2024-24526. Applications for Permits to Site Interstate Electric Transmission Facilities  

  • Annual Changes Resulting From Order on Rehearing in Docket No. RM22-7-001

    Number of respondents Number of responses 83 per respondent Total number of responses Avg. burden hrs. & cost per response 84 Total annual burden hours & total annual cost
    (1) (2) (1) × (2) = (3) (4) (3) × (4) = 5
    Tribal Engagement Plan 1 1 1 27 hrs.; $2,700 27 hrs.; $2,700.

Document Information

Effective Date:
11/22/2024
Published:
10/23/2024
Department:
Federal Energy Regulatory Commission
Entry Type:
Rule
Document Number:
2024-24526
Dates:
This rule is effective November 22, 2024.
Pages:
84465-84472 (8 pages)
Docket Numbers:
Docket No. RM22-7-001, Order No. 1977-A
Topics:
Administrative practice and procedure, Electric power, Reporting and recordkeeping requirements
PDF File:
2024-24526.pdf
CFR: (2)
18 CFR 50
18 CFR 380