94-26537. Newberry Geothermal Pilot Project; Record of Decision  

  • [Federal Register Volume 59, Number 206 (Wednesday, October 26, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-26537]
    
    
    [[Page Unknown]]
    
    [Federal Register: October 26, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Bonneville Power Administration
    
     
    
    Newberry Geothermal Pilot Project; Record of Decision
    
    AGENCY: Bonneville Power Administration (BPA), DOE.
    
    ACTION: Notice of Record of Decision.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Bonneville Power Administration has issued a Record of 
    Decision (ROD) to purchase electrical power from the proposed Newberry 
    Geothermal Pilot Project (Newberry Project), to provide billing 
    credits\1\ to Eugene Water & Electric Board (EWEB), and to provide 
    wheeling services to EWEB for the transmission of this power to their 
    system. BPA has decided to acquire 20 average megawatts (aMW) of 
    electrical power from a privately-owned geothermal power plant on the 
    west flank of Newberry Volcano in Deschutes County, Oregon. The 
    Newberry Project will generate 30 aMW and will be developed, owned, and 
    operated by CE Newberry, Inc. of Portland, Oregon. In addition, BPA has 
    decided to grant billing credits to EWEB for 10 aMW of electrical power 
    and to provide wheeling services to EWEB for the transmission of this 
    power to their system. BPA expects the Newberry Project to be in 
    commercial operation by November 1997.
    ---------------------------------------------------------------------------
    
        \1\One method that BPA uses to acquire energy resources is 
    Billing Credits. With this innovative mechanism, authorized by the 
    Northwest Power Act, BPA provides a credit to an eligible customer 
    for load reduction actions and energy resource developments. A 
    complete description of the Billing Credits Policy is presented in 
    an Environmental Assessment (DOE/EA-0180, June 1982), which has been 
    made available to the public.
    ---------------------------------------------------------------------------
    
        BPA has statutory responsibilities to supply electrical power to 
    its utility, industrial and other customers in the Pacific Northwest. 
    The Newberry Project will be used to meet the electrical power supply 
    obligations of these customers. The Newberry Project will also 
    demonstrate the availability of geothermal power to meet power supply 
    needs in the Pacific Northwest and is expected to be the first 
    commercial geothermal plant in the region
    
    ADDRESSES: Copies of the Newberry Project FEIS, Executive Summary, 
    Appendices, and Comment Report, (DOE EIS-0207, June 1994), and the 
    USFS/BLM ROD are available from the Fort Rock Ranger District, 1230 NE 
    Third Street, Suite A262, Bend, Oregon 97701; telephone (503) 383-4703. 
    Copies of this ROD, the MAP, and the Resource Programs EIS are 
    available from BPA's Public Involvement Office, PO Box 12999, Portland, 
    Oregon 97212 or by calling BPA's nationwide toll-free document request 
    line, 1-800-622-4520.
    
    FOR FURTHER INFORMATION CONTACT: Ms. Katherine S. Pierce, NEPA 
    Compliance Officer for the Office of Energy Resources--RAE, Bonneville 
    Power Administration, PO Box 3621, Portland, Oregon 97208, telephone 
    (503) 230-3962.
        Public availability: This ROD will be distributed to all persons 
    and agencies known to be interested in or affected by the proposed 
    action or alternative.
    
    SUPPLEMENTARY INFORMATION:
    
