98-27346. STP Nuclear Operating Company, South Texas Project, Units 1 and 2; Confirmatory Order Modifying License, Effective Immediately  

  • [Federal Register Volume 63, Number 197 (Tuesday, October 13, 1998)]
    [Notices]
    [Page 54737]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-27346]
    
    
    
    [[Page 54737]]
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-498 and 499]
    
    
    STP Nuclear Operating Company, South Texas Project, Units 1 and 
    2; Confirmatory Order Modifying License, Effective Immediately
    
    I
        STP Nuclear Operating Company, (the Licensee) is the holder of 
    Facility Operating License Nos. NPF-76 and NPF-80, which authorizes 
    operation of South Texas Project, Units 1 and 2, located in Matagorda 
    County, TX.
    II
        The staff of the U.S. Nuclear Regulatory Commission (NRC) has been 
    concerned that Thermo-Lag 330-1 fire barrier systems installed by 
    licensees may not provide the level of fire endurance intended and that 
    licensees that use Thermo-Lag 330-1 fire barriers may not be meeting 
    regulatory requirements. During the 1992 to 1994 timeframe, the NRC 
    staff issued Generic Letter (GL) 92-08, ``Thermo-Lag 330-1 Fire 
    Barriers'' and subsequent requests for additional information that 
    requested licensees to submit plans and schedules for resolving the 
    Thermo-Lag issue. The NRC staff has obtained and reviewed all 
    licensees' corrective plans and schedules. The staff is concerned that 
    some licensees may not be making adequate progress toward resolving the 
    plant-specific issues, and that some implementation schedules may be 
    either too tenuous or too protracted. For example, several licensees 
    informed the NRC staff that their completion dates had slipped by 6 
    months to as much as 3 years. For plants that have completion action 
    scheduled beyond 1997, the NRC staff has discussed with these licensees 
    the progress of the licensees' corrective actions and the extent of 
    licensee management attention regarding completion of Thermo-Lag 
    corrective actions. South Texas Project, Units 1 and 2, are two of the 
    plants whose schedule extends beyond 1997.
        Based on the information submitted by STP Nuclear Operating 
    Company, the NRC staff has concluded that the schedules presented by 
    STP Nuclear Operating Company are reasonable. This conclusion is based 
    on (1) the amount of installed Thermo-Lag, (2) the complexity of the 
    plant-specific fire barrier configurations and issues, (3) the need to 
    perform certain plant modifications during outages as opposed to those 
    that can be performed while the plant is at power, and (4) integration 
    with other significant, but unrelated issues that STP Nuclear Operating 
    Company is addressing at its plant. In order to remove compensatory 
    measures such as fire watches, it has been determined that resolution 
    of the Thermo-Lag corrective actions by STP Nuclear Operating Company 
    must be completed in accordance with current STP Nuclear Operating 
    Company schedules. By letter dated June 15, 1998, the NRC staff 
    notified STP Nuclear Operating Company of its plan to incorporate STP 
    Nuclear Operating Company's schedule commitment into a requirement by 
    issuance of an order and requested consent from the Licensee. By letter 
    dated June 25, 1998, the Licensee provided its consent to issuance of a 
    Confirmatory Order.
    III
        The Licensee's commitment as set forth in its letter of June 25, 
    1998, is acceptable and is necessary for the NRC to conclude that 
    public health and safety are reasonably assured. To preclude any 
    schedule slippage and to assure public health and safety, the NRC staff 
    has determined that the Licensee's commitment in its June 25, 1998, 
    letter be confirmed by this Order. The Licensee has agreed to this 
    action. Based on the above, and the Licensee's consent, this Order is 
    immediately effective upon issuance.
    IV
        Accordingly, pursuant to sections 103, 161b, 161i, 161o, 182, and 
    186 of the Atomic Energy Act of 1954, as amended, and the Commission's 
    regulations in 10 CFR 2.202 and 10 CFR Part 50, it is hereby ordered, 
    effective immediately, that:
    
        STP Nuclear Operating Company shall complete final 
    implementation of Thermo-Lag 330-1 fire barrier corrective actions 
    at South Texas Project, Units 1 and 2, described in the STP Nuclear 
    Operating Company submittals to the NRC dated December 20, 1995, 
    August 26, 1996, November 6, 1996, and July 7, 1997, as modified and 
    summarized by the letters of April 15, 1998, and June 4, 1998, by 
    the end of 1998, excluding those corrective actions which are the 
    subject of the pending deviation request from Appendix R, Section 
    II.G.2.c, dated September 14, 1995, as supplemented by letters dated 
    November 6, 1996, May 22, 1997, August 4, 1997, and April 15, 1998, 
    for NRC staff review and approval pursuant to License Condition 2.E 
    of a change to the approved fire protection program. A schedule for 
    completion of any corrective actions associated with this request 
    will be determined separately.
    
        The Director, Office of Nuclear Reactor Regulation, may relax or 
    rescind, in writing, any provisions of this Confirmatory Order upon a 
    showing by the Licensee of good cause.
    V
        Any person adversely affected by this Confirmatory Order, other 
    than the Licensee, may request a hearing within 20 days of its 
    issuance. Where good cause is shown, consideration will be given to 
    extending the time to request a hearing. A request for extension of 
    time must be made in writing to the Director, Office of Nuclear Reactor 
    Regulation, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555, 
    and include a statement of good cause for the extension. Any request 
    for a hearing shall be submitted to the Secretary, U.S. Nuclear 
    Regulatory Commission, Attention: Chief, Rulemakings and Adjudications 
    Staff, Washington, D.C. 20555. Copies of the hearing request shall also 
    be sent to the Director, Office of Nuclear Reactor Regulation, U. S. 
    Nuclear Regulatory Commission, Washington, D. C. 20555, to the Deputy 
    Assistant General Counsel for Enforcement at the same address, to the 
    Regional Administrator, NRC Region IV, 611 Ryan Plaza Drive, Suite 400, 
    Arlington, Texas, 76011 and to the Licensee. If such a person requests 
    a hearing, that person shall set forth with particularity the manner in 
    which his/her interest is adversely affected by this Order and shall 
    address criteria set forth in 10 CFR 2.714(d).
        If a hearing is requested by a person whose interest is adversely 
    affected, the Commission will issue an Order designating the time and 
    place of any such hearing. If a hearing is held, the issue to be 
    considered at such hearing shall be whether this Confirmatory Order 
    should be sustained.
        In the absence of any request for hearing, or written approval of 
    an extension of time in which to request a hearing, the provisions 
    specified in Section IV above shall be final 20 days from the date of 
    this Order without further order or proceedings. If an extension of 
    time for requesting a hearing has been approved, the provisions 
    specified in Section IV shall be final when the extension expires if a 
    hearing request has not been received. An answer or a request for 
    hearing shall not stay the immediate effectiveness of this Order.
    
        Dated at Rockville, Maryland this 2nd day of October 1998.
    
        For the Nuclear Regulatory Commission.
    Samuel J. Collins,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-27346 Filed 10-9-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
10/13/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-27346
Pages:
54737-54737 (1 pages)
Docket Numbers:
Docket Nos. 50-498 and 499
PDF File:
98-27346.pdf