[Federal Register Volume 61, Number 206 (Wednesday, October 23, 1996)]
[Notices]
[Pages 54991-54992]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-27100]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP97-17-000]
ANR Pipeline Company; Notice of Request Under Blanket
Authorization
October 17, 1996.
Take notice that on October 8, 1996, ANR Pipeline Company (ANR),
500 Renaissance Center, Detroit, Michigan 48243, filed in Docket No.
CP97-17-000 a request pursuant to Sections 157.205 and 157.212 of the
Commission's Regulations under the Natural Gas Act (18 CFR 157.205 and
157.212) for authorization to construct and operate an interconnection
between ANR and Wisconsin Fuel & Light Company (WF&L), in Marathon
County, Wisconsin, to accommodate WF&L's continuing growth load. ANR
makes such request under its blanket certificate issued in Docket No.
CP82-480-000 pursuant to Section 7 of the Natural Gas Act, all as more
fully set forth in the request on file with the Commission and open to
public inspection.
ANR is proposing to modify its existing Callon tap which is located
on ANR's Wittenberg Lateral in Marathon County. ANR mentions that the
Callon tap was originally installed as part of the Wittenberg Lateral
in 1969, but that ANR never delivered gas at that tap. ANR states that
WF&L submitted a request to ANR, in which WF&L requested to tie into
the Callon tap in order to accommodate continuing load growth in WF&L's
Wausau distribution area. It is indicated that the Callon tap currently
consists of a 4-inch underground valve with a high head extension and a
blind flange. ANR states that it is proposing to modify the Callon tap
so that it would be above ground, making maintenance and repairs more
convenient. ANR further states that it proposes to add a flange and an
[[Page 54992]]
insulated flange, a reducer, two piping elbows, and approximately eight
feet of 2-inch piping at this interconnection, as part of the
modification.
ANR avers that approximately 240 Mcf of natural gas during a peak
day, will be delivered to this interconnection, and that the delivery
quantity will be within WF&L's certificated entitlements. It is
estimated that the proposed modification will cost approximately
$3,000.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 96-27100 Filed 10-22-96; 8:45 am]
BILLING CODE 6717-01-M