    Purpose and Background
    
        The Bonneville Power Administration (BPA) is a self-financing 
    Federal power marketing agency with statutory responsibility to supply 
    electricity to utility, industrial, and other customers in the Pacific 
    Northwest. The Pacific Northwest Electric Power Planning and 
    Conservation Act (Northwest Power Act) requires BPA to meet its 
    customers' electric power requirements. 16 U.S.C. 839d(a)(2). As part 
    of its mission, BPA is responsible for acquiring conservation and 
    additional generation resources sufficient to meet the future needs of 
    its utility customers. Section 6(d) of the Northwest Power Act 
    authorizes BPA to acquire experimental, developmental, demonstration, 
    or pilot projects of a type with potential for providing cost- 
    effective service to the region. 16 U.S.C. 839d(d).
        The Pacific Northwest Electric Power and Conservation Planning 
    Council (Council), in its 1986 Power Plan, noted that ``* * * 
    approximately 4,400 megawatts of cost-effective electrical energy could 
    be obtained through the development of regional geothermal resource 
    areas.'' However, because the resource had not been confirmed, it was 
    not included in the portfolio of the 1986 Plan. The Power Plan called 
    for methods of confirming this resource so that it would be available 
    when needed. Newberry Volcano, Oregon, was identified as one of the 
    most promising sites.
        The Newberry Project was selected under the BPA Geothermal Pilot 
    Project Program. The goal of the Program is to initiate development of 
    the Pacific Northwest's large, but essentially untapped, geothermal 
    resources, and to confirm the availability of this resource to meet the 
    energy needs of the region. The primary underlying objective of this 
    Program is to assure the supply of alternative sources of electrical 
    power to help meet growing regional power demands and needs.
        BPA's purposes for this action are to:
        (1) Meet contractual obligations to supply requested, cost-
    effective power to BPA customers, having considered potential 
    environmental impacts and mitigation measures in its decision;
        (2) Assure consistency with BPA's statutory responsibilities, 
    including the Pacific Northwest Electric Power Planning and 
    Conservation Act (Northwest Power Act), while taking into consideration 
    the Pacific Northwest Electric Power and Conservation Planning 
    Council's (Council) Conservation and Electric Power Plan (Power Plan) 
    and Fish and Wildlife Program; and
        (3) Test the availability of geothermal energy to provide a 
    reliable, economical, and environmentally acceptable alternative energy 
    source to help meet the region's power needs.
        To make these decisions, BPA cooperated on and adopted the Newberry 
    Geothermal Pilot Project Final Environmental Impact Statement (FEIS) 
    (DOE/EIS--0207, June 1994). The FEIS was tiered to the Resource 
    Programs Environmental Impact Statement (RPEIS-DOE/EIS-0162), which 
    considered the environmental tradeoffs among the resource types 
    available to meet BPA's needs.
        The FEIS evaluated the exploration, development, utilization, and 
    decommissioning phases of the Newberry Project as well as related 
    transmission, wheeling, and billing credit components. Alternative A is 
    the CEC/EWEB proposal, and Alternative B is the three Federal agencies' 
    modification of the proposal. In addition to identifying and analyzing 
    the environmental impacts of these two alternatives for the Newberry 
    Project, the FEIS also evaluated the No Action alternative. By 
    contract, the Newberry Project is required to meet all Federal, state, 
    and local requirements. The FEIS fulfills the requirements of the 
    National Environmental Policy Act (NEPA) and meets the needs of the 
    U.S. Forest Service (USFS) and the Bureau of Land Management (BLM), who 
    have documented their decisions in a separate, joint ROD. BPA has also 
    determined that this action is consistent with the Council's 1991 Power 
    Plan.
        Based on the information analyzed and disclosed in the FEIS and 
    associated documents, including the USFS/BLM ROD, BPA has determined 
    that the preferred alternative is Alternative B with the conditions and 
    mitigation and monitoring elements described in the USFS/BLM ROD. A 
    Mitigation Action Plan (MAP) developed from the FEIS analysis is 
    available. It requires implementation of the specific mitigation 
    requirements described in the FEIS and USFS/BLM ROD.
        BPA develops and publishes a biennial integrated least cost plan, 
    the Resource Program. In its Draft 1990 Resource Program, BPA said it 
    would be willing to participate in up to three geothermal pilot 
    projects. The purpose of these projects would be to initiate 
    development, confirm resources, and determine the ability to develop 
    three of the largest, most promising sites in the region. BPA agreed to 
    purchase--in joint ventures with regional utilities--up to 10 average 
    megawatts (aMW) from each of three projects. After receiving comments 
    from customers supporting the projects, and after the Council approved 
    this approach in its 1991 Power Plan, BPA published a solicitation that 
    resulted in seven proposals.
        The objectives of BPA's solicitation were to:
        (1) Meet contractual obligations to supply requested, cost-
    effective power to BPA customers, having considered potential 
    environmental impacts and mitigation measures in its decision;
        (2) Assure consistency with BPA's statutory responsibilities, 
    including the Northwest Power Act, while taking into consideration the 
    Council's Power Plan and Fish and Wildlife Program; and
        (3) Test the availability of geothermal energy to provide a 
    reliable, economical, and environmentally acceptable alternative energy 
    source to help meet the region's power needs. Three projects were 
    selected for contract negotiations on December 17, 1991. One of the 
    selected projects was a proposal by the California Energy Company (CEC) 
    and the Eugene Water & Electric Board (EWEB) to develop a 30-aMW 
    geothermal power plant and supporting facilities at Newberry Volcano, 
    Oregon.
        This Administrative Record of Decision sets out the reasons for 
    BPA's decision to execute a Power Purchase Agreement with CE Newberry, 
    Inc. (a subsidiary of CEC), through which BPA will purchase electrical 
    output from the proposed Newberry Project; to execute a Billing Credits 
    Generation Agreement with EWEB for a portion of the output from the 
    Newberry Project; and to provide wheeling services to EWEB for the 
    transmission of this electricity to their system.
    
