02-24863. Integrated System Rates  

  • [Federal Register Volume 67, Number 190 (Tuesday, October 1, 2002)]
    [Notices]
    [Pages 61610-61617]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 02-24863]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Southwestern Power Administration
    
    
    Integrated System Rates
    
    AGENCY: Southwestern Power Administration, DOE.
    
    ACTION: Notice of rate order.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Secretary acting under sections 301(b), 302(a), 402(e), 
    641, 642, 643, and 644, of the Department of Energy Organization Act 
    (Pub. L. 95-91), has approved and placed in effect on an interim basis 
    Rate Order No. SWPA-48 which provides for the following Integrated 
    System Rate Schedules:
    
    Rate Schedule P-02, Wholesale Rates for Hydro Peaking Power
    Rate Schedule NFTS-02, Wholesale Rates for Non-Federal Transmission/
    Interconnection Facilities Service
    Rate Schedule EE-02, Wholesale Rate for Excess Energy
    
        The rate schedules supersede the existing rate schedules shown 
    below:
    
    Rate Schedule P-98D, Wholesale Rates for Hydro Peaking Power--
    (superseded by P-02)
    Rate Schedule NFTS-98D, Wholesale Rates for Non-Federal Transmission/
    Interconnection Facilities Service--(superseded by NFTS-02)
    Rate Schedule EE-98, Wholesale Rate for Excess Energy--(superseded by 
    EE-02)
    
    DATES: The effective period for the rate schedules specified in Rate 
    Order No. SWPA-48 is October 1, 2002, through September 30, 2006.
    
    FOR FURTHER INFORMATION CONTACT: Forrest E. Reeves, Assistant 
    Administrator, Office of Corporate Operations, Southwestern Power 
    Administration, Department of Energy, One West Third Street, Tulsa, 
    Oklahoma 74103, (918) 595-6696, [email protected]
    
    [[Page 61611]]
    
    
    SUPPLEMENTARY INFORMATION: Southwestern Power Administration's 
    (Southwestern) Administrator has determined, based on the Fiscal Year 
    (FY) 2002 Integrated System Current Power Repayment Study, that 
    existing rates will not satisfy cost recovery criteria specified in 
    Department of Energy Order No. RA 6120.2 and Section 5 of the Flood 
    Control Act of 1944. The finalized FY 2002 Integrated System Power 
    Repayment Studies (PRSs), indicate that an increase in annual revenue 
    of $6,138,503, or 5.6 percent, beginning October 1, 2002, will satisfy 
    cost recovery criteria for the Integrated System projects. The proposed 
    Integrated System rate schedules would increase annual revenues from 
    $109,463,500 to $115,006,176, primarily to recover increased 
    expenditures in operations and maintenance (O&M) and investment. In 
    addition, an analysis of the Purchased Power Deferral Account indicates 
    the need for an annual increase of $595,827 to recover the purchased 
    energy costs. This rate proposal also includes a provision to continue 
    the Administrator's Discretionary Purchased Power Adder Adjustment, to 
    adjust the purchased power adder annually, of up to $0.0011 per 
    kilowatthour as necessary, at his/her discretion, under a formula-type 
    rate, with notification to the FERC.
        Following review of Southwestern's proposal within the Department 
    of Energy, I approved, Rate Order No. SWPA-48, on an interim basis 
    through September 30, 2006, or until confirmed and approved on a final 
    basis by the FERC.
    
        Dated: September 18, 2002.
    Spencer Abraham,
    Secretary.
    
    In the Matter of: Southwestern Power Administration Integrated System 
    Rates; Order Confirming, Approving and Placing Increased Power Rate in 
    Effect on an Interim Basis
    
    [Rate Order No. SWPA-48]
    
        Pursuant to sections 302(a) and 301(b) of the Department of Energy 
    Organization Act, Public Law 95-91, the functions of the Secretary of 
    the Interior and the Federal Power Commission under section 5 of the 
    Flood Control Act of 1944, 16 U.S.C. 825s, for the Southwestern Power 
    Administration (Southwestern) were transferred to and vested in the 
    Secretary of Energy. By Delegation Order No. 0204-108, effective 
    December 14, 1983, 48 FR 55664, the Secretary of Energy delegated to 
    the Deputy Secretary of Energy on a non-exclusive basis the authority 
    to confirm, approve and place into effect on an interim basis power and 
    transmission rates, and delegated to the Federal Energy Regulatory 
    Commission (FERC) on an exclusive basis the authority to confirm, 
    approve and place in effect on a final basis, or to disapprove power 
    and transmission rates. Amendment No. 1 to Delegation Order No. 0204-
    108, effective May 30, 1986, 51 FR 19744, revised the delegation of 
    authority to confirm, approve and place into effect on an interim basis 
    power and transmission rates to the Under Secretary of Energy rather 
    than the Deputy Secretary of Energy. This delegation was reassigned to 
    the Deputy Secretary of Energy by Department of Energy (DOE) Notice 
    1110.29, dated October 27, 1988, and clarified by Secretary of Energy 
    Notice SEN-10-89, dated August 3, 1989, and subsequent revisions. By 
    Amendment No. 2 to Delegation Order No. 0204-108, effective August 23, 
    1991, 56 FR 41835, the Secretary of the Department of Energy revised 
    Delegation Order No. 0204-108 to delegate to the Assistant Secretary, 
    Conservation and Renewable Energy, the authority which was previously 
    delegated to the Deputy Secretary in that Delegation Order. By 
    Amendment No. 3 to Delegation Order No. 0204-108, effective November 
    10, 1993, 58 FR 59717, the Secretary of Energy revised the delegation 
    of authority to confirm, approve and place into effect on an interim 
    basis power and transmission rates by delegating that authority to the 
    Deputy Secretary of Energy. By notice, dated April 15, 1999, the 
    Secretary of Energy rescinded the authority of the Deputy Secretary of 
    Energy under Delegation Order No. 0204-108. By Delegation Order No. 
    0204-172, effective November 11, 1999, the Secretary of Energy again 
    provided interim rate approval authority to the Deputy Secretary of 
    Energy. Pursuant to Delegation Order No. 00-037-00, effective December 
    6, 2001, authority is delegated to the Deputy Secretary of Energy for 
    interim rate approval and to the Federal Energy Regulatory Commission 
    for final rate approval. Delegation Order No. 0204-108 is no longer 
    applicable to rates filed by the Power Marketing Administrations. While 
    presently there is no Deputy Secretary; the Secretary of Energy 
    possesses the necessary authority to approve rates.
    
