95-25687. Stampede Division, Washoe Project Notice of Rate Order No. WAPA- 67  

  • [Federal Register Volume 60, Number 200 (Tuesday, October 17, 1995)]
    [Notices]
    [Pages 53785-53789]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-25687]
    
    
    
    -----------------------------------------------------------------------
    
    
    DEPARTMENT OF ENERGY
    
    Stampede Division, Washoe Project Notice of Rate Order No. WAPA-
    67
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of rate order.
    
    -----------------------------------------------------------------------
    
    [[Page 53786]]
    
    
    SUMMARY: Notice is given of the confirmation and approval by the Deputy 
    Secretary of the Department of Energy (DOE) of Rate Order No. WAPA-67 
    and Rate Schedule SNF-4 placing the revised nonfirm energy rates for 
    energy from the Stampede Division, Washoe Project (Stampede) of the 
    Western Area Power Administration (Western) into effect on an interim 
    basis. These rates are the interim rates, called the provisional rates, 
    and they will remain in effect on an interim basis until the Federal 
    Energy Regulatory Commission (FERC) confirms, approves, and places them 
    into effect on a final basis or until they are replaced by other rates.
        Western has executed agreements with the Sierra Pacific Power 
    Company (Sierra), the U.S. Department of the Interior, Fish and 
    Wildlife Service (FWS) and the U.S. Department of the Interior, Bureau 
    of Reclamation (Reclamation) to provide service to project use 
    facilities. The costs associated with such service will be 
    nonreimbursable, and will not be recovered through the power revenues. 
    The remaining reimbursable costs and the energy remaining after meeting 
    project use service are used to calculate the cost recovery rate. This 
    rate ensures payment of all reimbursable expenses and investments 
    within the required time frames. The cost recovery rate is above the 
    current market price for nonfirm energy.
        Under Rate Schedule SNF-4, nonfirm energy that is available after 
    project use service has been met will be sold at a rate that is equal 
    to or higher than the Stampede Energy Exchange Account (SEEA) rate but 
    no greater than the cost recovery rate. Rate Schedule SNF-4 provides 
    the formulae to determine the SEEA and cost recovery rates for Stampede 
    nonfirm energy. These formulae are:
    
        The SEEA rate will be 85 percent of the then-effective non-time 
    differentiated rate as provided in Sierra's California Quarterly 
    Short-Term Purchase Price Schedule for As-Available Purchases from 
    Qualifying Facilities with Capacities of 100 kilowatts or less.
        The cost recovery rate is calculated by dividing the revenue 
    requirement needed to repay all reimbursable power costs by the 
    nonfirm energy remaining after meeting project use service.
    
        A comparison of existing and provisional rates follows:
    
    ----------------------------------------------------------------------------------------------------------------
                                                Existing rate as of July  Provisional rate October    Percentage of 
                                                        1, 1994                    1, 1995               change     
    ----------------------------------------------------------------------------------------------------------------
    Rate Schedule............................  SNF-3                      SNF-4                                     
    Floor (SEEA) Rate (mills/kWh)............  27.69                      19.26*                              -30.44
    Ceiling (Cost Recovery) Rate (mills/kWh).  67.39                      80.44**                              19.36
    ----------------------------------------------------------------------------------------------------------------
    *The average SEEA rate for FY 1995.                                                                             
    **The estimated cost recovery rate for FY 1996 through FY 2000.                                                 
    
        Under the existing rate schedule, Stampede nonfirm energy is sold 
    through an annual bidding process on a short-term nonfirm basis. A 
    floor and ceiling rate for the bidding process is calculated each year. 
    The floor rate is based on annual operation and maintenance expenses 
    plus two mills per kilowatthour, and the ceiling rate is the rate 
    required to repay annual expenses and investment within the required 
    time frames.
    
