[Federal Register Volume 59, Number 196 (Wednesday, October 12, 1994)]
[Unknown Section]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-25133]
[[Page Unknown]]
[Federal Register: October 12, 1994]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP94-817-000]
Natural Gas Pipeline Company of America; Notice of Application
October 5, 1994.
Take notice that on September 29, 1994, Natural Gas Pipeline
Company of America (Natural), 701 East 22nd Street, Lombard, Illinois,
60148, filed in Docket No. CP94-817-000 an application pursuant to
Section 7(c) of the Natural Gas Act, requesting authorization to
construct and operate 2.86 miles of 36 inch loop line in Effingham
County, Illinois, to accommodate an additional 32 Mmcf per day of gas
from Natural's Loudon Storage Field to the Chicago market area, all as
more fully set forth in the application on file with the Commission and
open to public inspection.
Natural states that this proposal will result in the No. 3 line of
Natural's Gulf Coast Mainline extending from the immediate outlet of
Natural's Loudon Storage Field northward toward the Chicago market
area. It is further stated that this additional loop will benefit
Natural's system by improving the utilization of the existing
certificated peak daily deliverability at Loudon.
It is estimated that the facilities for this project will cost
approximately $2.83 million, which Natural proposes to finance with
funds on hand.
Any person desiring to be heard or to make any protest with
reference to said application should on or before October 26, 1994,
file with the Federal Energy Regulatory Commission, Washington, D.C.
20426, a motion to intervene or a protest in accordance with the
requirements of the Commission's Rules of Practice and Procedure (18
CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act
(18 CFR 157.10). All protests filed with the Commission will be
considered by it in determining the appropriate action to be taken but
will not serve to make the protestants parties to the proceeding. Any
person wishing to become a party to a proceeding or to participate as a
party in any hearing therein must file a motion to intervene in
accordance with the Commission's Rules.
Take further notice that, pursuant to the authority contained in
and subject to jurisdiction conferred upon the Federal Energy
Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and
the Commission's Rules of Practice and procedure, a hearing will be
held without further notice before the Commission or its designee on
this application if no motion to intervene is filed within the time
required herein, if the Commission on its own review of the matter
finds that a grant of the certificate is required by the public
convenience and necessity. If a motion for leave to intervene is timely
filed, or if the Commission on its own motion believes that a formal
hearing is required, further notice of such hearing will be duly given.
Under the procedure herein provided for, unless otherwise advised,
it will be unnecessary for Natural to appear or be represented at the
hearing.
Lois D. Cashell,
Secretary.
[FR Doc. 94-25133 Filed 10-11-94; 8:45 am]
BILLING CODE 6717-01-M