    Background
    
        Federal Energy Regulatory Commission (FERC) confirmation and 
    approval of the following Integrated System (System) rate schedules was 
    provided in FERC Docket No. EF98-4011-000 issued April 29, 1998, for 
    the period January 1, 1998, through September 30, 2001:
    
    Rate Schedule P-98D, Wholesale Rates for Hydro Peaking Power--
    (superseded by P-02)
    Rate Schedule NFTS-98D, Wholesale Rates for Non-Federal Transmission/
    Interconnection Facilities Service--(superseded by NFTS-02)
    Rate Schedule EE-98, Wholesale Rate for Excess Energy--(superseded by 
    EE-02)
    
        On July 26, 2001, these rate schedules were extended on an interim 
    basis by the Deputy Secretary under Rate Order No. 45 for the period 
    October 1, 2001, through September 30, 2002. During the period that 
    current rates have been in effect, Southwestern has modified the 
    Integrated System rate schedules three times for the purpose of 
    clarifying and revising specific provisions that did not impact revenue 
    requirements. Each modification of the rate schedules was approved by 
    FERC on a final basis, the latest being rate schedules, P-98D and NFTS-
    98D, which were approved by FERC on July 31, 2001.
        Southwestern Power Administration's (Southwestern), Current Power 
    Repayment Study (PRS) indicates that the existing rate would not 
    satisfy present financial criteria regarding repayment of investment 
    within a 50-year period due to increasing operation and maintenance 
    expenditures and investment for both the Corps of Engineers (Corps) and 
    Southwestern. The revised PRS indicates that an increase in annual 
    revenues of $6,138,503 was necessary beginning October 1, 2002, to 
    accomplish repayment in the required number of years. Accordingly, 
    Southwestern has prepared proposed rate schedules based on the FY 2002 
    Rate Design Study and the additional revenue requirement.
        Informal meetings were held in April 2002 with customer 
    representatives to review the repayment and rate design processes and 
    present the basis for the 5.6 percent annual revenue increase. In May 
    2002, Southwestern prepared a proposed 2002 PRS for the Integrated 
    System.
        Title 10, part 903, subpart A of the Code of Federal Regulations, 
    ``Procedures for Public Participation in Power and Transmission Rate 
    Adjustment,'' has been followed in connection with the proposed rate 
    adjustments. More specifically, opportunities for public review and 
    comment on proposed System power rates during a 90-day period were 
    announced by notice published in the Federal Register May 21, 2002, (67 
    FR
    
    [[Page 61612]]
    
    35802). A Public Information Forum was held June 6, 2002, in Tulsa, 
    Oklahoma, and a Public Comment Forum was scheduled to be held July 10, 
    2002, also in Tulsa, but was canceled since no one indicated their 
    intent to attend. Written comments were due by August 19, 2002. 
    Southwestern mailed copies of the proposed May 2002 Power Repayment and 
    Rate Design Studies to customers and interested parties that requested 
    the data, for review and comment during the formal period of public 
    participation.
        Following conclusion of the comment period on August 19, 2002, 
    comments presented during the formal public participation process were 
    reviewed. Once all comments were carefully evaluated, the 2002 Power 
    Repayment and Rate Design Studies were completed. No changes were made 
    to the FY 2002 PRS based on comments received. The studies were 
    finalized in August 2002. The Administrator has made the decision to 
    submit the rate proposal for interim approval and implementation. The 
    comments resulting from the public participation process and responses, 
    as developed by Southwestern's staff, are contained in this Rate Order.
    
    Discussion
    
    General
    
        The existing rate schedules developed in the FY 1997 Integrated 
    System Power Repayment Studies were the basis for revenue determination 
    in the August 2002 Integrated System Current Power Repayment Study. The 
    Current Power Repayment Study indicates that existing rates are 
    insufficient to produce the annual revenues necessary to accomplish 
    repayment of the capital investment as required by Section 5 of the 
    Flood Control Act of 1944 and Department of Energy (DOE) Order No. RA 
    6120.2.
        A Revised Power Repayment Study was prepared based on $6,138,503 of 
    additional annual revenue beginning October 1, 2002, to satisfy 
    repayment criteria. This amount is no different than what was proposed 
    in May 2002. No adjustments were made to the May 2002 PRS based on 
    comments received except to finalize the PRS.
        During development of the May rate design study, Southwestern 
    recognized that no costs for Non-Federal, non-firm transmission service 
    were being incurred under the current transmission rate schedule. So, 
    Southwestern redesigned the rate for Non-Federal, non-firm transmission 
    service to be a formula rate rather than a specific dollar rate. 
    Currently, all requests for Non-Federal, non-firm transmission on 
    Southwestern's transmission system must use the Southwest Power Pool 
    regional open access transmission tariff rate. Consequently, 
    Southwestern does not have contractual arrangements for Non-Federal, 
    non-firm transmission service at this time; however, should 
    Southwestern need to provide that service in the future, a rate will be 
    available.
        In Southwestern's 1988, 1990 and 1997 Rate Proposals, two 
    noteworthy issues, which were previously approved by FERC were 
    described in detail. The issues, which still exist today, were (1) the 
    treatment of a portion of the Truman project investment as not 
    currently repayable, and (2) the purchased power adder and 
    discretionary adjustment.
    
