98-28330. Texas Gas Transmission Corporation; Notice of Request Under Blanket Authorization
[Federal Register Volume 63, Number 204 (Thursday, October 22, 1998)]
[Notices]
[Pages 56632-56633]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-28330]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-809-000]
Texas Gas Transmission Corporation; Notice of Request Under
Blanket Authorization
October 16, 1998.
Take notice that on September 30, 1998, Texas Gas Transmission
Corporation (Texas Gas), Post Office Box 20008, Owensboro, Kentucky
42304, filed a request with the Commission in Docket No. CP98-809-000,
pursuant to Sections 157.205 and 157.216(b) of the Commission's
Regulations under the Natural Gas Act (NGA) for authorization to
abandon by removal the Stanolind Oil & Gas Corporation Meter Station
(meter station) located on Texas Gas' Eunice-Woodlawn Line in Jefferson
Davis Parish, Louisiana authorized in blanket certificate issued in
Docket No. CP92-407-000, all as more fully set forth in the request on
file with the Commission and open to public inspection.
Texas Gas reports that on April 24, 1997, Texas Gas received
approval in Docket No. CP98-288-000 to abandon the transportation
service for ANR authorized in Docket No. G-10295. With the abandonment
of the transportation service, the meter station is no longer needed.
The meter station was constructed by Texas Gas to receive gas for the
account of American Louisiana Pine Line Company, now ANR Pipeline
Company (ANR), which was being produced from Stanolind's acreage in the
South Elton and transport the gas to points of interconnection between
the systems of Texas Gas and American Louisiana. Texas Gas further
reports that the facilities to be removed consist of a 4''-meter run,
measurement building and related equipment. Texas Gas has estimated the
cost of removal to be $500.
Any person or the Commission's staff may, within 45 days after the
Commission has issued this notice, filed pursuant to Rule 214 of the
Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or
notice of intervention and pursuant to Section 157.205 of the
Regulations under the NGA (18 CFR 157.205) a protest to the
[[Page 56633]]
request. If no protest is filed within the allowed time the proposed
activity shall be deemed to be authorized effective the day after the
time allowed for filing a protest. If a protest is filed and not
withdrawn within 30 days after the time allowed for filing a protest,
the instant request shall be treated as an application for
authorization pursuant to Section 7 of the NGA.
David P. Boergers,
Secretary.
[FR Doc. 98-28330 Filed 10-21-98; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 10/22/1998
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 98-28330
- Pages:
- 56632-56633 (2 pages)
- Docket Numbers:
- Docket No. CP98-809-000
- PDF File:
-
98-28330.pdf