96-26401. Williams Natural Gas Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 61, Number 201 (Wednesday, October 16, 1996)]
    [Notices]
    [Page 53911]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-26401]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP97-14-000]
    
    
    Williams Natural Gas Company; Notice of Request Under Blanket 
    Authorization
    
    October 9, 1996.
        Take notice that on October 4, 1996, Williams Natural Gas Company 
    (WNG), P.O. Box 3288, Tulsa, Oklahoma 74101, filed in Docket No. CP97-
    14-000 a request pursuant to Secs. 157.205, 157.212 and 157.216 of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.212 and 157.216) for authorization to abandon by reclaim the 
    Western Resources, Inc. Jewell town border setting and a high pressure 
    regulator setting, and to relocate and construct a replacement town 
    border setting, all located in Jewell County, Kansas, under WNG's 
    blanket certificate issued in Docket No. CP82-479-000 pursuant to 
    Section 7 of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        WNG proposes to replace the Jewell town border setting with a skid-
    mounted positive displacement meter setting with two self-operated 
    pressure regulator cuts. The new facilities will be located across the 
    road from the existing site at the high pressure regulator location in 
    Jewell County, Kansas. The facilities are being relocated due to space 
    limitation and site stability at the present site.
        WNG states that the projected volume of delivery will remain 
    unchanged; the most recent annual volume through the Jewell town border 
    setting was 109,500 Dth with a peak day volume of 359 Dth. WGN 
    estimates the construction cost to be $21,679 and the reclaim cost to 
    be $3,285.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Sec. 157.205 of the 
    Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the 
    request. If no protest is filed within the time allowed therefor, the 
    proposed activity shall be deemed to be authorized effective the day 
    after the time allowed for filing a protest. If a protest is filed and 
    not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-26401 Filed 10-15-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
10/16/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-26401
Pages:
53911-53911 (1 pages)
Docket Numbers:
Docket No. CP97-14-000
PDF File:
96-26401.pdf