    Legal Authority
    
        BPA is a self-financing power marketing agency with the United 
    States Department of Energy. BPA was established by the Bonneville 
    Project Act of 1937, 16 U.S.C. 832 et seq., to market wholesale power 
    from the Bonneville Dam and to construct power lines for the 
    transmission of this power to load centers in the Northwest. As other 
    Federal dams and transmission lines were built, the combined power and 
    transmission facilities have been integrated into a single power supply 
    system. Today, BPA markets power from 30 Federal hydroelectric projects 
    and two nuclear plants. BPA's transmission systems contain 14,797 
    circuit miles and provide about half of the region's power and three-
    fourths of its transmission capacity.
        BPA sells wholesale electric power to 126 utilities, 13 direct 
    service industrial customers (DSIs), and several government agencies. 
    BPA's primary marketing area is the Pacific Northwest region, comprised 
    of the states of Washington, Oregon, Idaho, that portion of Montana 
    lying west of the continental divide, and small portions of California, 
    Utah, Wyoming, and Nevada. 16 U.S.C. 837 and 839a(14). BPA also has 
    congressional authorization to sell or exchange wholesale power outside 
    the Pacific Northwest to the extent that such power is surplus to the 
    needs of the region. See 16 U.S.C. 837a.
        The Northwest Power Act directs BPA to serve the net power 
    requirements of any Pacific Northwest electric utility requesting 
    service, and to serve existing DSIs in the Pacific Northwest. 16 U.S.C. 
    839c(b)(1) and (d). Although BPA cannot own or construct electric 
    generating facilities, the Northwest Power Act permits BPA to acquire 
    rights to the output or capability of electric power resources. See 16 
    U.S.C. 839a(1) and 16 U.S.C. 839d. BPA may acquire a major resource (a 
    resource having a planned capability greater than 50 aMW and acquired 
    for more than 5 years, 16 U.S.C. 839a(12)) if it is consistent with the 
    Council's Power Plan. 16 U.S.C. 839d(c)(1)(D). If the resource is not 
    major, the Northwest Power Act instructs that the resource must be 
    consistent with the priorities required of the Plan. 16 U.S.C. 
    839d(b)(1) and (2).
        The Northwest Power Act authorizes BPA to acquire experimental, 
    developmental, demonstration, or pilot projects of a type with 
    potential for providing cost-effective service to the region. 16 U.S.C. 
    839d(d).
        BPA is also directed by the Northwest Power Act to grant billing 
    credits to a customer, if requested. 16 U.S.C. 839d(h). A billing 
    credit agreement is a contract between BPA and a customer, under which 
    BPA gives the customer a credit on its power bill for the difference 
    between BPA's wholesale power rate and the cost of power from a new 
    resource. The energy and capacity on which the credit is based is the 
    net amount the resource reduces the customer's load on BPA.
        Finally, BPA must satisfy all requirements of the National 
    Environmental Policy Act (NEPA). 42 U.S.C. 4321 et seq.
    