    Harry S Truman Project
    
        The Truman issue arose out of the limitations placed on the 
    project's operations by the Corps. The project was designed and 
    constructed to have 160 MW of dependable (marketable) capacity through 
    the use of six reversible pump turbine generating units which could 
    return water to the reservoir following normal generation, to mitigate 
    extreme variations in water available for generation and the lack of 
    storage capacity in the project (only two feet). Pumping ensures 
    project dependable capacity and allows marketing of all six units. A 
    substantial fish kill during testing of the units and considerable 
    opposition to the project's operation, both in the pumping mode and the 
    full six-unit generation mode, led the Corps to significantly restrict 
    the project's operation. In particular, the project's pumps may not be 
    used and only a limited number of units may be utilized simultaneously. 
    Consequently, Southwestern is unable to market full capacity from the 
    project and has declared only two units in commercial operation. 
    Southwestern proposed to the FERC in the 1988 rate filing that, since 
    the entire project was neither revenue-producing, declared in 
    commercial operation, nor expected to be in service within the then-
    existing cost evaluation period, the total investment allocated to 
    power was not repayable under DOE or FERC regulations. Southwestern 
    further proposed an adjustment to Truman's allocated costs and reduced 
    the repayable investment to an amount equal to approximately 44 percent 
    of then-allocated costs, with the remaining amount to be deferred until 
    the project can be operated as it was designed. The FERC approved this 
    proposal as an acceptable interim measure while the Corps develops a 
    cost allocation for Truman based on actual operating conditions. 
    Southwestern also proposed this concept to the Corps, and the Corps 
    agreed to consider it as an option in developing the cost allocation 
    for the project. Subsequently, the Corps has completed a major revision 
    to the Truman project cost allocation and has utilized Southwestern's 
    proposed concept for determining repayable investment at the project 
    during the interim period until the project becomes fully operational. 
    Although not yet approved on a final basis, the Interim Cost Allocation 
    proposed by the Corps for the Truman project has been utilized in the 
    development of the 1990, 1997 and 2002 PRSs in support of the revenue 
    requirements of Southwestern's Integrated System and the rate proposal, 
    as the most recent cost allocation available which reasonably reflects 
    the level of costs expected to be payable at the Truman project during 
    the cost evaluation period.
        During February 1997, the Interagency Committee on Cost Allocations 
    (ICCA) met to review and potentially approve the Truman, Stockton, and 
    Clarence Cannon project cost allocations. The Stockton cost allocation 
    was subsequently approved on a final basis on May 8, 1997. The Clarence 
    Cannon was approved on August 25, 1998. The Truman cost allocation was 
    to be sent back to the Corps' Kansas City District office to make 
    changes in the allocation's assumptions and then be prepared for 
    finalization. However, in June 1997, a meeting of the Southwestern, the 
    Corps and several customer representatives was held to discuss the 
    Truman cost allocation. The customers expressed their concern about the 
    significant level of costs being proposed while the project continued 
    to be limited in its ability to produce hydropower. At this meeting, 
    the Corps agreed to review the issue of assigning hydro-related costs 
    to another project purpose that had contributed to limiting the hydro 
    operation of the project. The allocation of those costs to another 
    purpose would be potentially considered temporary and the costs would 
    be reallocated back to the hydropower purpose in an amount relational 
    to the part of the hydropower purpose functioning as originally 
    designed. Southwestern is continuing to pursue finalization of this 
    cost allocation with the Corps. However, it is not anticipated that the 
    Truman cost allocation will be finalized in the near future; therefore, 
    Southwestern has continued to use the Interim Cost Allocation for the 
    Truman project in development of the 2002 PRS.
    
    [[Page 61613]]
    
    Purchased Power Deferral Account (Discretionary Adjustment and Adder)
    
        During the time the purchased power adder and the deferral 
    accounting mechanism have been in place, they have proven to be 
    effective in assuring that purchased power revenues equal purchased 
    power costs over time. The financial interests of the Government have 
    been protected in this endeavor, and the rate component has been 
    adjusted as necessary. In the 1997 Rate Proposal, Southwestern 
    requested approval for the Administrator to have authority to adjust 
    the purchased power rate component up to once annually, based on a 
    formula-type rate included in the rate schedules, by up to $0.0011 per 
    kWh at his or her discretion. The flexibility derived from this 
    authority enables Southwestern to react more quickly to significant 
    changes in water conditions which may have occurred during the 
    preceding year or simply to exercise better control on the amount of 
    revenue in the Account and to better limit the over or under recoveries 
    of revenue. The Administrator utilized this authority in implement 
    adjustments of up to $0.0011 per kWh to help increase revenues 
    collected in the Account during the previous years of less than average 
    water conditions and the corresponding increase in the costs for 
    purchased power. This authority seems to remain appropriate, 
    particularly in light of the fact that the Account has no direct effect 
    on Integrated System repayment requirements and the separate rate 
    component serves to provide revenues to meet expected costs which, if 
    they do not come to pass, are either held to meet future costs or 
    result in a lower purchased power rate for customers. Therefore, 
    Southwestern's Administrator requests continuing authority to adjust 
    the purchased power rate component annually based on a formula-type 
    rate included in the rate schedules.
        An element directly related to the Account and accrual of interest 
    thereto is the determination of the purchased power adder itself. 
    Southwestern is proposing, as in all previous proposals beginning with 
    the 1983 implementation of the purchased power rate component, that the 
    adder be set equal to the current average long-term purchased power 
    rate requirement. As shown in the Rate Design Study, the amount is 
    determined by dividing the estimated total average direct purchased 
    power costs by Southwestern's total annual contractual 1200-hour 
    peaking energy commitments to the customers (exclusive of contract 
    support arrangements). In this rate proposal, the resulting Purchased 
    Power Adder (Adder) is $0.0025 per kWh of peaking energy. The total 
    revenue created through application of this Adder would enable 
    Southwestern to cover its average annual purchased power costs.
        Rate schedules were designed to recover the additional revenue 
    requirements. The basic monthly demand charge for the sale of Federal 
    hydroelectric power and the base energy charge have increased. The 
    transformation charge, though paid by a few customers having 69 kV and 
    below deliveries, has increased and affects revenues as well. In 
    addition, transmission charges for non-Federal, firm service have 
    increased. The increases to both transformation and transmission 
    charges are due to additions and replacements that have been made to 
    Southwestern's aging transmission facilities since the last rate 
    change.
        In accordance with FERC's Order No. 888, Southwestern will continue 
    charging separately for five ancillary services and offering network 
    transmission service. Southwestern's rate design has separated the five 
    ancillary services for all transmission service. Two ancillary 
    services, Scheduling, System Control and Dispatch Service and Reactive 
    and Voltage Support Service, are required for every transmission 
    transaction. These charges are also a part of the capacity rate for 
    Federal power. This is consistent with Southwestern's long-standing 
    practice of charging for the sale and delivery of Federal power in its 
    Federal demand charge. The three remaining ancillary services will be 
    made available to any transmission user within Southwestern's control 
    area, including Federal power customers. The Rate Schedules for Peaking 
    Power and Non-Federal Transmission Service reflect these charges. 
    Network transmission service will be provided to those, also within 
    Southwestern's control area, who request the service, but for non-
    Federal deliveries only. The rate and application of this service are 
    identified in the Non-Federal Transmission/Interconnection Facilities 
    Service Rate Schedule, NFTS-02.
    