    DATES: Rate Schedule SNF-4 will be placed into effect on an interim 
    basis on October 1, 1995, and will be in effect until FERC confirms, 
    approves, and places the rate schedule in effect on a final basis, or 
    until the rate schedule is superseded.
    
    FOR FURTHER INFORMATION CONTACT:
    
    Mr. James C. Feider, Area Manager, Sacramento Area Office, Western Area 
    Power Administration, 114 Parkshore Drive, Folsom, CA 95630, (916) 353-
    4418
    Mr. Joel Bladow, Assistant Administrator for Washington Liaison, 
    Western Area Power Administration, Room 8G-027, Forrestal Building, 
    1000 Independence Avenue SW., Washington, DC 20585-0001, (202) 586-
    5581.
    
    SUPPLEMENTARY INFORMATION: By Amendment No. 3 to Delegation Order No. 
    0204-108, published November 10, 1993 (58 FR 59716), the Secretary of 
    Energy (Secretary) delegated (1) the authority to develop long-term 
    power and transmission rates on a nonexclusive basis to the 
    Administrator of Western; (2) the authority to confirm, approve, and 
    place such rates into effect on an interim basis to the Deputy 
    Secretary; and (3) the authority to confirm, approve, and place into 
    effect on a final basis, to remand, or to disapprove such rates to 
    FERC. Existing DOE procedures for public participation in power rate 
    adjustments are contained in 10 CFR Part 903.
        These power rates were developed pursuant to section 302(a) of the 
    DOE Organization Act, 42 U.S.C. 7152(a), through which the power 
    marketing functions of the Secretary of the Interior and Reclamation 
    under the Reclamation Act of 1902, 43 U.S.C. 371 et seq., as amended 
    and supplemented by subsequent enactments, particularly section 9(c) of 
    the Reclamation Project Act of 1939, 43 U.S.C. Sec. 485h(c), and other 
    acts specifically applicable to the project involved, were transferred 
    to and vested in the Secretary.
        Under Western's contract with Sierra, all Stampede nonfirm energy 
    is debited to the SEEA, at the SEEA rate. The cost of project use 
    service is then credited to the SEEA. Power remaining after meeting 
    project use service will be offered to other entities, giving priority 
    to preference customers, through an annual bidding process. Bids will 
    be accepted only if the bid rate is equal to or higher than the SEEA 
    rate, and less than the cost recovery rate. If no bid meets this 
    criteria, the nonfirm energy will be deemed sold to Sierra at the SEEA 
    rate.
        If the SEEA arrangements with Sierra are terminated, Western will 
    offer all available nonfirm energy for sale at the cost recovery rate, 
    or the highest rate bid that is below the cost recovery rate.
        Stampede power costs associated with providing project use service 
    are nonreimbursable pursuant to Public Law 84-858 (70 Stat. 777) and 
    Public Law 101-618 (104 Stat. 3289) and are not recovered through power 
    revenues. The amount of the annual nonreimbursable costs is calculated 
    by multiplying the total annual power costs by a ratio of the cost of 
    providing project use service to the revenues from Stampede generation 
    as recorded in the SEEA. The remaining reimbursable costs and energy 
    remaining after project use service has been provided are used to 
    calculate the cost recovery rate. The power repayment study and other 
    analyses indicate the revised cost 
    
    [[Page 53787]]
    recovery rate provides sufficient revenue to pay all reimbursable 
    annual costs including interest expense, plus repayment of required 
    investment within the allowable time period.
        Rate Order No. WAPA-67 confirming, approving, and placing the 
    proposed Stampede rate adjustment into effect on an interim basis, is 
    issued, and the new Rate Schedule SNF-4 will be submitted promptly to 
    FERC for confirmation and approval on a final basis.
    
        Issued in Washington, DC, September 29, 1995.
    Charles B. Curtis,
    Deputy Secretary.
    
    Department of Energy Deputy Secretary
    
        In the matter of: Western Area Power Administration Rate 
    Adjustment for Stampede Division, Washoe Project.
    
