99-27209. Arizona Public Service Company; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing  

  • [Federal Register Volume 64, Number 201 (Tuesday, October 19, 1999)]
    [Notices]
    [Pages 56369-56372]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-27209]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. STN 50-528]
    
    
    Arizona Public Service Company; Notice of Consideration of 
    Issuance of Amendment to Facility Operating License, Proposed No 
    Significant Hazards Consideration Determination, and Opportunity for a 
    Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License No. 
    NPF-41 issued to Arizona Public Service Company for operation of the 
    Palo Verde Nuclear Generating Station Unit 1 located in Maricopa 
    County, Arizona.
        The proposed amendment would revise Technical Specification (TS) 
    Section 3.8.4, ``DC Sources--Operating,'' to waive, on a one-time 
    basis, the requirement to perform Surveillance Requirement (SR) 3.8.4.8 
    for Unit 1 channels A, B, and C.
        Battery replacement in Unit 1 was scheduled to be completed during 
    the current refueling outage (1R08, Fall 1999). Because of problems 
    experienced by the vendor of the low specific gravity rectangular cell 
    batteries, four acceptable batteries are not available and the planned 
    battery replacement will not be completed as planned. Unit 1 will, 
    therefore, need to operate for one more cycle with the high specific 
    gravity round cell batteries.
        Because the high specific gravity round cell batteries will remain 
    in Unit 1 for an additional cycle, the licensee is required to perform 
    a performance discharge test or a modified performance discharge test 
    in accordance with TS SR 3.8.4.8. SR 3.8.4.8 requires that a 
    performance discharge test be performed to verify battery capacity on a 
    60-month frequency. The specified frequency for this SR, including the 
    additional time allowed by SR 3.0.2 (1.25 times the interval specified 
    in the frequency), for
    
    [[Page 56370]]
    
