95-25905. Transcontinental Gas Pipe Line Corporation; Notice of Application  

  • [Federal Register Volume 60, Number 202 (Thursday, October 19, 1995)]
    [Notices]
    [Pages 54073-54074]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-25905]
    
    
    
    -----------------------------------------------------------------------
    
    [[Page 54074]]
    
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-16-000]
    
    
    Transcontinental Gas Pipe Line Corporation; Notice of Application
    
    October 13, 1995.
        Take notice that on October 10, 1995, Transcontinental Gas Pipe 
    Line Corporation (Transco) P.O. Box 1396, Houston, Texas 77251, filed 
    in Docket No. CP96-16-000 an application, pursuant to Section 7(c) of 
    the Natural Gas Act, for a certificate of public convenience and 
    necessity for (1) authorization to construct and operate certain 
    pipeline facilities on Transco's mainline pipeline system in order to 
    create additional firm transportation capacity, extending from 
    Transco's production area in Louisiana to the vicinity of the border 
    between North Carolina and South Carolina (designated as the SunBelt 
    Expansion Project) and (2) approval of incremental initial rates for 
    the firm transportation service to be rendered through such incremental 
    firm transportation capacity, all as more fully set forth in the 
    application which is on file with the Commission and open to public 
    inspection.
        Transco states that the SunBelt Expansion Project is an incremental 
    expansion of Transco's mainline in its Southeastern market area which 
    will provide the dekatherm equivalent of 145,666 Mcf per day (Mcf/d) of 
    additional firm transportation capacity. Transco proposes an in-service 
    date of November 1, 1997. Transco states that the incremental capacity 
    will provide access to two of Transco's major supply areas; 100,001 
    Mcf/d of the capacity will commence at Transco's Station 65 in St. 
    Helena Parish, Louisiana and 45,665 Mcf/d will commence at Station No. 
    85, which is at the point of interconnection between Transco's mainline 
    and its Mobile Bay Lateral near Butler, Alabama. The incremental 
    capacity will extend to points of delivery in the vicinity of Transco's 
    Station No. 145 near the North Carolina and South Carolina border.
        Transco states that the firm transportation service under the 
    SunBelt Expansion Project will be rendered pursuant to Rate Schedule FT 
    of Transco's FERC Gas Tariff. Transco proposes initial rates designed 
    on a straight fixed-variable rate design methodology and an incremental 
    cost of service designed to recover the cost of the proposed 
    facilities.
        In order to expand system capacity, Transco proposes to construct 
    and operate the following facilities:
    
        (1) A 15,000 Horsepower (HP) compressor addition at Transco's 
    Station 80 in Jones and Jasper Counties, Mississippi.
        (2) Modifications to existing compressor equipment at Transco's 
    Station 100 in Chilton County, Alabama to eliminate or modify 
    current air permit restrictions, thereby allowing increased annual 
    operating hours and resulting in a uprate of 900 HP.
        (3) A 15,000 HP compressor installation at a proposed new 
    compressor station (Station 105) in Coosa County, Alabama.
        (4) Modifications to existing compressor equipment at Transco's 
    Station 110 in Randolph County, Alabama to eliminate or modify 
    current air permit restrictions, thereby allowing increased annual 
    operating hours and resulting in an uprate of 2,400 HP.
        (5) A 15,000 HP compressor installation at a proposed new 
    compressor station (Station 125) in Walton County, Georgia.
        (6) Modifications to existing compressor equipment at Transco's 
    Station 130 in Madison County, Georgia to eliminate or modify 
    current air permit restrictions, thereby allowing increased annual 
    operating hours and resulting in an uprate of 2,400 HP.
        (7) Modifications to existing compressor equipment at Transco's 
    Station 140 in Spartanburg County, South Carolina to eliminate or 
    modify current air permit restrictions, thereby allowing increased 
    annual operating hours and resulting in an uprate of 2,400 HP.
        (8) 14.92 miles of 42-inch Mainline ``D'' pipeline loop between 
    Stations 140 and 145, beginning at milepost 1222.66 and ending at 
    milepost 1237.58 in Cherokee County, South Carolina.
    
        Transco estimates that the project will cost $84,995,849, which 
    will be financed initially through short-term loans and funds on hand, 
    with permanent financing to be undertaken at a later date.
        Transco proposes to charge a monthly reservation rate of $13.20 per 
    Mcf for firm transportation services from Station 65 to shipper 
    delivery points and $10.20 per Mcf for transportation from Station 85 
    to shipper delivery points. Transco indicates that SunBelt Expansion 
    Project shippers will also be charged the electric power unit rate, 
    fuel retention factor, ACA and GRI and any other applicable charges 
    under Rate Schedule FT. It is noted that the electric power unit rate 
    and fuel retention will vary depending on the location of each 
    shipper's receipt and delivery points.
        Transco states that it has executed precedent agreements with ten 
    shippers which assure that all of the incremental firm capacity will be 
    subscribed on a firm basis for 20-year initial terms.
        Any person desiring to be heard or to make any protest with 
    reference to said application should on or before November 3, 1995, 
    file with the Federal Energy Regulatory Commission, Washington, DC 
    20426, a motion to intervene or a protest in accordance with the 
    requirements of the Commission's Rules of Practice and Procedure (18 
    CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act 
    (18 CFR 157.10). All protests filed with the Commission will be 
    considered by it in determining the appropriate action to be taken but 
    will not serve to make the protestants parties to the proceeding. Any 
    person wishing to become a party to the proceeding or to participate as 
    a party in any hearing therein must file a motion to intervene in 
    accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this application if no motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate is required by the public 
    convenience and necessity. If a motion for leave to intervene is timely 
    filed, or if the Commission on its own motion believes that a formal 
    hearing is required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for Transco to appear or be represented at the 
    hearing.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-25905 Filed 10-18-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
10/19/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-25905
Pages:
54073-54074 (2 pages)
Docket Numbers:
Docket No. CP96-16-000
PDF File:
95-25905.pdf