    [Rate Order No. WAPA-67]
    
    Order Confirming, Approving and Placing the Stampede Division, Washoe 
    Project Nonfirm Power Rates Into Effect on an Interim Basis
    
    October 1, 1995.
        These power rates were developed pursuant to section 302(a) of the 
    Department of Energy (DOE) Organization Act, 42 U.S.C. 7152(a), through 
    which the power marketing functions of the Secretary of the Interior 
    and the Bureau of Reclamation (Reclamation) under the Reclamation Act 
    of 1902, 43 U.S.C. 371 et seq., as amended and supplemented by 
    subsequent enactments, particularly section 9(c) of the Reclamation 
    Project Act of 1939, 43 U.S.C. 485h(c), and other acts specifically 
    applicable to the project involved, were transferred to and vested in 
    the Secretary of Energy (Secretary).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary delegated (1) the 
    authority to develop long-term power and transmission rates on a 
    nonexclusive basis to the Administrator of the Western Area Power 
    Administration (Western); (2) the authority to confirm, approve, and 
    place such rates into effect on an interim basis to the Deputy 
    Secretary; and (3) the authority to confirm, approve, and place into 
    effect on a final basis, to remand, or to disapprove such rates to the 
    Federal Energy Regulatory Commission (FERC). Existing DOE procedures 
    for public participation in power rate adjustments are contained in 10 
    CFR Part 903.
    
    Acronyms and Definitions
    
        As used in this rate order, the following acronyms and definitions 
    apply:
    
    DOE: U.S. Department of Energy
    DOE Order RA 6120.2: A Department of Energy order dealing with power 
    marketing administration financial reporting.
    FERC: Federal Energy Regulatory Commission
    FWS: U.S. Department of the Interior, Fish and Wildlife Service
    FY: Fiscal Year
    kW: Kilowatt
    kWh: Kilowatthour
    mills/kWh: Mills per kilowatthour
    PRS: Power repayment study
    Reclamation: U.S. Department of the Interior, Bureau of Reclamation
    SEEA: Stampede Energy Exchange Account
    Sierra: Sierra Pacific Power Company
    Stampede: Stampede Division, Washoe Project
    Western: U.S. Department of Energy, Western Area Power Administration
    
    Effective Date
    
        The rates will become effective on an interim basis on October 1, 
    1995, and will be in effect pending FERC's approval of them or 
    substitute rates on a final basis for a 5-year period, or until 
    superseded.
    
    Public Notice and Comment
    
        The Procedures for Public Participation in Power and Transmission 
    Rate Adjustments and Extensions, 10 CFR Part 903, have been followed by 
    Western in the development of these nonfirm power rates. Stampede is a 
    power system which normally has annual sales less that 100 million kWh 
    and an installed capacity of less than 20,000 kW; therefore this rate 
    adjustment constitutes a minor rate adjustment as defined by 10 CFR 
    Part 903.2(f). Since this is a minor rate adjustment, no public 
    meetings were scheduled; however, Western accepted comments from 
    interested parties.
        The following summarizes the steps Western took to allow 
    involvement of interested parties in the rate process:
        1. A Federal Register notice was published on June 5, 1995 (60 FR 
    29586), officially announcing the proposed nonfirm power rate 
    adjustment, initiating the public consultation and comment period.
        2. On June 14, 1995 a letter was mailed from Western's Sacramento 
    Area Office to all interested parties announcing the publication of the 
    Federal Register notice on June 5, 1995.
        3. On June 15, 1995 a rate adjustment brochure was available to all 
    interested parties upon request.
        4. The comment period ended on July 5, 1995; no comments or 
    requests for information were received during the comment period.
    