    Description of Need
    
        BPA load forecasts for the 1990 Resource Program showed that if the 
    medium load growth rate occurs, BPA must acquire 500 aMW by the year 
    2000 to meet customers' needs. Pacific Northwest Loads and Resources 
    Study, 1990. If utility and DSI loads grow at the medium-high rate, BPA 
    will need to acquire an additional 1,500 aMW by the year 2000. The 
    analysis in BPA's Resource Programs Environmental Impact Statement 
    (RPEIS) showed that geothermal is a reliable source of electric power 
    that can help meet energy needs in the Pacific Northwest. Final 
    Environmental Impact Statement: Resource Programs, 1993.
    
    1990 Resource Program
    
        BPA's 1990 Resource Program, issued July 1990, defined the actions 
    BPA would take to develop new resources to meet the power requirements 
    of its customers. The 1990 Resource Program focused on Fiscal Years 
    1992 and 1993, and included near-term actions to prepare for these 
    years. One of these actions was an offer to participate in geothermal 
    pilot projects aimed at confirming resources and determining 
    developability at three of the largest, most promising sites in the 
    Pacific Northwest.
        The 1990 Resource Program was developed through an extensive public 
    process that included a technical review panel. Many of the comments 
    received supported BPA's participation in geothermal pilot projects.
    
    Council Plan
    
        The Council's 1991 Power Plan noted that the geothermal 
    confirmation program in BPA's 1990 Resource Program was consistent with 
    the recommendations of the Council's Research, Development, and 
    Demonstration Advisory Committee. The Council's ``Recommended 
    Activities for Implementing the 1991 Power Plan'' included geothermal 
    demonstration projects initiated by BPA and the region's utilities. The 
    Council acknowledged that energy costs of a demonstration plant would 
    likely be higher than the marginal cost of other new resources, but the 
    premium would decline over time.
    
    Pilot Project Solicitation
    
    Request for Proposals
    
        BPA published a Request for Proposals (RFP) in Commerce Business 
    Daily on July 5, 1991. The RFP stated that BPA would be willing to 
    purchase up to 10 aMW of electric power from each of three projects 
    located in or near the BPA service area. Other conditions specified in 
    the RFP were:
         BPA would not finance projects but only purchase output
         Part of the output from each project had to be purchased 
    by another utility
         Overall project size could be greater than 10 aMW
         The proposed site had to be capable of supporting at least 
    100 MW
         The proposed site had to be suitable for operation as a 
    Federal geothermal unit
         The resource area had to be undeveloped for electric power 
    production
         The power contract had to include an option for BPA to 
    purchase subsequent output from the site
         Projects that would allow BPA to be a cooperating agency 
    in a BLM environmental process were strongly preferred
        These conditions were intended in part to limit the number of 
    proposals likely to be submitted. BPA could devote only a small amount 
    of staff time to evaluating proposals, and therefore tried to be quite 
    specific about what it wanted.
        Project sponsors were encouraged to submit project outlines or 
    summaries ahead of time before developing detailed proposals. This was 
    intended to prevent developers from spending money developing proposals 
    that would not meet program goals. Several developers met with program 
    staff or discussed the RFP on an informal basis before submitting 
    proposals. Letters of intent were due September 3, 1991, and proposals 
    were due October 1, 1991.
        Further information on BPA's Geothermal Pilot Project Program was 
    published prior to the solicitation in an article in a geothermal 
    industry trade journal, the Geothermal Resources Council BULLETIN 
    (December 1990). The article specified that the projects had to be in 
    three different resource areas, preferably involving different resource 
    developers. This article was provided to developers and others who 
    inquired about the RFP or the Geothermal Pilot Project Program.
    
