94-25303. Duke Power Company; Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing  

  • [Federal Register Volume 59, Number 197 (Thursday, October 13, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-25303]
    
    
    [[Page Unknown]]
    
    [Federal Register: October 13, 1994]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket Nos. 50-369 and 50-370]
    
     
    
    Duke Power Company; Consideration of Issuance of Amendment to 
    Facility Operating License, Proposed No Significant Hazards 
    Consideration Determination, and Opportunity for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License Nos. 
    NPF-9 and NPF-17 issued to Duke Power Company (the licensee) for 
    operation of the McGuire Nuclear Station, Units 1 and 2, located in 
    Mecklenburg County, North Carolina.
        The proposed amendment would correct a technical deficiency 
    existing in the Technical Specifications (TS) which has caused 
    difficulty to plant operations when swapping of the NV pumps was needed 
    in Modes 4, 5, and 6. This amendment is requested to permit flexibility 
    in the operation of the NV pumps during unit startup. McGuire Unit 1 is 
    currently in cycle 10 startup process.
        Before issuance of the proposed license amendment, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        The Commission has made a proposed determination that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendment would not (1) 
    involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
        1. Basis for Conclusion That the Amendment Would Not Involve a 
    Significant Increase in the Probability or Consequences of an 
    Accident Previously Evaluated:
        No significant increase in probability of an accident previously 
    analyzed will occur. While the probability of the mass addition 
    pressure transient will increase slightly, this increase is judged 
    to be insignificant due to the short time of operation with two NV 
    pumps (15 minutes) and the accompanying TS 3.4.9.3 
    requirement for two operable NC system PORVs.
        The consequences of the mass addition pressure transient 
    accident will not increase for the same reasons described above.
        2. Basis for Conclusion that the Amendment Would Not Create the 
    Possibility of a New or Different Kind of Accident From Any 
    Previously Analyzed:
        The accident related to the operation of an additional NV pump 
    is the mass addition pressure transient accident as previously 
    analyzed and documented in the basis for TS 3.1.2.3, 3.1.2.4, and 
    3.5.3. No other new accident or different kind of accident will be 
    created by allowing two NV pump operation for 15 minutes via this 
    proposed TS Amendment.
        3. Basis for Conclusion That the Amendment Would Not Represent A 
    Significant Reduction in A Margin of Safety:
        The margin of safety regarding the mass addition pressure 
    transient will not be appreciably decreased due to the short 
    duration (15 minutes) of two NV pump operation combined 
    with the operability of two NC system PORVs required by TS 3.4.9.3 
    in Mode 4 (300 deg.F). Additionally, the margin of safety 
    will be marginally increased as relates to the NC pump seal failure 
    small break LOCA due to the increased assurance of NC pump seal flow 
    during NV train swaps.
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three standards of 10 CFR 50.92(c) are 
    satisfied. Therefore, the NRC staff proposes to determine that the 
    amendment request involves no significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within 30 days after the date of 
    publication of this notice will be considered in making any final 
    determination.
        Normally, the Commission will not issue the amendment until the 
    expiration of the 30-day notice period. However, should circumstances 
    change during the notice period such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendment before the expiration of 
    the 30-day notice period, provided that its final determination is that 
    the amendment involves no significant hazards consideration. The final 
    determination will consider all public and State comments received. 
    Should the Commission take this action, it will publish in the Federal 
    Register a notice of issuance and provide for opportunity for a hearing 
    after issuance. The Commission expects that the need to take this 
    action will occur very infrequently.
        Written comments may be submitted by mail to the Rules Review and 
    Directives Branch, Division of Freedom of Information and Publications 
    Services, Office of Administration, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555, and should cite the publication date and page 
    number of this Federal Register notice. Written comments may also be 
    delivered to Room 6D22, Two White Flint North, 11545 Rockville Pike, 
    Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. 
    Copies of written comments received may be examined at the NRC Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC 
    20555.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
        By November 14, 1994, the licensee may file a request for a hearing 
    with respect to issuance of the amendment to the subject facility 
    operating license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene. Requests for a hearing and a petition for leave to intervene 
    shall be filed in accordance with the Commission's ``Rules of Practice 
    for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
    persons should consult a current copy of 10 CFR 2.714 which is 
    available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC 20555 and at the local 
    public document room located at Atkins Library, University of North 
    Carolina, Charlotte (UNCC Station), North Carolina 28223. If a request 
    for a hearing or petition for leave to intervene is filed by the above 
    date, the Commission or an Atomic Safety and Licensing Board, 
    designated by the Commission or by the Chairman of the Atomic Safety 
    and Licensing Board Panel, will rule on the request and/or petition; 
    and the Secretary or the designated Atomic Safety and Licensing Board 
    will issue a notice of hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) The nature of the petitioner's right under the 
    Act to be made party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspects(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the basis of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue to law or fact. Contentions shall be limited to matters within 
    the scope of the amendment under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If a hearing is requested, the Commission will make a final 
    determination on the issue of no significant hazards consideration. The 
    final determination will serve to decide when the hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendment and make it immediately effective, notwithstanding the 
    request for a hearing. Any hearing held would take place after issuance 
    of the amendment.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendment.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555, Attention: Docketing and Services 
    Branch, or may be delivered to the Commission's Public Document Room, 
    the Gelman Building, 2120 L Street, NW., Washington, DC 20555, by the 
    above date. Where petitions are filed during the last 10 days of the 
    notice period, it is requested that the petitioner promptly so inform 
    the Commission by a toll-free telephone call to Western Union at 1-
    (800) 248-5100 (in Missouri 1-(800) 342-6700). The Western Union 
    operator should be given Datagram Identification Number N1023 and the 
    following message addressed to Herbert N. Berkow, petitioner's name and 
    telephone number, date petition was mailed, plant name, and publication 
    date and page number of this Federal Register notice. A copy of the 
    petition should also be sent to the Office of the General Counsel, U.S. 
    Nuclear Regulatory Commission, Washington, DC 20555, and to Mr. Albert 
    Carr, Duke Power Company, 422 South Church Street, Charlotte, North 
    Carolina 28242, attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1) (i)-(v) and 2.714(d).
        For further details with respect to this section, see the 
    application for amendment dated October 4, 1994, which is available for 
    public inspection at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC 20555 and at the local 
    public document room located at Atkins Library, University of North 
    Carolina, Charlotte (UNCC Station), North Carolina 28223.
    
        Dated at Rockville, Maryland, this 6th day of October, 1994.
    
        For the Nuclear Regulatory Commission.
    Victor Nerses,
    Project Manager, Project Directorate II-3, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    [FR Doc. 94-25303 Filed 10-12-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
10/13/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-25303
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: October 13, 1994, Docket Nos. 50-369 and 50-370