95-24376. Northern Natural Gas Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 60, Number 190 (Monday, October 2, 1995)]
    [Notices]
    [Pages 51469-51470]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-24376]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP95-761-000]
    
    
    Northern Natural Gas Company; Notice of Request Under Blanket 
    Authorization
    
    September 26, 1995.
        Take notice that on September 18, 1995, Northern Natural Gas 
    Company (Northern), 111 South 103rd Street, Omaha, Nebraska 68124-1000, 
    filed in Docket No. CP95-761-000 a request pursuant to Sections 157.205 
    and 157.212 of the Commission's Regulations under the Natural Gas Act 
    (18 CFR 157.205, 157.212) for authorization to upgrade an existing 
    delivery point in Renville County, Minnesota, under Northern's blanket 
    certificate issued in Docket No. CP82-401-000 pursuant to Section 7 of 
    the Natural Gas Act, all as more fully set forth in the request that is 
    on file with the Commission and open to public inspection.
        Northern states that service will be provided to Great Plains 
    Natural Gas Company (Great Plains) under currently effective 
    interruptible throughput service agreement(s). The upgrade of Renville 
    #3 TBS is required for providing additional service for heating a new 
    egg processing farm. The incremental volumes to be delivered to Great 
    Plains are 190 MMBtu on a peak day and 33.902 MMBtu on an annual basis. 
    The Renville #33 TBS is located at Section 3, T115N, R36W, Renville 
    County, Minnesota and the estimated cost for upgrading is $1,000. 
    Northern states that the total volumes to be delivered to Great Plains 
    after the request do not exceed the total volumes authorized prior to 
    the request. Northern states that the proposed activity is not 
    prohibited by its existing tariff and that it has sufficient capacity 
    to accommodate the changes proposed herein without detriment or 
    disadvantage to its other customers.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    
    [[Page 51470]]
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-24376 Filed 9-29-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
10/02/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-24376
Pages:
51469-51470 (2 pages)
Docket Numbers:
Docket No. CP95-761-000
PDF File:
95-24376.pdf