    Project History
    
        The Stampede Dam was authorized under the Washoe Project Act of 
    August 1, 1956 (70 Stat. 775). Power facilities were not constructed 
    when Stampede Dam was built because the power function was determined 
    not economically justified at the time. A re-evaluation of a powerplant 
    at Stampede was conducted and published in a special Reclamation 
    report, Adding Powerplants at Existing Federal Dams in California, in 
    July 1976. Reclamation recommended construction of the Stampede 
    powerplant, and construction was completed in 1987. Since 1988, energy 
    produced at the Stampede powerplant has been sold to the highest bidder 
    on a short-term nonfirm basis, as the preference entity, defined in the 
    marketing plan for Stampede power, has been unable to contract for 
    transmission from Stampede to their point of delivery. In addition, the 
    Stampede floor and ceiling rates calculated in accordance with the 
    existing rate schedule has been higher than the market rate for nonfirm 
    energy.
        FWS facilities at Stampede were authorized by the Washoe Project 
    Act of August 1, 1956 (70 Stat. 775). Lahonton Fish Hatchery and the 
    Marble Bluff Fish Facility were designated as project use facilities by 
    Reclamation, but Western has been unable to provide project use service 
    because transmission service was not available. On April 1, 1994 
    Western executed Contract No. 94-SAO-00010 with Sierra which 
    established the SEEA and provides Western the mechanism necessary to 
    provide project use power to FWS. Western entered into an agreement 
    with FWS for project use service on June 29, 1994. Subsequently, on 
    December 19, 1994, Western and Reclamation entered into Letter of 
    Agreement No. 94-SAO-00036 which provides the method to determine the 
    percentage of the annual costs of Stampede operation, maintenance, 
    interest expense and capital cost repayment associated with providing 
    project use service to be nonreimbursable. Nonreimbursable costs are 
    not recovered through power revenues. The nonreimbursable costs are 
    based on the ratio of the annual cost of project use service to the 
    total annual revenue recorded in the SEEA from Stampede nonfirm energy. 
    This percentage has been applied to all current and future year costs 
    in the Stampede PRS.
    
    [[Page 53788]]
    
    
    Power Repayment Studies
    
        A PRS is prepared each year to determine if power revenues will be 
    sufficient to pay, within the prescribed time periods, all reimbursable 
    costs assigned to the power function. Repayment criteria are based on 
    law, policies, and authorizing legislation. DOE Order RA 6120.2, 
    section 12b, requires that:
    
        In addition to the recovery of the above costs (operation and 
    maintenance and interest expenses) on a year-by-year basis, the 
    expected revenues are at least sufficient to recover (1) each dollar 
    of power investment at Federal hydroelectric generating plants 
    within 50 years after they become revenue producing, except as 
    otherwise provided by law; (2) each annual increment of Federal 
    transmission investment within the average service life of such 
    transmission facilities or within a maximum of 50 years, whichever 
    is less; plus, (3) the cost of each replacement of a unit of 
    property of a Federal power system within its expected service life 
    up to a maximum of 50 years.
    
    Existing and Provisional Rates
    
        A comparison of the existing and provisional rates follows:
    
                                      Comparison of Existing and Provisional Rates                                  
    ----------------------------------------------------------------------------------------------------------------
                                                                                                          Percentage
                                    Existing rate as of July 1, 1994   Provisional rate October 1, 1995   of change 
    ----------------------------------------------------------------------------------------------------------------
    Rate Schedule................  SNF-3............................  SNF-4............................  ...........
    Floor (SEEA) Rate (mills/kWh)  27.69............................  19.26*...........................       -30.44
    Ceiling (Cost Recovery) Rate   67.39............................  80.44**..........................        19.36
     (mills/kWh).                                                                                                   
    ----------------------------------------------------------------------------------------------------------------
    *The average SEEA rate for FY 1995.                                                                             
    **The estimated cost recovery rate for FY 1996 through FY 2000.                                                 
    
