DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers
Intent To Prepared a Dredge Material Management Plan Programmatic
Environmental Impact Statement (PEIS) for Los Angeles Area Harbors and
Marinas
AGENCY: U.S. Army Corps of Engineers (Corps), Los Angeles District,
DOD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: The Corps, Los Angeles District, has maintenance authorities
for the following marinas and harbors in Los Angeles County: Marina del
Rey, Redondo, Los Angeles and Long Beach. Recently, the Corps has
conducted dredge efforts on a biennial basis at the Marina del Rey
harbor and the Los Angeles River mouth due to unanticipated and
exceptionally high flows associated with extreme storm activity. High
runoff in the watershed has caused severe sedimentation problems in the
downstream portions of the rivers, especially in the approach channels
to the ocean. With high sediment loads settling in the approach
channels, the Corps has been required to dredge the channels under
Emergency Authorities for navigation safety purposes. To expedite the
process, the Corps has dredged only clean materials suitable for
unconfined ocean disposal by conventional methods. Other sediments
remained in situ. Efforts have been hampered by the inability to find
disposal sites for materials not suitable for unconfined ocean
disposal. As recent investigations have detected more and more harbors
and marinas containing sediments questionable for unconfined ocean
disposal, the Corps is proactively exploring use of unconventional
dredge and disposal techniques for these types of materials. The Marina
del Rey harbor and the Los Angeles River mouth contain sediments
questionable for unconfined ocean disposal, the DMMP is being developed
to specifically permit removal and disposal of sediments not suitable
for conventional techniques in an environmentally acceptable manner and
place. It is estimated that 515,000 cubic meters (M \3\) of sediments
need to be removed from the harbor entrance at Marina del Rey and
700,000 M \3\ at the mouth of the Los Angeles River to continue to
provide safe navigation opportunities. Based on historic and recent
testing, it is expected that 230,000 M \3\ at Marina del Rey and
250,000 M \3\ at Los Angeles River are not suitable for unconfined
ocean disposal.
FOR FURTHER INFORMATION CONTACT: For further information contact Mr.
Russell L. Kaiser at 213-452-3846 or U.S. Army Corps of Engineers, P.O.
Box 532711, Los Angeles, California, 90053-2325.
SUPPLEMENTARY INFORMATION: The Corps along with several other Federal,
state and local agencies and interested parties representing different
environmental groups in the Los Angeles region have been meeting
regularly over the last several years to discuss and develop a strategy
for the placement of contaminated sediments in an environmentally
acceptable manner and place. This consortium of agencies and interested
parties, hereafter known as the Contaminated Sediment Task Force
(CSTF), has formulated preliminary concepts for unconventional disposal
techniques.
The Corps has held several public scoping meetings in association
with this project. Formal meetings have been conducted on November 19,
1997, in Marina del Rey, California and on November 20, 1997, in Long
Beach, California to identify special interests and environmental
concerns. No major concerns nor issues were raised at these meetings.
As the CSTF meetings are open to the public, all interested parties and
agencies are welcome to attend and encouraged to participate in them.
Individuals and agencies may offer information or data relevant to the
proposed study and/or request to be placed on the mailing list for
future announcements and/or the PEIS by mailing the information and/or
request to Mr. Russell L. Kaiser. The Draft PEIS will be available for
review and comment in November 1998.
Alternatives
A full array of preliminary alternatives, using both conventional
and non-conventional disposal methods, have been developed to meet
project needs. Conventional methods include: beach nourishment and
unconfined ocean disposal. Non-conventional methods may include:
subaqueous capping, confined disposal, upland disposal, physical
separation, sediment mixing, concrete solidification/stabilization and
structural reconfiguration. Project criteria have indicated that the
following alternatives may be viable: (1) Subaqueous capping at North
Energy Island borrow pit; (2) Confined aquatic disposal on harbor side
of Long Beach Breakwater; (3) Port of Long Beach landfill at Pier S
with dredged material converted to structural grade by concrete
solidification/stabilization or by sediment mixing; (4) Upland disposal
at the ECDC Class II site in Carbon County, Utah, and/or (5) Treatment
of dredged material by physical separation. A co-equal analysis will be
conducted for the no action and each viable project alternative in the
PEIS pursuant with the National Environmental Policy Act of 1969, 42
U.S.C. 4321, as amended. Project area maps will be available upon
request.
Dated: September 18, 1998.
Robert L. Davis,
Colonel, Corps of Engineers, District Engineers.
[FR Doc. 98-26498 Filed 10-1-98; 8:45 am]
BILLING CODE 3710-KF-M