    Proposals Received
    
        Seven proposals were received. Two of them clearly did not meet 
    program objectives, and a third was withdrawn by the sponsor during the 
    evaluation period.
        One of the projects not meeting program objectives was located in 
    Canada. Although projects located outside the United States were not 
    excluded in the RFP, a foreign project would not have met the program 
    goal of testing ability to overcome (U.S.) institutional barriers to 
    development. Furthermore, a Canadian project would not be subject to a 
    Bureau of Land Management (BLM) environmental process.
        A project was proposed at Raft River, Idaho, employing a power 
    cycle (the ``Kalina'' cycle) considered to be precommercial. Testing 
    new power plant technologies was not a goal of the program, and 
    previously developed sites were specifically excluded by the RFP. In 
    the early 1980s, Raft River was the site of a demonstration plant 
    developed by the U.S. Department of Energy. Sponsors of the Canadian 
    and Raft River projects were notified on October 30, 1991, that their 
    proposals had been eliminated from consideration.
        Four proposals received detailed evaluation. They were:
         A proposal by the California Energy Company (CEC) and the 
    Eugene Water & Electric Board (EWEB) for a 30-MW project at Newberry 
    Volcano, Oregon.
         A proposal by Vulcan Power Company (Vulcan) for a 30-MW 
    project at Newberry Volcano, Oregon.
         A proposal by Trans-Pacific Geothermal Corporation for a 
    30-MW project at Vale, Oregon.
         A proposal by Unocal Corporation for a 14-MW project at 
    Glass Mountain, California.
    
