98-27345. 4.5 Foot Spillway Gate Extensions, Glen Canyon Dam  

  • [Federal Register Volume 63, Number 197 (Tuesday, October 13, 1998)]
    [Notices]
    [Pages 54730-54732]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-27345]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF THE INTERIOR
    
    Bureau of Reclamation
    
    
    4.5 Foot Spillway Gate Extensions, Glen Canyon Dam
    
    AGENCY: Bureau of Reclamation, Interior.
    
    ACTION: Decision to postpone installation.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Based upon recommendations from the Adaptive Management Work 
    Group (AMWG), the Secretary of the Interior has decided to postpone the 
    permanent installation of the 4.5 foot spillway gate extensions on Glen 
    Canyon Dam. During this postponement, the operation of the dam, as 
    stated in the Record of Decision, shall be in accordance with the 
    Annual Operating Plan (AOP) process and shall not include the 
    reservation of storage to compensate for space that would have been 
    created by the installation of the spillway gate extensions.
    
    SUPPLEMENTARY INFORMATION: Since large dam releases have significant 
    impacts on downstream resources, the Glen Canyon Dam Environmental 
    Impact Statement (GCDEIS) contained recommendations on restricting the 
    frequency of large releases above powerplant capacity, citing two 
    options for controlling such releases. The Record Of Decision (ROD) for 
    the GCDEIS selected the option of installing spillway gate extensions 
    rather than the option of providing a greater vacant storage space 
    buffer to reduce the frequency of powerplant bypasses.
    
    GCDEIS and Grand Canyon Protection Act (GCPA) Conclusions Regarding 
    Powerplant Bypasses
    
        The majority of the Glen Canyon Environmental Studies (GCES) Phase 
    1 research work took place in the mid-1980's, when the releases from 
    Glen Canyon Dam were at an all time high since the construction of the 
    dam. These flood flows were radically different than historic releases 
    and caused such large downstream effects that they greatly influenced 
    the GCES recommendations. On page 83 of the final GCES Phase 1 report, 
    the first and foremost conclusion was that ``Adverse downstream 
    consequences are caused primarily by sustained flood releases 
    significantly greater than powerplant capacity and by fluctuating 
    releases'', noting the erosive effect of floods on sand deposits and 
    vegetation. Generally, these conclusions suggested the elimination or 
    reduction of flood flows.
        In the committee report accompanying the GCPA legislation, the 
    Congress continued this thinking on adverse impacts by stating that 
    ``Flood releases from the dam erode beaches used by recreational 
    rafters and campers. The river's now reduced sediment loads are 
    inadequate to replenish beaches, even if flood releases occur once 
    every twenty years. Flood releases destroy riparian vegetation and 
    birds.'' The Act did not specify remedial measures, but seemed to imply 
    that even the aggressive spill avoidance strategy that had been 
    implemented to reduce spill frequency might be insufficient.
        These conclusions produced the GCDEIS decision to reduce the return 
    period of powerplant bypasses above 45,000 cfs to no more than an 
    average of 1 in 100 years. The option of installing the spillway gate 
    extensions was selected as part of the preferred alternative instead of 
    the option of targeting an additional 750,000 acre-feet of vacant 
    storage space when the reservoir filled in July. The extensions were 
    determined to be 4.5 feet in height, in contrast to the 8-foot high 
    extensions installed during 1983. Additional questions about the need 
    to reduce the frequency of powerplant bypasses and the desired 
    magnitude and impacts of sustained high releases during extreme flood 
    years now provide impetus to re-examine the original decision that an 
    additional 750,000 acre-feet of vacant storage space is needed through 
    the installation of the gate extensions.
    
    The Evolution of Understanding Regarding High Releases
    
        Despite the enormous beaches created by the 1983 spill event, the 
    general thinking at that time was that there was a very limited supply 
    of sediment below Glen Canyon Dam and that spills destructively moved 
    much of this sediment out of the Grand Canyon. During the high flow 
    years of 1984-1986, the main channel sediment storage was likely much 
    lower than prior to 1983, and the deposition rate during the 1984-1986 
    spills was lower as a result. Sediment experts then believed that the 
    river downstream of the dam was in a sediment-starved condition. 
    Sediment supply thus became one of the primary driving
    
    [[Page 54731]]
    
    forces behind ecological recommendations for changing powerplant 
    operations.
        Based upon continuing research, including evaluation of the Beach 
    Habitat Building Flow (BHBF), sediment researchers now believe that 
    flood flows counteract the possible adverse impacts that fluctuations 
    have on beach erosion, thus rebuilding the deposits that would 
    eventually slough back into the eddies, regardless of the nature of the 
    powerplant operations. Some suggested that more frequent floods could 
    allow higher levels of fluctuations.
    
    The Agreement Contained in the 1996 AOP
    
        With this evolving positive view towards spills, a desire for a 
    test of the GCDEIS BHBF was expressed by the Transition Work Group 
    beginning in 1994. The Basin States strongly opposed this request for a 
    purposeful powerplant bypass because the 1968 Colorado River Basin 
    Project Act requires avoiding anticipated spills, interpreted as 
    powerplant bypasses. This opposition created an impasse that blocked 
    such a test.
        Additional discussions between members of the Transition Work Group 
    and the Basin States resulted in a proposal for a modification of the 
    GCDEIS preferred alternative, that of moving BHBF from years of low 
    reservoir conditions (when spills would not be required for hydrologic 
    reasons) to years of high reservoir conditions and high inflows. Thus a 
    BHBF would occur in years when there was an expectation of having a 
    hydrological induced spill. This agreement was institutionalized in the 
    1996 AOP for the Colorado River and signed by the Secretary of the 
    Interior in December 1995. A subsequent BHBF test was conducted in 
    April 1996, confirming the hypothesis that high flows could rebuild 
    sandbar deposits. In December 1996, the GCDEIS Record of Decision was 
    assigned by the Secretary of the Interior and included this 
    modification to the preferred alternative.
    
