01-26302. Federal Acquisition Regulation; Small Entity Compliance Guide  

  • Start Preamble

    AGENCIES:

    Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Small Entity Compliance Guide.

    SUMMARY:

    This document is issued under the joint authority of the Secretary of Defense, the Administrator of General Services and the Administrator for the National Aeronautics and Space Administration. This Small Entity Compliance Guide has been prepared in accordance with Section 212 of the Small Business Regulatory Enforcement Fairness Act of 1996 (Public Law 104-121). It consists of a summary of rules appearing in Federal Acquisition Circular (FAC) 2001-01 which amend the FAR. An asterisk (*) next to a rule indicates that a regulatory flexibility analysis has been prepared in accordance with 5 U.S.C. 604. Interested parties may obtain further information regarding these rules by referring to FAC 2001-01 which precedes this document. These documents are also available via the Internet at http://www.arnet.gov/​far.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Laurie Duarte, FAR Secretariat, (202) 501-4225. For clarification of content, contact the analyst whose name appears in the table below.

    List of Rules in FAC 2001-01

    ItemSubjectFAR caseAnalyst
    I*Application of the Davis-Bacon Act to Construction Contracts With Options to Extend the Term of the Contract1997-613Nelson.
    IIAcquisition of Commercial Items2000-303Moss.
    IIIPrompt Payment Under Cost-Reimbursement Contracts for Services (Interim)2000-308Olson.
    IVVeterans’ Employment1998-614Nelson.
    V*Veterans Entrepreneurship and Small Business Development Act of 1999 (Interim)2000-302Cundiff.
    Start Printed Page 53501
    VIVery Small Business Pilot Program2001-001Cundiff

    Item I—Application of the Davis-Bacon Act to Construction Contracts With Options To Extend the Term of the Contract

    This final rule implements the Department of Labor's requirement to incorporate a current Davis-Bacon Act wage determination at the exercise of each option to extend the term of a contract for construction.

    Item II—Acquisition of Commercial Items

    This final rule amends the FAR to clarify the definition of “commercial item.” The revised language will help contracting officers make commerciality determinations. The rule also alerts contracting officers to be aware of customary commercial terms and conditions that may affect the contract price when pricing commercial items. The rule also clarifies that subpart 46.8, Contractor Liability for Loss of or Damage to Property of the Government, does not apply to acquisitions of commercial items. Contracting officers should use standard commercial practices instead of the policies in subpart 46.8. Finally, the rule amends the clause at 52.212-4, Limitation of liability, to conform it to standard commercial practice.

    Item III—Prompt Payment Under Cost-Reimbursement Contracts for Services

    This interim rule implements changes in the Office of Management and Budget's (OMB) Prompt Payment Act regulations at 5 CFR 1315 that implemented Section 1010 of the National Defense Authorization Act for Fiscal Year 2001. Those changes were published by OMB as an interim final rule and became effective on December 15, 2000 (65 FR 78403) and were applicable to all covered contracts awarded on or after December 15, 2000. Section 1010 of the National Defense Authorization Act for Fiscal Year 2001 requires agencies to pay an interest penalty, in accordance with regulations issued, whenever an interim payment under a cost-reimbursement contract for services is paid more than 30 days after the agency receives a proper invoice from a contractor. The Act does not permit payment of late payment penalty interest for any period prior to December 15, 2000.

    This FAR amendment eliminates the prior policy and contract clause prohibitions on payment of late payment penalty interest for late interim finance payments under cost-reimbursement contracts for services. It adds new policy and contract clause coverage to provide for those penalty payments.

    Item IV—Veterans’ Employment

    This final rule amends the FAR to implement statutory and regulatory changes relating to veterans’ employment opportunities and reporting. Most significantly for contracting officers, the rule amends the FAR to prohibit contracting officers from obligating or expending appropriated funds to enter into a contract with a contractor that has not met its veterans’ employment reporting requirements (VETS—100 Report). This prohibition does not apply to contracts for commercial items or contracts valued at or below the simplified acquisition threshold. The rule adds a new solicitation provision that requires each offeror to represent, by submission of its offer, that it is in compliance with the VETS—100 reporting requirements. The contracting officer may verify compliance by checking with the Department of Labor.

    Item V—Veterans Entrepreneurship and Small Business Development Act of 1999

    This interim rule amends the FAR to implement section 803 of the Small Business Reauthorization Act of 2000, part of the Consolidated Appropriations Act, 2001 (Pub. L. 106-554) that was enacted on December 21, 2000.

    This rule requires a contractor that is required to submit a subcontracting plan to report as a separate subcontracting plan goal requirement, subcontracting activity pertaining to service-disabled veteran-owned small business concerns. The rule also changes the Standard Form (SF) 294, “Subcontracting Report for Individual Contracts,” and the SF 295, “Summary Subcontract Report,” to capture this category of information for the contracting officer.

    Item VI—Very Small Business Pilot Program

    This final rule amends FAR Subpart 19.9 to implement Section 503(c) of the Small Business Reauthorization Act of 2000 (part of Public Law 106-554). Section 503(c) extends, for three additional years, the Very Small Business Pilot Program until September 30, 2003. The purpose of the program is to improve access to Government contract opportunities for concerns that are substantially below SBA's size standards by reserving certain acquisitions for competition among such concerns.

    Start Signature

    Dated: October 12, 2001.

    Al Matera,

    Director, Acquisition Policy Division.

    End Signature End Further Info End Preamble

    [FR Doc. 01-26302 Filed 10-19-01; 8:45 am]

    BILLING CODE 6820-EP-P

Document Information

Published:
10/22/2001
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Small Entity Compliance Guide.
Document Number:
01-26302
Pages:
53500-53501 (2 pages)
Docket Numbers:
FAR Case 1997-613, FAR Case 2000-303, FAR Case 2000-308, FAR Case 1998-614, FAR Case 2000-302, FAR Case 2001-001
PDF File:
01-26302.pdf
CFR: (1)
48 CFR None