    three of the Unit 1 batteries (channels A, B, and C) will be exceeded 
    starting in December 1999. The channel D performance discharge test is 
    not due until the next Unit 1 refueling outage (1R09, Spring 2001).
        The licensee states that this condition could not be avoided since 
    Palo Verde had planned to replace the batteries during the current Unit 
    1 refueling outage and the battery vendor was not able to provide four 
    qualified batteries in time for the outage. As late as September 10, 
    1999, the vendor was still confident that it could provide the 
    replacement batteries for Unit 1. Only two of the four replacement 
    batteries have been received on site.
        Before issuance of the proposed license amendment, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under 
    exigent circumstances, the NRC staff must determine that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendment would not (1) 
    involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
        Standard 1--Does the proposed change involve a significant 
    increase in the probability or consequences of an accident 
    previously evaluated?
        No. The proposed change does not involve a significant increase 
    in the probability or consequences of an accident previously 
    evaluated.
        The DC power sources are required to ensure that sufficient 
    power is available to supply safety-related equipment required for 
    safe plant shutdown and the mitigation and control of accident 
    conditions. Since the batteries are not accident initiators and are 
    intended to mitigate the consequences of an accident, the delay of 
    the performance discharge test does not involve a significant 
    increase in the probability of an accident previously evaluated.
        The purpose of SR 3.8.4.8 is to determine overall battery 
    degradation due to age and usage. This information is then used to 
    determine the expected service life of the battery and when the 
    battery needs to be replaced. The last performance discharge test of 
    the batteries showed that the Unit 1 batteries were capable of 
    supplying over 100 percent of their rated capacity. The highest 
    design basis load demand for these batteries is less than 50 percent 
    of the actual rated capacity of the batteries. There is over 100 
    percent margin for these batteries. Therefore, the batteries 
    currently have a high capacity and a large margin above the needed 
    capacity.
        Since the battery capacity has remained well over 100 percent 
    for two performance discharge tests for channels A, B, and C and for 
    a third performance discharge test for channel D, and the batteries 
    have been installed for less than eight years, deferring the 
    performance discharge test for 18 months will not result in 
    overestimating the expected service life of the batteries.
        Since the batteries will be replaced during the next (ninth) 
    refueling outage the remaining installed life of these batteries is 
    18 months. To demonstrate design basis capability and operability 
    for this period, the service test in SR 3.8.4.7, in addition to the 
    other surveillance tests required by Technical Specification 3.8.4 
    and Technical Specification 3.8.6, ``Battery Cell Parameters,'' will 
    be performed in lieu of the performance discharge test.
        The proposed change does not result in any hardware changes or 
    changes to plant operating practices, nor does it affect plant 
    operation. Therefore, since the batteries have high capacity and 
    significant margin and will perform their design function as 
    intended, this change does not involve a significant increase in the 
    consequences of an accident previously evaluated.
        Standard 2--Does the proposed change create the possibility of a 
    new or different kind of accident from any accident previously 
    evaluated?
        No. The proposed change does not create the possibility of a new 
    or different kind of accident from any accident previously 
    evaluated.
        The DC power sources are required to ensure that sufficient 
    power is available to supply safety-related equipment required for 
    safe plant shutdown and the mitigation and control of accident 
    conditions. The purpose of SR 3.8.4.8 is to determine overall 
    battery degradation due to age and usage. This information is then 
    used to determine the expected service life of the battery and when 
    the battery needs to be replaced. The last performance discharge 
    test of the batteries showed that the Unit 1 batteries were capable 
    of supplying over 100 percent of their rated capacity. The highest 
    design basis load demand for these batteries is less than 50 percent 
    of the actual rated capacity of the batteries. There is over 100 
    percent margin for these batteries. Therefore, the batteries 
    currently have a high capacity and a large margin above the needed 
    capacity.
        Since the battery capacity has remained well over 100 percent 
    for two performance discharge tests for channels A, B, and C and for 
    a third performance discharge test for channel D, and the batteries 
    have been installed for less than eight years, deferring the 
    performance discharge test for 18 months will not result in 
    overestimating the expected service life of the batteries.
        Since the batteries will be replaced during the next (ninth) 
    refueling outage the remaining installed life of these batteries is 
    18 months. To demonstrate design basis capability and operability 
    for this period, the service test in SR 3.8.4.7, in addition to the 
    other surveillance tests required by Technical Specification 3.8.4 
    and Technical Specification 3.8.6, ``Battery Cell Parameters,'' will 
    be performed in lieu of the performance discharge test.
        The proposed change does not change the plant design or 
    configuration (no new or different type of equipment will be 
    installed), or change the method of operation of the plant. The 
    batteries have high capacity and significant margin and will perform 
    their design function as intended. Therefore, this change does not 
    create the possibility of a new or different kind of accident from 
    any previously evaluated.
        Standard 3--Does the proposed change involve a significant 
    reduction in a margin of safety?
        No. The proposed change does not involve a significant reduction 
    in a margin of safety.
        The proposed amendment would waive, on a one time basis, the 
    requirement to perform SR 3.8.4.8 for Unit 1 channels A, B, and C. 
    The surveillance requirement would be waived until the next 
    refueling outage for Unit 1 (1R09 Spring 2001). The purpose of the 
    battery performance test required by this surveillance requirement 
    is to determine overall battery degradation due to age and usage. 
    This information is then used to determine the expected service life 
    of the battery and when the battery needs to be replaced. The last 
    performance discharge test of the batteries showed that the Unit 1 
    batteries were capable of supplying over 100 percent of their 
    capacity. The highest design basis load demand for these batteries 
    is less than 50 percent of the actual rated capacity of the 
    batteries. There is over 100 percent margin for these batteries. 
    Therefore, the batteries currently have a high capacity and a large 
    margin above the needed capacity.
        Since the battery capacity has remained well over 100 percent 
    for two performance discharge tests for channels A, B, and C and for 
    a third performance discharge test for channel D, and the batteries 
    have been installed for less than eight years, deferring the 
    performance discharge test for 18 months will not result in 
    overestimating the expected service life of the batteries.
        Since the batteries will be replaced during the next (ninth) 
    refueling outage the remaining installed life of these batteries is 
    18 months. To demonstrate design basis capability and operability 
    for this period, the service test in SR 3.8.4.7, in addition to the 
    other surveillance tests required by Technical Specification 3.8.4 
    and Technical Specification 3.8.6, ``Battery Cell Parameters,'' will 
    be performed in lieu of the performance discharge test.
        The batteries have demonstrated that they have a high capacity, 
    they have been installed for only a short duration of their expected 
    service life, they have a large margin above the needed capacity, 
    and will perform their design function as intended. Therefore, this 
    proposed change does not involve a significant reduction in a margin 
    of safety.
    