    Evaluation Process
    
        Proposals were evaluated by a project team composed of BPA staff. 
    Two sets of criteria were used. The first set, considered ``threshold'' 
    criteria, were the criteria stated in the RFP. Proposals were 
    eliminated from further consideration if they failed to meet any of 
    these criteria except the utility cost sharing requirement. Threshold 
    criteria included:
         Resource area considered capable of producing at least 100 
    MW. Since BPA required the sites to be undeveloped, there was no way to 
    know reservoir size with much certainty for the proposed sites. If 
    better data were not available, a resource estimate by the U.S. 
    Geological Survey or some other authoritative source was considered 
    sufficient basis for meeting this criterion.
         Suitable for operation as a unit. For the purpose of 
    conserving the resource, Federal geothermal leasing regulations allow 
    geothermal leaseholders to unite with each other in the development or 
    operation of any geothermal resource area. The leases affected by such 
    a cooperative arrangement are called a unit, and one of the 
    leaseholders is designated the unit operator. 43 CFR 3243. BPA wanted 
    to encourage coordinated development and avoid resource depletion 
    problems experienced elsewhere, and therefore included suitability for 
    unitization as a selection criteria. The lease block had to be unitized 
    or suitable for unit operation with the developer as operator. If the 
    area was not already unitized, the developer had to control a large and 
    reasonably contiguous lease block. Bureau of Land Management staff were 
    consulted regarding the suitability of proposed sites for unitization. 
    It should be noted that unitization in itself was not the objective of 
    this requirement. The objective was to encourage coordinated 
    development and conservation of the resource.
         Resource area not previously developed for electric power 
    production. A program goal was to develop new resources. If a power 
    project had already been developed at a site, the site did not meet 
    this criterion.
         Output contract proposed. BPA was willing to purchase 
    output only, not finance projects.
         Amenable to BPA receiving an option on future power from 
    the lease block. Since the cost of power from the first project was 
    expected to exceed the cost of other resources available to BPA, BPA 
    required a right of first refusal on up to 100 MW of additional 
    development at each site. Subsequent plants would benefit from 
    established infrastructure and lower risks, and the cost of power from 
    them would likely be more cost-effective.
         Cost sharing by another utility. Initiating development of 
    Northwest resources would have regionwide benefit. A cooperative effort 
    that included cost sharing seemed appropriate. It was recognized that 
    developers might have difficulty enlisting another utility before BPA 
    identified candidate projects, so failure to meet this criterion did 
    not disqualify a proposal during the evaluation period. Developers were 
    notified of this.
         Project allows BPA to be a cooperating agency in a BLM 
    environmental process. Staffing constraints would not allow BPA to be 
    the lead agency in the NEPA review. This criterion effectively limited 
    projects to Federal or Tribal land.
        The second set of criteria addressed the developers ability to 
    complete the project successfully. These are standard criteria used by 
    BPA in previous and subsequent solicitations, and included:
         Development team experience. How qualified was the project 
    team? Had they worked together on previous successful projects? A 
    salaried staff currently involved in project development or in 
    operating projects tended to be rated more highly than a listing of 
    consultants that would be hired for a proposed project. A salaried 
    staff was thought to indicate greater stability and commitment by the 
    developer to maintaining a long term presence in the geothermal 
    industry. There was also no guarantee that the listed consultants would 
    ever work on a proposed project.
         Ability to finance the project. Proven ability to finance 
    projects was desired. Was the developer experienced in obtaining 
    construction and long term project financing? Was the financing plan 
    realistic? Audited financial reports were requested from each 
    developer, and Dun and Bradstreet financial information reports were 
    obtained, if available.
         Project design. Had all important aspects of project 
    design been considered?
         Transmission availability. Were transmission capacity or 
    wheeling services available to deliver the energy to the BPA grid?
         Site control. Developers were asked to provide copies of 
    lease documents or other evidence of site control.
         Development schedule. Was the development schedule 
    realistic, well thought out, and logical? Did it include all important 
    activities?
         Environmental impacts/siting issues/permits and licenses. 
    To what extent had environmental and siting issues been identified? 
    What progress had been made in obtaining permits and licenses? BPA 
    staff consulted with land management agencies in the project areas, and 
    requested additional information from developers, when necessary.
         Cost of energy. This was used more as a starting point for 
    negotiations than as a selection criterion. BPA did not expect 
    developers to commit to a price until the terms and conditions of the 
    power contract were better known. Another reason for not selecting 
    based on price was to avoid being forced to select weak projects with 
    unrealistic power prices and to discourage ``low-ball'' bids.
        The evaluation process included a preliminary evaluation of the 
    proposals, followed by requests from the BPA project team for 
    additional information and a final evaluation.
        An issue of site control affecting the two proposed projects at 
    Newberry Volcano was examined. The ownership or ownership share of 
    three leases--OR 11987, OR 11992, and OR 45506--was a matter of dispute 
    between CEC and Vulcan. Since both developers considered it likely that 
    litigation would be necessary to resolve this dispute, and because 
    BPA's decision to purchase only output was thought to place all risk of 
    nonperformance on the developer, this was not a critical factor in the 
    selection process.
        The BPA team selected three projects for further consideration, and 
    the Administrator was briefed and a final decision made on December 17, 
    1991. The proposers were notified of BPA's decision by registered 
    letter between December 18 and December 20, 1991.
        The December 18 letter to Vulcan Power Company, which was not 
    selected, explained the reasons for BPA's decision. The CEC/EWEB 
    project was stronger in many respects and met BPA requirements for 
    utility cost sharing. Also, Vulcan lacked a history of successful 
    project development (the one project it attempted was unsuccessful). As 
    noted in the December 1990 Geothermal Resources Council BULLETIN 
    article mentioned above, only one project would be chosen at each site.
    
