96-27100. ANR Pipeline Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 61, Number 206 (Wednesday, October 23, 1996)]
    [Notices]
    [Pages 54991-54992]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-27100]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP97-17-000]
    
    
    ANR Pipeline Company; Notice of Request Under Blanket 
    Authorization
    
    October 17, 1996.
        Take notice that on October 8, 1996, ANR Pipeline Company (ANR), 
    500 Renaissance Center, Detroit, Michigan 48243, filed in Docket No. 
    CP97-17-000 a request pursuant to Sections 157.205 and 157.212 of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205 and 
    157.212) for authorization to construct and operate an interconnection 
    between ANR and Wisconsin Fuel & Light Company (WF&L), in Marathon 
    County, Wisconsin, to accommodate WF&L's continuing growth load. ANR 
    makes such request under its blanket certificate issued in Docket No. 
    CP82-480-000 pursuant to Section 7 of the Natural Gas Act, all as more 
    fully set forth in the request on file with the Commission and open to 
    public inspection.
        ANR is proposing to modify its existing Callon tap which is located 
    on ANR's Wittenberg Lateral in Marathon County. ANR mentions that the 
    Callon tap was originally installed as part of the Wittenberg Lateral 
    in 1969, but that ANR never delivered gas at that tap. ANR states that 
    WF&L submitted a request to ANR, in which WF&L requested to tie into 
    the Callon tap in order to accommodate continuing load growth in WF&L's 
    Wausau distribution area. It is indicated that the Callon tap currently 
    consists of a 4-inch underground valve with a high head extension and a 
    blind flange. ANR states that it is proposing to modify the Callon tap 
    so that it would be above ground, making maintenance and repairs more 
    convenient. ANR further states that it proposes to add a flange and an
    
    [[Page 54992]]
    
    insulated flange, a reducer, two piping elbows, and approximately eight 
    feet of 2-inch piping at this interconnection, as part of the 
    modification.
        ANR avers that approximately 240 Mcf of natural gas during a peak 
    day, will be delivered to this interconnection, and that the delivery 
    quantity will be within WF&L's certificated entitlements. It is 
    estimated that the proposed modification will cost approximately 
    $3,000.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-27100 Filed 10-22-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
10/23/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-27100
Pages:
54991-54992 (2 pages)
Docket Numbers:
Docket No. CP97-17-000
PDF File:
96-27100.pdf