety issues have been 
    raised. See Consolidated Edison Co. of New York (Indian Point Units 1, 
    2, and 3) CLI-75-8, 2 NRC 173, 175 (1975) and Washington Public Power 
    Supply System (WPPSS Nuclear Project No. 2), DD-84-7 19 NRC 899, 924 
    (1984). This is the standard that has been applied to the concerns 
    raised by the Petitioner to determine whether the action requested by 
    the Petitioner, or other enforcement action, is warranted.
        On the basis of the above assessment, I have concluded that no 
    substantial health and safety issues have been raised regarding 
    Millstone Nuclear Power Station, Unit 1, that would require initiation 
    of additional enforcement action as requested by the Petitioner.
        The NRC has taken appropriate enforcement action for the events 
    referenced in the Petition. The Petitioner's request for additional 
    action is denied. As provided in 10 CFR 2.206(c), a copy of this 
    Decision will be filed with the Secretary of the Commission for the 
    Commission's review. This Decision will constitute the final action of 
    the Commission 25 days after issuance unless the Commission, on its own 
    motion, institutes review of the Decision in that time.
    
        Dated at Rockville, Maryland, this 19th day of December 1995.
    
        For the Nuclear Regulatory Commission.
    William T. Russell,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 96-286 Filed 1-8-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
01/09/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-286
Pages:
671-672 (2 pages)
Docket Numbers:
Docket No. 50-245
PDF File:
96-286.pdf