    Contract Negotiations
    
        The three projects selected for contract discussions were Glass 
    Mountain, Vale, and the CEC/EWEB Newberry Project. All three projects 
    were considered capable of meeting the goals of the program. Total 
    output from the three projects exceeded the 30 aMW BPA agreed to 
    purchase in the solicitation. But because the terms of the power 
    purchase contracts and the degree of participation by other utilities 
    were not known at this time (only one of the projects had identified a 
    utility partner), and in the interest of meeting program goals, BPA 
    agreed to consider purchasing more than 30 aMW. The Glass Mountain and 
    Vale Projects will, if appropriate, be the subject of separate Records 
    of Decision, and will not be discussed further in this document.
        Negotiations for the Newberry Project began in January 1992, and 
    were completed in December 1992. The negotiations resulted in three 
    proposed agreements:
         A Power Purchase Agreement between CEC and BPA;
         A Billing Credits Generation Agreement between EWEB and 
    BPA;
         A Power Purchase Agreement between CEC and EWEB.
        Under its Power Purchase Agreement with CEC, BPA would purchase 
    approximately 20 average megawatts of output from the project and 
    receive an option on an additional 67 megawatts, if available in the 
    future. Under its Power Purchase Agreement with CEC, EWEB would 
    purchase 10 average megawatts from the project and receive an option on 
    33 megawatts, if available. BPA would give EWEB billing credits for 10 
    average megawatts under a Billing Credits Generation Agreement. The 
    term of the agreements is 50 years from the commercial operation date 
    of the project.
        The price of energy will not exceed BPA's Alternative Cost, as 
    established in BPA's 1990 Billing Credit Solicitation. The Alternative 
    Cost is the estimated cost which BPA would incur as a result of 
    acquiring new resources, and is the upper limit on the amount of a 
    billing credit other than conservation.
    
    Memorandum of Understanding
    
        A Memorandum of Understanding (MOU) between CE Newberry, Inc. (a 
    subsidiary of the California Energy Company), EWEB, and BPA was 
    executed on December 17, 1992. The MOU acknowledged that the parties 
    had reached agreement on contract principles, and defined the roles of 
    the parties during the environmental review required by NEPA. The MOU 
    noted that BPA had not made a final decision to sign any power purchase 
    or other agreements, and that such power purchase obligation would not 
    arise, if at all, until the environmental impacts of the proposed 
    Newberry Project had been analyzed in accordance with NEPA.
    
    Environmental Considerations
    
    National Environmental Policy Act Background
    
        The National Environmental Policy Act (NEPA) is the basic national 
    charter for protection of the environment. It establishes policy, sets 
    goals, and provides means for carrying out its policy. NEPA requires 
    Federal agencies to make environmental information available to public 
    officials and citizens before decisions are made and before actions are 
    taken. Accurate scientific analysis, expert agency comments, and public 
    scrutiny are essential to implementing NEPA. The NEPA process is 
    intended to help public officials make decisions that are based on an 
    understanding of environmental consequences. NEPA mandates that Federal 
    agencies use all practical means to protect, restore, and enhance the 
    quality of the human environment and avoid or minimize any possible 
    adverse effects of their actions upon the quality of the human 
    environment.
    
    Newberry Geothermal Pilot Project Environmental Impact Statement
    
        On December 2, 1992, a Notice of Intent to Prepare an Environmental 
    Impact Statement (EIS) in accordance with NEPA was published by the 
    Environmental Protection Agency (EPA) in the Federal Register. This EIS 
    would analyze the environmental impacts of various alternatives related 
    to the development of the proposed Newberry Geothermal Pilot Project 
    (Newberry Project). The U.S. Forest Service (USFS) would be the Lead 
    Agency in this process; the Bureau of Land Management (BLM) and BPA 
    would be Cooperating Agencies.
        BPA adopted the Newberry Geothermal Pilot Project Final 
    Environmental Impact Statement (FEIS) (DOE/EIS-0207, June 1994). The 
    FEIS was tiered to the Resource Programs Environmental Impact Statement 
    (RPEIS-DOE/EIS-0162), which considered the environmental tradeoffs 
    among the resource types available to meet BPA's need.
        The FEIS evaluated the exploration, development, utilization, and 
    decommissioning phases of the Newberry Project as well as related 
    transmission, wheeling, and billing credit components. Alternative A is 
    the CEC/EWEB proposal, and Alternative B is the three Federal agencies' 
    modification of the proposal. In addition to identifying and analyzing 
    the environmental impacts of these two alternatives for the proposed 
    Newberry Project, the FEIS also evaluated the No Action alternative. 
    The Power Purchase and Billing Credits Agreements require that the 
    Newberry Project meet all Federal, state, and local requirements. The 
    FEIS fulfills the requirements of the National Environmental Policy Act 
    (NEPA) and meets the needs of the USFS and the BLM, who have documented 
    their decisions in a separate, joint Record of Decision (ROD). BPA has 
    also determined that this action is consistent with the Council's 1991 
    Power Plan.
        The following alternatives were considered in the EIS:
    