    
    [[Page 56371]]
    
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three standards of 10 CFR 50.92(c) are 
    satisfied. Therefore, the NRC staff proposes to determine that the 
    amendment request involves no significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within 14 days after the date of 
    publication of this notice will be considered in making any final 
    determination.
        Normally, the Commission will not issue the amendment until the 
    expiration of the 14-day notice period. However, should circumstances 
    change during the notice period, such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendment before the expiration of 
    the 14-day notice period, provided that its final determination is that 
    the amendment involves no significant hazards consideration. The final 
    determination will consider all public and State comments received. 
    Should the Commission take this action, it will publish in the Federal 
    Register a notice of issuance. The Commission expects that the need to 
    take this action will occur very infrequently.
        Written comments may be submitted by mail to the Chief, Rules and 
    Directives Branch, Division of Administrative Services, Office of 
    Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555-0001, and should cite the publication date and page number of 
    this Federal Register notice. Written comments may also be delivered to 
    Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
    Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Copies of 
    written comments received may be examined at the NRC Public Document 
    Room, the Gelman Building, 2120 L Street, NW., Washington, DC.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
        By November 18, 1999, the licensee may file a request for a hearing 
    with respect to issuance of the amendment to the subject facility 
    operating license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene. Requests for a hearing and a petition for leave to intervene 
    shall be filed in accordance with the Commission's ``Rules of Practice 
    for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
    persons should consult a current copy of 10 CFR 2.714 which is 
    available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the Phoenix Public Library, 1221 N. Central 
    Avenue, Phoenix, Arizona 85004. If a request for a hearing or petition 
    for leave to intervene is filed by the above date, the Commission or an 
    Atomic Safety and Licensing Board, designated by the Commission or by 
    the Chairman of the Atomic Safety and Licensing Board Panel, will rule 
    on the request and/or petition; and the Secretary or the designated 
    Atomic Safety and Licensing Board will issue a notice of hearing or an 
    appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) The nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue of law or fact. Contentions shall be limited to matters within 
    the scope of the amendment under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If the amendment is issued before the expiration of the 30-day 
    hearing period, the Commission will make a final determination on the 
    issue of no significant hazards consideration. If a hearing is 
    requested, the final determination will serve to decide when the 
    hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendment and make it immediately effective, notwithstanding the 
    request for a hearing. Any hearing held would take place after issuance 
    of the amendment.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendment.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by close of business on the above date. A copy of the petition should 
    also be sent to the Office of the General Counsel, U.S. Nuclear 
    Regulatory Commission, Washington, DC 20555-0001, and to Nancy C. 
    Loftin, Esq., Corporate Secretary and Counsel, Arizona Public Service 
    Company, P.O. Box 53999, Mail Station 9068, Phoenix, Arizona 85072-
    3999, attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests
    
    [[Page 56372]]
    
    for hearing will not be entertained absent a determination by the 
    Commission, the presiding officer or the presiding Atomic Safety and 
    Licensing Board that the petition and/or request should be granted 
    based upon a balancing of the factors specified in 10 CFR 
    2.714(a)(1)(i)-(v) and 2.714(d).
        For further details with respect to this action, see the 
    application for amendment dated October 8, 1999, which is available for 
    public inspection at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room, located at the Phoenix Public Library, 1221 N. Central 
    Avenue, Phoenix, Arizona 85004.
    
        Dated at Rockville, Maryland, this 13th day of October, 1999.
    
        For the Nuclear Regulatory Commission.
    Nageswaran Kalyanam,
    Project Manager, Section 2, Project Directorate IV & Decommissioning, 
    Division of Licensing Project Management, Office of Nuclear Reactor 
    Regulation.
    [FR Doc. 99-27209 Filed 10-18-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
10/19/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-27209
Pages:
56369-56372 (4 pages)
Docket Numbers:
Docket No. STN 50-528
PDF File:
99-27209.pdf