    Impacts of Using Spillway Gate Extensions
    
    GCDEIS Expectations Related To Spillway Gate Extensions
    
        The Colorado River Simulation System (CRSS) modeling,which formed 
    the hydrologic basis for many of the GCDEIS decisions, determined that 
    bypasses were rare events, and if a small amount of buffer space were 
    provided, releases greater than 45,000 cfs could be avoided. Since it 
    uses a monthly time step, the CRSS model could not really estimate the 
    peak bypass release other than to average the release over the month in 
    which it occurred. Thus some judgment was used in estimating the 
    frequency of releases greater than 45,000 cfs.
    
    The Limited Value of the Spillway Gate Extensions
    
        The GCDEIS commitment to install the 4.5-foot extensions would 
    produce about 750,000 acre-feet of surcharge storage space above the 
    normal maximum water surface of 3700 feet. While this is a large amount 
    of reservoir space, it is small in comparison to either average April--
    July inflow which is about 7.8 MAF or the 2.1 MAF forecast error term 
    for June 1 (5 percent exceedence level). A buffer of this size would 
    affect primarily moderately high years in which bypasses were on the 
    range of several hundred thousand acre-feet. Such bypasses could be 
    reduced or eliminated entirely by storing the excess inflow behind the 
    gate extensions until it could be released through the powerplant.
        Inflow volumes of extremely high inflow years such as 1983 or 1984 
    had return periods of about 1 in 100 years. These are the types of 
    years which would produce releases in excess of 45,000 cfs, perhaps for 
    an extended period of time as occurred in 1983. The volume of bypasses 
    in these types of years are very large, 3.4 MAF in 1983 and 1.0 MAF in 
    1984. The greatest determining factor in the amount of bypass is the 
    forecast error associated with high inflow years.
        In contrast, moderately high inflow years such as 1985, 1986, and 
    1995 would cause bypasses of about 100,000 to 800,000 acre-feet using 
    current operating practices. These bypass volumes could be released 
    through the outlet tubes in 3 to 25 days, thus limiting total releases 
    to 45,000 cfs or less. During these types of years, it would be very 
    unlikely that use of the spillways would be required.
    
    The Need to Reduce the Frequency of Powerplant Bypasses
    
        Current thinking among sediment experts is that, given high flow 
    conditions resulting from large runoff years, releases above 25,000 cfs 
    should be preceded by BHBFs. The BHBF should be greater in magnitude 
    than the highest expected future release. This not only moves sediment 
    higher on beaches away from future releases, but also coarsens the main 
    channel bed which reduces future sediment transport. Some sediment 
    experts believe that there is sufficient regeneration of main channel 
    sediment supplies to allow BHBFs in all years that such events would be 
    allowed by the 1996 agreement, even every year if possible. Longer 
    duration spills may have different effects than the short duration 
    BHBFs, so additional sediment transport modeling would help clarify the 
    allowable frequency of such spills.
    
    The Positive Value of the Spillway Gate Extensions
    
        Although the extensions are not required to limit spillway use to 
    the 1 in 100 year return period cited in the GCDEIS, some limited value 
    can be gained from their installation during years in which peak 
    releases would be less than 45,000 cfs. In these cases, if the total 
    bypass volume was expected to be 750,000 acre-feet or less, then the 
    entire expected bypasses could be stored behind the extensions and 
    released later in the summer. This might produce some environmental 
    benefits by not releasing greater than 30,000 cfs if such releases 
    would cause ecological harm. However, it would also carry the dam 
    safety risks associated with purposefully storing more water in the 
    reservoir than was assumed during the design of the spillways. If an 
    extremely rare high inflow event occurred, it could conceivably overtop 
    the dam, even with full use of the spillways.
        It appears from this discussion, that only inflow years with a 
    return period of about 1 in 100 years would force the use of the 
    spillways and release more than 45,000 cfs. Reclamation believes that 
    current operating practices under the AOP would initiate high 
    powerplant releases and bypasses early enough as required to safely 
    operate the dam, thus meeting the intent of the GCDEIS provision 
    without requiring either the additional storage buffer or the spillway 
    gate extensions.
    
    Decision
    
        Based upon the analysis and comments received from the AMWG the 
    Secretary of the Interior has decided to postpone permanent 
    installation of the 4.5 foot spillway gate extensions. During the 
    postponement period, operation of the dam, as stated in the Record of 
    Decision, shall be in accordance with the AOP process and shall not 
    include reservation of storage to compensate for that space that would 
    have been created by the gate extensions. Also, Reclamation will report 
    annually to the technical Work Group and AMWG on the effect of not 
    installing the gate extensions on: (1) The probability of meeting BHBF 
    triggering criteria and (2) the probability of limiting spills greater 
    than 45,000 cfs to a 1 in 100 frequency.
    
    
    [[Page 54732]]
    
    
        Dated: October 6, 1998.
    R. Steve Richardson,
    Acting Commissioner, Bureau of Reclamation.
    [FR Doc. 98-27345 Filed 10-9-98; 8:45 am]
    BILLING CODE 4310-94-M
    
    
    

Document Information

Published:
10/13/1998
Department:
Reclamation Bureau
Entry Type:
Notice
Action:
Decision to postpone installation.
Document Number:
98-27345
Pages:
54730-54732 (3 pages)
PDF File:
98-27345.pdf