98-28331. Northern Natural Gas Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 63, Number 204 (Thursday, October 22, 1998)]
[Notices]
[Page 56631]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-28331]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP99-11-000]
Northern Natural Gas Company; Notice of Request Under Blanket
Authorization
October 16, 1998.
Take notice that on October 9, 1998, Northern Natural Gas
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed
in Docket No. CP99-11-000, a request pursuant to Section 157.205 and
157.212 of the Commission's Regulations under the Natural Gas Act (18
CFR 157.205 and 157.212) for authorization to upgrade the Farley #1 TBS
existing delivery point and appurtenant facilities located in Dubuque
County, Iowa, to accommodate natural gas deliveries to UtiliCorp
United, Inc. (UCU) under Northern's blanket certificate issued in
Docket No. CP82-401-000, pursuant to 18 CFR Part 157, Subpart F of the
Natural Gas Act, all as more fully set forth in the request which is on
file with the Commission and open to public inspection.
Northern states that it requests authorization to upgrade the
existing delivery point to accommodate natural gas deliveries to UCU
under currently effective throughput service agreement(s). Northern
asserts that UCU has requested the proposed upgrade to provide
additional natural gas service to the Farley #1#1 TBS for redelivery to
a grain dryer. It is further stated that the estimated incremental
volumes proposed to be delivered to UCU at this delivery point is 171
MMBtu on a peak day and 19,276 MMBtu on an annual basis. Northern
states that the estimated cost to upgrade the existing delivery point
is $7,000. Northern further states that UCU would reimburse Northern
for the total cost to upgrade the existing delivery point.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 98-28331 Filed 10-21-98; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 10/22/1998
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 98-28331
- Pages:
- 56631-56631 (1 pages)
- Docket Numbers:
- Docket No. CP99-11-000
- PDF File:
-
98-28331.pdf