    Comments and Responses
    
        The Southwestern Power Administration (Southwestern) received 
    numerous questions to which responses were provided during the public 
    participation period and which are included in the background 
    information. In addition, Southwestern received comments from five 
    entities during the public participation process. Those comments are 
    summarized into six general areas of concern, and Southwestern's 
    responses to the concerns raised are as follows:
    
    Corps O&M Expenses
    
    Comments
    
        Southwestern should revisit its projections of the Corps of 
    Engineers Operation and Maintenance (O&M) costs with particular 
    attention to projected personnel costs to assure projections are 
    conservative and that all efficiencies consistent with sound business 
    principles have been incorporated into these areas. With respect to 
    personnel costs, commentors take issue with inclusion of expenses for 
    trainees to replace retiring personnel. Commentors state that this 
    reflects poor planning on the part of the Corps and should not be 
    reflected as a part of the ongoing future base costs because such an 
    assumption inflates long term future cost estimates and rates.
    
    Response
    
        Projections for Corps of Engineers (Corps) O&M are developed by the 
    Corps and provided to Southwestern annually. The Corps makes 
    projections of their base O&M costs using historical information and 
    planning documents, and also includes projections for large maintenance 
    items for each of the projects that have been included in their outyear 
    budget estimates. These projections are made in current year dollars 
    and do not include inflation. Southwestern reviews this information, 
    questioning the Corps where inconsistencies seem to occur, clarifying 
    its understanding of the cost estimates, and adjusting the estimates to 
    future year dollars based on the Gross Domestic Product Index to 
    incorporate inflationary expectations. The Corps has advised 
    Southwestern that, among other costs, the addition of trainees and 
    increased project maintenance are two elements in base costs. The Corps 
    informed Southwestern that trainee costs are limited to projects where 
    retirements are imminent but project maintenance will continue to 
    increase until such time as the projects identified for rehabilitation 
    can be completed. Southwestern inquired further and was advised that 
    the Corps is confident that their O&M estimates fairly represent the 
    minimum expenditure level expected for the projects' O&M and that this 
    level of expenditure is expected to continue into the future.
        Southwestern does not receive the detail of personnel costs 
    included in the Corps' O&M estimates, nor is it necessary for 
    Southwestern to have this information since the Corps provides
    
    [[Page 61614]]
    
    total forecasted O&M expenditures by project. Although Southwestern can 
    provide suggestions, proposing changes to the management of the Corps' 
    resources, particularly their personnel processes, is beyond the scope 
    of Southwestern's authorities. Southwestern is tasked with recovering 
    the power costs at Corps of Engineers dams; the Corps is responsible 
    for managing their organization. The Corps believes that its internal 
    controls, accounting system reviews and funding procedures effectively 
    provide the needed level of justification, consistency and control of 
    its O&M expenditures. Southwestern has no oversight authority with 
    regard to Corps expenditures for O&M activities. Southwestern agrees 
    that such costs should be prudently and timely incurred at reasonable 
    levels consistent with sound business principles. The estimates 
    historically provided by the Corps have been reasonably accurate in 
    total, although they fluctuate somewhat from actual expenditures by 
    individual project.
        The primary cause for the increase in Corps O&M between the FY 1997 
    PRS (on which current rates are based) and the FY 2002 PRS is the 
    inclusion, beginning with the FY 1998 PRS, of an estimate for the 
    Unfunded Civil Service Retirement System (CSRS) and Health/Life 
    Insurance Benefits. Without the inclusion of this increased cost 
    element in the FY 2002 PRS (which were not part of the forecast in the 
    FY 1997 filing), the Corps' O&M estimate, including the average year 
    large maintenance items, has increased less than 2% in total over the 
    last five years. Although the Corps has historically been fairly 
    accurate, their projections for O&M costs for the past two years have 
    been less than what was recorded on their financial statements. The 
    Corps has confirmed that the past few years' projections were based on 
    anticipated reductions in funding, but have realized they were 
    underestimating and in the FY 2002 projections have increased their 
    estimates to better reflect their expected expenditures.
        The Corps' estimates of O&M are based on what they believe will be 
    their actual expenditures on their financial statements. This process 
    is consistent with the requirements of RA 6120.2. The procedure for the 
    Corps to provide O&M estimates is based on a Memorandum of Agreement 
    with the Corps of Engineers in November 1989, and has been fairly 
    accurate. The projection of Corps O&M in the FY 2002 PRS for the final 
    year of the cost evaluation period (FY 2006) is 3.8 percent higher than 
    the Corps' actual O&M expenditures for historical year FY 2001, 
    primarily reflecting an expected period of relatively stable funding.
        Southwestern believes that the estimates provided by the Corps for 
    their O&M are reasonable based on their historical accuracy and 
    accurately reflect what the Corps will ultimately book as actual 
    expenditures on their financial statements.
    