        The formula for the SEEA rate is:
        The SEEA rate will be 85 percent of the then-effective non-time-
    differentiated rate as provided in Sierra's California Quarterly Short-
    Term Purchase Price Schedule for As- Available Purchases from 
    Qualifying Facilities with Capacities of 100 kW or less.
        The formula for the cost recovery rate is:
        The cost recovery rate is calculated by dividing the revenue 
    requirement needed to repay all reimbursable power costs by the nonfirm 
    energy remaining after meeting project use service.
        Under the existing rate schedule, Stampede nonfirm energy is sold 
    through an annual bidding process on a short-term nonfirm basis. A 
    floor and ceiling rate for the bidding process is calculated each year. 
    The floor rate is based on annual operation and maintenance expenses 
    plus two mills per kilowatthour, and the ceiling rate is the rate 
    required to repay annual expenses and investment within the required 
    time frames.
    
    Certification of Rate
    
        Western's Administrator has certified that the Stampede nonfirm 
    power rates placed into effect on an interim basis herein are the 
    lowest possible rates consistent with sound business principles. The 
    rates have been developed in accordance with administrative policies 
    and applicable laws.
    
    Discussion
    
        Sierra has agreed to purchase all Stampede generation at the SEEA 
    rate. The dollar value from these sales are debited to the SEEA. Bills 
    for project use service at Lahonton Fish Hatchery and Marble Bluff Fish 
    Facility are then credited to the SEEA. During April of each year, any 
    balance in the SEEA may be converted to an energy amount and offered to 
    other entities, with priority given to preference customers.
        The energy remaining after meeting project use service is 
    calculated by dividing the dollar balance in the SEEA by 85 percent of 
    the then-effective time-differentiated rate as provided in Sierra's 
    California Quarterly Short-Term Purchase Price Schedule for As-
    Available purchases from Qualifying Facilities with Capacities of 100 
    kW or less. Power remaining after meeting project use service will be 
    offered to interested parties and preference customers through an 
    annual bidding process. Bids will be accepted only if the bid rate is 
    equal to or higher than the SEEA rate and less than the cost recovery 
    rate. If no bid meets this criteria, the nonfirm energy will be deemed 
    sold to Sierra at the SEEA rate. If the SEEA arrangements with Sierra 
    are terminated, Western will offer all available nonfirm energy for 
    sale at the cost recovery rate, or the highest rate bid that is below 
    the cost recovery rate.
        Western prepared a PRS which identified power related costs for the 
    study period. A percentage equal to the ratio of the estimated cost for 
    project use service to the estimated revenue from Stampede generation 
    recorded in the SEEA was applied to the power costs to determine the 
    amount of nonreimbursable cost. The remaining reimbursable cost and the 
    estimated energy remaining after meeting project use service were used 
    to determine the cost recovery rate necessary for repayment of 
    Stampede. The cost recovery rate was designed to allow repayment of the 
    reimbursable portion of the plant investment, operation and maintenance 
    expenses, capitalized deficits, interest expenses, and replacements 
    based on the nonfirm energy available for sale after project use 
    service has been met.
    
    Statement of Revenue and Related Expenses
    
        The following table provides a summary of revenue and expense data 
    through the 5-year proposed rate approval period.
    
       Stampede Division, Washoe Project, 5-Year Rate Period, Revenues and  
                                    Expenses                                
    ------------------------------------------------------------------------
                                                                  Rate case 
                                                                     PRS    
                                                                reimbursable
                                                                 revenue and
                                                                  expenses  
                                                                 1996-2000* 
    ------------------------------------------------------------------------
    Revenues..................................................    $1,357,713
    Expenses:                                                               
      O&M.....................................................      $324,749
      Interest................................................       900,120
      Capitalized Expenses....................................       132,844
                                                               -------------
          Total...............................................    $1,357,713
    ------------------------------------------------------------------------
    *Data reflects costs remaining to be repaid through power revenues after
      applying nonreimbursable percentage.                                  
    
    Comments
    
        During the 30-day comment period, Western did not receive any 
    written comments either requesting information or commenting on the 
    rate adjustment.
    
