2024-22601. Takes of Marine Mammals Incidental to Specified Activities; Taking Marine Mammals Incidental to the Maryland Offshore Wind Project, Offshore of Maryland
Table 1—US Wind's Anticipated Construction Campaign Schedule
Campaigns Construction year Number of 11-m monopiles for WTGs Number 3-m pin piles for OSS jacket foundations 1 Number of 1.8-m pin piles for Met tower Onshore export cables Offshore substations MarWin 1 (2025) 21 4 (1 jacket) 0 4 1 Momentum 2 (2026) 55 8 (2 jackets) 3 0 2 Future Development 3 (2027) 38 4 (1 jacket) 0 0 1 1 Potential OSS foundations could also include monopile and suction bucket jacket foundations.