    Corps of Engineers--Estimates for Large Maintenance Items
    
    Comments
    
        Southwestern should revisit its process for determining estimates 
    of future Large Maintenance Items (LMI) for purposes of the PRS. It 
    would appear that the process Southwestern is using is not in 
    compliance with RA 6120.2. Southwestern should modify the process to 
    include a comparison of actual LMI costs in previous years with the 
    forecasted LMI for those years contained in previous PRSs. In addition, 
    Southwestern should closely examine the proposed 5.25 percent one-year 
    LMI factor proposed by the East Texas Cooperatives, a figure premised 
    on a more accurate methodology than used by Southwestern.
    
    Response
    
        Southwestern has reviewed its methodology for mitigating the impact 
    of Large Maintenance Items which are estimated to occur in the final 
    year of the cost evaluation period and has determined that the 
    methodology is sound, produces reasonable estimates and has been 
    reasonably accurate historically when combined as a part of overall 
    total estimates of Corps O&M costs.
        The estimates of large maintenance items are provided by the Corps, 
    in detail by project, by year. In an effort to minimize wide swings in 
    the effect of large maintenance items (specifically in the last year) 
    and to add stability to rates, Southwestern developed a procedure over 
    fifteen years ago that removes the large maintenance estimates in the 
    fifth year of the cost evaluation period and replaces that estimate 
    with a ten-year average of large maintenance item estimates. In order 
    to alleviate the impact that one or two years of increased large 
    maintenance items had on the rates, Southwestern has used an average 
    over a ten-year period. This has ``leveled out'' the LMI estimates and 
    has, when added to the routine O&M, reflected a more accurate estimate 
    of what the Corps' expenditures have been in the fifth year. This 
    method of forecasting appears to be very efficient since in comparing 
    the historical fifth year estimate with its corresponding actual 
    expenditure, the Corps' O&M estimates appear to be quite reasonable. In 
    fact, during the past few years, the estimate of total Corps O&M 
    expenditures for the fifth year, which include Southwestern's 
    methodology for estimating the large maintenance item component, has 
    been within three percent of the actual for that year, with the most 
    recent estimate being within 0.1 percent of the actual.
        Southwestern has also evaluated the use of an average of the most 
    recent forecasts as suggested by one entity commenting, but found that 
    in years when forecasts for that one year were significantly higher, 
    there was a substantial impact on the rate Southwestern would charge. 
    By using the suggested methodology in the commentor's suggestion, the 
    one-year average factor for eight of the past ten years would have 
    resulted in a factor significantly greater than the recommended 5.25 
    percent. While the proposal to use one year's average would reflect a 
    decrease in this PRS, use of the recommended methodology in eight of 
    the past ten years would have resulted in an increase in revenue 
    requirements for those years and possible rate increases. Consequently, 
    Southwestern believes the proposed method is less accurate than the 
    existing method and reintroduces yearly variations which are mitigated 
    under the existing method in response to customer concerns expressed 
    some years ago.
        The use of actual historical data on large maintenance items and 
    base expenses may be preferable, but with the lack of detailed data 
    available from the Corps and with power being only one of the purposes 
    for which the Corps captures financial data, we believe it is not a 
    practical approach. In addition, it would add very little, if anything, 
    to the accuracy of the Corps' O&M estimates which in total have been 
    very good.
        Southwestern has confirmed that the Corps' O&M estimates are based 
    on historical costs and actual project costs in accordance with RA 
    6120.2. Southwestern reviews the estimates to compare with actuals. 
    However, the Corps also considers in its estimates the RA 6120.2 
    requirement that, ``forecast shall take into account known factors 
    which are expected to affect the future level of such costs during the 
    cost evaluation period.'' The PRS reflects actual LMI in the Corps' 
    total historical O&M expenses for each year since it is part of the 
    total O&M number. The Corps provides actual O&M expenses based on 
    joint-use and specific-use cost
    
    [[Page 61615]]
    
    pursuant to their regulations for their financial statement reporting.
        As has been noted, Southwestern believes that the estimate in the 
    fifth year of average LMI expenses for Corps O&M expenses is reasonably 
    accurate. Southwestern prepares PRSs each year and will continue to 
    monitor its processes to assure estimates are reasonable and that all 
    efficiencies consistent with sound business principles have been 
    incorporated.
    
    Southwestern's O&M Expenses
    
        Southwestern's O&M expenses have increased by approximately $13 
    million over the FY 1997 Power Repayment Study. Included in 
    Southwestern's O&M expenses are salaries and wages, maintenance costs 
    on aging transmission facilities, transmission-related services and 
    purchased power costs. The commentors state that Southwestern should 
    reduce its forecasted O&M expenses to reflect more reasonable 
    estimates.
    