    Environmental Evaluation
    
        In compliance with the National Environmental Policy Act of 1969, 
    42 U.S.C. 4321 et seq.; Council on Environmental Quality Regulations 
    (40 CFR Parts 1500-1508); and DOE NEPA 
    
    [[Page 53789]]
    Regulations (10 CFR Part 1021), Western has determined that this action 
    is categorically excluded from the preparation of an environmental 
    assessment or an environmental impact statement. A categorical 
    exclusion was issued on May 1, 1995.
    
    Executive Order 12866
    
        DOE has determined that this rate action is not a significant 
    regulatory action because it does not meet the criteria of Executive 
    Order 12866, 58 CFR 51735. Western has an exemption from centralized 
    regulatory review under Executive Order 12866; accordingly, no 
    clearance of this notice by the Office of Management and Budget is 
    required.
    
    Availability of Information
    
        Information regarding this rate adjustment, including PRSs, 
    letters, memorandums, and other supporting material made or kept by 
    Western for the purpose of developing the nonfirm energy rate, is 
    available for public review in the Sacramento Area Office, Western Area 
    Power Administration, Office of the Assistant Area Manager for Power 
    Marketing, 114 Parkshore Drive, Folsom, California 95630; and Western 
    Area Power Administration, Office of the Assistant Administrator for 
    Washington Liaison, Room 8G-027 Forrestal Building, 1000 Independence 
    Avenue SW., Washington, DC 20585.
    
    Submission to Federal Energy Regulatory Commission
    
        The rates herein confirmed, approved, and placed into effect on an 
    interim basis, together with supporting documents, will be submitted to 
    FERC for confirmation and approval on a final basis.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me by the Secretary of Energy, I confirm and approve on an interim 
    basis, effective October 1, 1995, Rate Schedule SNF-4 for the Stampede 
    Division, Washoe Project. The rate schedule shall remain in effect on 
    an interim basis, pending FERC confirmation and approval or a 
    substitute rate on a final basis, through September 30, 2000.
    
        Issued in Washington, DC, September 29, 1995.
    Charles B. Curtis,
    Deputy Secretary.
    Rate Schedule SNF-4
    (Supersedes Schedule SNF-3)
    
    United States Department of Energy, Western Area Power Administration, 
    Stampede Division, Washoe Project
    
    Schedule of Rate for Nonfirm Energy
    
        Effective: October 1, 1995, through September 30, 2000.
        Available: Within the marketing area served by the Sacramento Area 
    Office.
        Applicable: This rate is applicable to sales of nonfirm energy in 
    excess of project use service. Sales shall be subject to terms and 
    conditions among the respective entities specified at the time of sale.
        Rate: The rate for nonfirm energy sales from Stampede will be equal 
    to or greater than the Stampede Energy Exchange Account (SEEA) rate and 
    less than the cost recovery rate. The SEEA rate is 85 percent of the 
    then-effective non-time-differentiated rate as provided in the Sierra 
    Pacific Power Company's California Quarterly Short-Term Purchase Price 
    Schedule for As-Available Purchases from Qualifying Facilities with 
    Capacities of 100 kilowatts or less.
        The cost recovery rate is calculated by dividing the revenue 
    requirement needed to repay all annual reimbursable power costs by the 
    nonfirm energy remaining after providing project use service.
    
    [FR Doc. 95-25687 Filed 10-16-95; 8:45 am]
    BILLING CODE 6450-01-P
    
    

Document Information

Effective Date:
10/1/1995
Published:
10/17/1995
Department:
Energy Department
Entry Type:
Notice
Action:
Notice of rate order.
Document Number:
95-25687
Dates:
Rate Schedule SNF-4 will be placed into effect on an interim basis on October 1, 1995, and will be in effect until FERC confirms, approves, and places the rate schedule in effect on a final basis, or until the rate schedule is superseded.
Pages:
53785-53789 (5 pages)
PDF File:
95-25687.pdf