98-27899. Bangor Hydro-Electric Company; Notice Establishing Procedures for Relicensing and a Deadline for Submission of Final Amendments  

  • [Federal Register Volume 63, Number 201 (Monday, October 19, 1998)]
    [Notices]
    [Pages 55858-55859]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-27899]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Project No. 2721-013]
    
    
    Bangor Hydro-Electric Company; Notice Establishing Procedures for 
    Relicensing and a Deadline for Submission of Final Amendments
    
    October 13, 1998.
        The license for the Howland Hydro Project, FERC No. 2721, located 
    on the Piscataquis River in Penobscot County, near Howland, Maine, will 
    expire on September 30, 2000. On September 28, 1998, an application for 
    new major license was filed. The following is an approximate schedule 
    and procedures that will be followed in processing the application:
    
    [[Page 55859]]
    
    
    
    ------------------------------------------------------------------------
                   Date                                Action
    ------------------------------------------------------------------------
    January 30, 1999..................  Commission notifies applicant that
                                         its application has been accepted
                                         and specifies the need for
                                         additional information and due
                                         date.
    January 30, 1999..................  Commission issues public notice of
                                         the accepted application
                                         establishing dates for filing
                                         motions to intervene and protest.
    March 31, 1999....................  Commission's deadline for applicant
                                         for filing a final amendment, if
                                         any to its application.
    December 31, 1999.................  Commission notifies all parties and
                                         agencies that the application is
                                         ready for environmental analysis.
    ------------------------------------------------------------------------
    
        Upon receipt of all additional information and the information 
    filed in response to the public notice of the acceptance of the 
    application, the Commission will evaluate the application in accordance 
    with applicable statutory requirements and take appropriate action on 
    the application.
        Any questions concerning this notice should be directed to Ed Lee 
    at (202) 219-2809.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-27899 Filed 10-16-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
10/19/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-27899
Pages:
55858-55859 (2 pages)
Docket Numbers:
Project No. 2721-013
PDF File:
98-27899.pdf