    Response
    
        Southwestern's O&M expense estimates increased significantly 
    between the FY 1997 Power Repayment Study (PRS) and the current PRS for 
    a number of reasons. Purchased Power costs increased by approximately 
    $3 million due to greater than expected unit cost increases and 
    reductions in the availability of banking energy arrangements. In 
    addition, costs increased by $4.4 million due to requirements beginning 
    January 1, 1998, for transmission losses to be replaced through 
    purchased energy rather than reduced in kind as done previously. This 
    cost is totally offset by a corresponding increase in revenues 
    collected from transmission customers, but nonetheless appears as a 
    significant cost increase. The rate for Federal power and energy, 
    including the Purchased Power Adder are not affected by this cost.
        Southwestern has experienced increased costs for transmission 
    service charges since FY 1997. Due to implementation of a new contract, 
    Southwestern now pays an additional $1.0 million for transmission 
    service. However, the impact of this increase in Southwestern's 
    transmission service costs has been minimized by an increase in 
    transmission revenues.
        Southwestern's Transmission and Marketing expense have increased by 
    $4.6 million over the FY 1997 PRS estimates. A significant portion of 
    this increase is related to Southwestern's employee salaries, even 
    though Southwestern has reduced Full-Time Equivalents by approximately 
    8 percent. This increase in employee salaries and wages is due to cost 
    of living adjustments and other payroll requirements set by the U.S. 
    Congress and regulated wage surveys affecting craft personnel and 
    dispatchers. The remaining portion of Transmission and Marketing costs 
    have increased proportionately to historical trends and are within the 
    rate of inflation for the period.
        Southwestern has based its O&M expense estimates in the FY 2002 PRS 
    on historical trends and future budget projections. As evidenced by the 
    increase in historical costs, many of which are outside Southwestern's 
    control, Southwestern believes its estimates are reasonable and will 
    represent what is anticipated to be recorded on Southwestern's 
    financial statements.
    
    Corps and Southwestern's Investment Estimates
    
    Comments
    
        Some commentors have expressed concern regarding the level of added 
    investment during the initial 5-year cost evaluation period (CEP) and 
    that past history shows an over-forecasting of actual plant in service 
    to estimates. Some commentors recommended that Southwestern reduce its 
    forecast for added investment while others expressed a desire for the 
    appropriate level to be achieved to assure rehabilitation of the Corps' 
    aging plants. Also noted in the comments was a lack of decreased O&M 
    expense related to replacing older, typically maintenance-intensive 
    plant.
    
    Response
    
        The estimates in the PRS for future investment (over the 5-year 
    CEP) is an average of $9 million per year for replacements, $18 million 
    in construction work in progress (projects that have been started but 
    not yet complete and on the ``books''), and a conservative estimate of 
    $35.7 million for single unit rehabilitations at four of the Corps' 22 
    projects. These projections are for only an incremental portion of the 
    total rehabilitation and represents what is expected to take place 
    within the 5-year CEP and has been committed to funding by the Corps. 
    It is anticipated that the remaining costs that fall outside the 5-year 
    CEP in the FY 2002 PRS will be included in future PRSs.
        Projections for the Corps Investment (replacements) are developed 
    based on data provided by the Corps to Southwestern every five years 
    and reviewed annually by the Corps. The Corps makes projections of 
    their investments based on planning documents. The Corps determines 
    what projects are in need of repair and makes a request for budget 
    appropriations to fund that replacement. The Corps has based their 
    estimates of future investments for the PRS on anticipated project 
    funding to perform the needed work. The funding has not always 
    materialized during the budgeting process. This has contributed to some 
    historical estimates being higher than actual expenditures.
        We believe the FY 2002 PRS estimates are more accurate than 
    previous estimates due to a new customer funding source whereby the 
    Corps has access to a consistent funding level in addition to the 
    appropriation process. The alternative customer funding process will 
    relieve some pressure due to reduced appropriations and allow for 
    projects to be started and completed in a timely manner. Southwestern 
    believes that with the alternative customer funding method in place, 
    more of the projected replacements and maintenance will be accomplished 
    by the Corps, and will result in more closely matching PRS estimates in 
    the future.
        In addition, the O&M costs for which the Corps provides 
    Southwestern estimates (as discussed in an earlier comment) are 
    anticipated to remain higher during the 5-year CEP, until such time as 
    all phases of the rehabilitations have been completed, due to having to 
    maintain and upgrade the rest of the aging facilities. Having discussed 
    these issues with Corps representatives, Southwestern believes that the 
    estimates provided by the Corps for O&M are based on their best 
    judgment as to what will be their actual expenditures. Southwestern 
    also believes that their O&M estimates, compared with actuals, are 
    fairly accurate and representative of what will be entered on their 
    financial statements. Southwestern shares the customers' belief that in 
    the future these O&M estimates may well, in fact, be reduced. But with 
    the appropriation reductions and other funding issues that the Corps 
    has encountered in the past, there remains a massive backlog of 
    projects that need to be completed as funding becomes available, which 
    means that it will be many years before a reduction in O&M is 
    recognized by the Corps. Contrary to one commentor's assertion, Corps 
    estimates do not continue to increase throughout the 50 year period. 
    Corps O&M estimates beyond the 5-year CEP are held constant from the 
    5th year through the 50th year yielding no additional expenses.
        As stated in RA6120.2 (paragraph 10), replacements of investment 
    will be
    
    [[Page 61616]]
    
    ``included in repayment studies by adding the estimated capital cost of 
    (the) replacement to the unpaid Federal investment in the year each 
    replacement is estimated to go into service.'' Southwestern is required 
    to forecast for replacements. Southwestern must forecast replacements 
    for the entire period of the PRS. The Corps provides the best data they 
    have available, together with the service lives of the equipment. 
    Southwestern and the Corps review these estimates annually and update 
    the replacement data with the goal to reflect what will occur on the 
    annual financial statements.
    
    Unfunded Civil Service Retirement System Benefits
    
    Comment
    
        Revenues collected by Southwestern for ``Unfunded'' Civil Service 
    Retirement System (CSRS) and Health and Life Insurance Benefits should 
    be (1) removed from Southwestern's rates because Southwestern has no 
    authority to collect them, (2) properly account for the additional 
    interest effects of the revenues collected, or (3) apply the revenues 
    collected to Southwestern's debt rather than to the CSRS expenses.
    
    Response
    
        Statement of Federal Financial Accounting Standards (SFFAS) No. 5, 
    requires all federal agencies, including Power Marketing 
    Administrations (PMAs), to record the full cost of pension and 
    postretirement benefits in financial statements beginning in fiscal 
    year 1997. SFFAS No. 5 prescribes that the aggregate entry age normal 
    (AEAN) actuarial cost method be used to calculate pension expenses and 
    accrued actuarial liabilities for pension benefits. Under the AEAN 
    method, which is based on dynamic economic assumptions, including 
    future salary increases, the actuarial present value of projected 
    benefits is allocated on a level basis over the earnings or the service 
    of the group between entry age and assumed exit ages and is applied to 
    pensions on the basis of a level percentage of earnings. The portion of 
    this actuarial present value allocated to a valuation year is called 
    the ``normal cost''. The Office of Personnel Management (OPM) applies 
    the AEAN method to estimate the amount by which employer and employee 
    contributions toward future CSRS pension benefits fall short of the 
    normal cost of those benefits.
        For CSRS employees, OPM reported that, in 1995, 25.14 percent of 
    gross salaries was the full (normal) cost to the federal government of 
    benefits earned that year by employees and that federal agencies 
    contributed 7 percent and employees contributed 7 percent to OPM for 
    CSRS, leaving a funding deficiency of 11.14 percent of each CSRS 
    employee's annual salary. Such deficiencies are made up by Treasury's 
    funding of OPM retirement costs. Southwestern has included an estimate 
    of the unfunded portion of the CSRS costs in its Power Repayment 
    Studies every year since 1998. Revenues have been returned to the 
    Treasury by Southwestern each year since 1998 to be used by Treasury to 
    fund OPM retirement benefits and health insurance costs.
        Even though this is the first Integrated System rate filing that 
    has included unfunded CSRS costs, it is not the first rate filing 
    Southwestern has submitted that includes unfunded CSRS costs. 
    Southwestern has had three previous rate filings since 1998 for two 
    other rate systems that have been submitted through the DOE and 
    ultimately approved by FERC. Southwestern did not receive any comments 
    related to the CSRS issue in any of the public comment periods of those 
    three rate filings. Furthermore, the Southeastern Power Administration 
    (SEPA) included CSRS cost estimates in a rate filing in 1998. The 
    comments on that rate filing included opposition to the inclusion of 
    the CSRS estimates. The FERC confirmed the SEPA filing on a final basis 
    and did not accept the arguments to exclude the CSRS costs. A request 
    for rehearing related to the filing was also denied.
        Authority to collect revenues for the unfunded CSRS costs comes 
    primarily from Section 5 of the Flood Control Act of 1944 which, in 
    part, states ``* * *Rate schedules shall be drawn having regard to the 
    recovery''* * * ``of the cost of producing and transmitting such 
    electric energy,* * *'' Unfunded CSRS has been determined to be a cost 
    of ``producing and transmitting electricity.'' Upon disbursement, the 
    Federal government funds the unfunded portion of the CSRS program just 
    as it funds the funded portion of the CSRS program. The difference is 
    that, when retirement payments are issued, OPM and not Southwestern is 
    the agency that the funding of the unfunded portion of CSRS costs is 
    directed to. The authority to collect revenues to repay the CSRS 
    program costs is no different than the authority to collect the funded 
    portion.
        Southwestern agrees with the comment that it should properly 
    account for the additional interest effects of the revenues collected 
    and is currently doing so. Southwestern's existing procedure imputes an 
    interest credit at current year interest rates on all revenues 
    received--which would include revenues received to repay CSRS costs. 
    The effect of the interest credit carries throughout the entire 
    repayment period.
        Regarding the issue of applying revenues received for CSRS expenses 
    to Southwestern's debt, the application of revenues is guided by DOE 
    Order 6120.2 (paragraph 8c.(3)) which states ``Annual revenues will be 
    first applied to the following recovery of costs during the year in 
    which they occurred: operation and maintenance (O&M), purchased and 
    exchanged power, transmission service and other, and interest expense 
    and any appropriation amortization of revenue bonds. Remaining revenues 
    are available for amortization* * *''. Therefore, Southwestern applies 
    its revenues received to the CSRS expenses before it applies any 
    revenue toward the amortization of the Federal investment.
    
    Isolated Projects and Bundled Rates
    
    Comments
    
        Southwestern should not be charging a pancaked rate for the sale 
    and delivery of Federal power. Those customers that receive Federal 
    power from isolated Corps projects should not be required to pay for 
    transmission and ancillary services that they do not use. In addition, 
    those customers should receive credit for incurring costs that the 
    typical Southwestern customer does not. Even though this issue was 
    raised in Southwestern's 1997 rate proceedings and was rejected by 
    Southwestern, the Secretary of Energy and the FERC, this issue should 
    be reconsidered and not viewed as a binding precedent because the 
    regulatory and market environment has changed considerably.
    
    Response
    
        Southwestern's sales of Federal power and energy are based on a 
    ``postage-stamp'' type rate, which is based on the financial 
    integration of all the projects marketed under the Integrated System, 
    as well as various components of Southwestern's transmission system. 
    The capacity rate for all Federal power customers includes a 
    transmission component and the two required ancillary services. This 
    rate has been set to assure that Southwestern charges itself the same 
    rates it charges for the use of the transmission system for wheeling 
    non-Federal power. The customers which receive the output of Corps of 
    Engineers projects that are presently electrically isolated from 
    Southwestern's primary interconnected system requested integration of 
    such projects into the Integrated System to
    
    [[Page 61617]]
    
    receive that system's benefits, including lower costs. In addition, 
    such customers receive a number of benefits from their project sales 
    which other Federal customers do not, such as overload capacity, 
    condensing, greater scheduling flexibility, and an exclusion from 
    paying the Purchased Power Adder. Such projects also include components 
    of Southwestern's transmission system and switchyard facilities used to 
    deliver power and energy from the dams. Revenues from all sales within 
    the Integrated System are applied toward repayment of all Federal 
    investment for all projects, regardless of their electrical integration 
    status.
        Southwestern is not required by FERC Order No. 888 or Order No. 
    2000 to offer unbundled services to its customers. Section 5 of the 
    Flood Control Act of 1944 sets forth the statutory requirements for the 
    sale and delivery of Federal power and energy. Furthermore, based on 
    DOE policy, ``each of the PMAs that own transmission facilities will 
    publish generally applicable open access wholesale transmission tariffs 
    and will take service itself under such tariffs. The tariffs will 
    include rates, terms, and conditions, and will offer transmission 
    services, including ancillary services, to all entities eligible to 
    seek a transmission order under section 211 of the Federal Power Act * 
    * *'' Southwestern has complied with this policy in separating its non-
    Federal transmission service and to provide for ancillary services.
        Even though Southwestern agrees that the electric industry has 
    changed considerably since 1997, the conditions and points raised 
    related to this issue are the same as were espoused in 1997. Upon 
    review, there does not appear to be any overriding factor that compels 
    Southwestern to change its previous determination that those customers 
    do benefit from the treatment of the transmission system and related 
    facilities and the power rate charged to the customers reflects such 
    benefits. The parties expressing these concerns voluntarily and 
    knowingly entered into long-term contractual arrangements to receive 
    the benefits of these projects at integrated system rates. We find it 
    disingenuous to now seek through the rate development process to 
    overturn what was done for their benefit through mutually agreeable bi-
    lateral contracts.
    
    Operational Efficiencies
    
    Comments
    
        Southwestern management should commit to incorporate any 
    operational efficiencies that would reduce the magnitude of the rate 
    increase. Such efficiencies should be fully discussed as part of the 
    Power Repayment Study. Overstatement of revenue requirements can tempt 
    management to operate less efficiently than might otherwise have been 
    possible.
    
    Response
    
        Southwestern agrees that it should incorporate all efficiencies 
    available into its day-to-day operations to accomplish the requirements 
    of Section 5 of the Flood Control Act of 1944 for Southwestern to 
    maintain ``the lowest possible rates to consumers consistent with sound 
    business principles.'' Southwestern's Power Repayment Studies are 
    developed annually to recover its costs to help accomplish that 
    requirement and not to specifically identify efficiencies that have 
    been instituted by the agency throughout the year. Southwestern 
    continually strives to incorporate efficiencies in its operational 
    activities. One example of such efficiencies can be illustrated by the 
    number of full-time employees (FTE) employed by Southwestern. Even with 
    the same number of customers and a significantly changing industry, the 
    FTE for 1997 was 193 while the FTE in 2001 was 178. Another example of 
    Southwestern's attention to efficient operation may be reflected in the 
    rates themselves. The average rates charged by Southwestern for energy 
    or transmission are the lowest in the region and will continue to be so 
    even if this proposed rate increase is implemented. Furthermore, most 
    of the increase in this proposed rate increase comes from costs outside 
    of Southwestern's direct control. Those costs include Corps of 
    Engineers costs, salary increases determined by Congress and charges 
    for unfunded civil service retirement system costs.
        Unlike many other utilities, Southwestern's management has no 
    incentive to raise rates to allow them to operate less efficiently. 
    Revenues received from sales of power and other services are deposited 
    directly into the U.S. Treasury and are credited toward the repayment 
    of the hydropower system costs. There are no additional revenues for 
    Southwestern's management to use from higher rates because operating 
    costs are obtained through a separate Congressional appropriation 
    process which is not directly related to higher or lower rates.
    
    Other Issues
    
        Other issues are discussed in the Administrator's Record of 
    Decision.
    
    Availability of Information
    
        Information regarding this rate proposal including studies, 
    comments and other supporting material, is available for public review 
    and comment in the offices of Southwestern Power Administration, One 
    West Third Street, Tulsa, OK 74101.
    
    Administrator's Certification
    
        The August 2002 Revised Power Repayment Study indicates that the 
    increased power rates will repay all costs of the Integrated System 
    including amortization of the power investment consistent with the 
    provisions of Department of Energy Order No. RA 6120.2. In accordance 
    with Delegation Order No. 00-037.00, December 6, 2001, and Section 5 of 
    the Flood Control Act of 1944, the Administrator has determined that 
    the proposed System rates are consistent with applicable law and the 
    lowest possible rates consistent with sound business principles.
    
    Environment
    
        The environmental impact of the proposed System rates was evaluated 
    in consideration of DOE's guidelines for implementing the procedural 
    provisions of the National Environmental Policy Act and was determined 
    to fall within the class of actions that are categorically excluded 
    from the requirements of preparing either an Environmental Impact 
    Statement or an Environmental Assessment.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me the Secretary of Energy, I hereby confirm, approve and place in 
    effect on an interim basis, effective October 1, 2002, the following 
    Southwestern System Rate Schedules which shall remain in effect on an 
    interim basis through September 30, 2006, or until the FERC confirms 
    and approves the rates on a final basis.
    
        Dated: September 18, 2002.
    Spencer Abraham,
    Secretary.
    [FR Doc. 02-24863 Filed 9-30-02; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Effective Date:
10/1/2002
Published:
10/01/2002
Department:
Southwestern Power Administration
Entry Type:
Notice
Action:
Notice of rate order.
Document Number:
02-24863
Dates:
The effective period for the rate schedules specified in Rate Order No. SWPA-48 is October 1, 2002, through September 30, 2006.
Pages:
61610-61617 (8 pages)
PDF File:
02-24863.pdf