    Alternative A
    
        Alternative A is the proposal as submitted by CE Exploration 
    (CEE, a subsidiary of the California Energy Company). It includes 
    exploration, development, production, utilization, and 
    decommissioning of the geothermal resources on CEE's Federal 
    geothermal leases on the west flank of Newberry Volcano. Highlights 
    of this alternative, which is described in more detail in the FEIS, 
    include development of exploration/production well pads at 14 
    specific locations; construction and operation of one 33-MW (gross 
    output) power plant at a specific site; construction of associated 
    pipelines and access roads; construction and utilization of an H-
    frame, 115-kilovolt transmission line along the north side of Forest 
    Road 9735 to deliver power from the plant to an existing 
    transmission line; and mitigation and monitoring measures as 
    proposed by CEE. These would be permanent facilities with a contract 
    life of at least 50 years.
    
    Alternative B
    
        Alternative B is a modification of Alternative A developed by 
    the three Federal agencies that allows for greater siting 
    flexibility to minimize potential environmental impacts once the 
    geothermal resource is defined through exploration. It is similar to 
    Alternative A in plant design and size, size of the well field and 
    pads, and design of the facilities except for the transmission line. 
    It differs most in respect to the siting flexibility of well pads, 
    power plant, pipelines, and access roads and the mitigation and 
    monitoring measures to be included. It is described in detail in the 
    FEIS and highlights include development of exploration/production 
    well pads at 14 out of 20 possible locations; siting the individual 
    well pads within a 40-acre or less siting area; construction and 
    operation of one 33-MW power plant at one of three possible 
    locations; construction of associated pipelines and access roads; 
    construction and utilization of a single pole design 115-kilovolt 
    transmission line to the south of Forest Road 9735; and additional 
    mitigation and monitoring measures proposed by the agencies and 
    public. These facilities would also be permanent, with a contract 
    life of at least 50 years.
    
    Alternative C
    
        Alternative C is the No Action alternative. Under this 
    alternative, BPA would not acquire the energy output from the 
    proposed Newberry Project, thereby foregoing the opportunity to 
    supplement BPA's energy supply and to demonstrate the availability 
    of geothermal power to help meet the region's power needs. BPA would 
    also not provide billing credits to EWEB, with the same results as 
    above, and would not provide wheeling services to transmit the 
    energy. CEE would not go forth with the project without the power 
    purchase agreement, and EWEB would cease further involvement without 
    billing credits. This alternative is environmentally preferable, as 
    it would result in no impacts to the immediate environment.
    
    Other Actions
    
        Because the proposed action will not satisfy BPA's total need for 
    electrical energy, implementing the proposed action will not foreclose 
    consideration of other potential BPA resource actions. Resource types 
    potentially available to meet future load growth were comparatively 
    evaluated in the RPEIS and include:
         Conservation (commercial, residential, and industrial 
    sectors);
         Renewables (hydropower, wind, biomass, solar, and other 
    geothermal power);
         Cogeneration;
         Combustion turbines;
         Nuclear; and
         Coal.
    
    Decision Factors and Issues
    
        All of the project alternatives were evaluated against the purpose 
    and need for the Newberry Project, and only Alternatives A and B would 
    satisfy the need for electrical power. These alternatives would also 
    help BPA meet its contractual obligations and are consistent with BPA's 
    statutory responsibilities. Based on the information analyzed and 
    disclosed in the FEIS and associated documents, including the USFS/BLM 
    ROD, BPA has determined that the preferred alternative is Alternative B 
    with the conditions and mitigation and monitoring elements described in 
    the USFS/BLM ROD. The rationale for selecting Alternative B is 
    summarized in the USFS/BLM ROD by major issues that were of most 
    concern or apparent controversy. A Mitigation Action Plan (MAP) 
    developed from the FEIS analysis is available. It requires 
    implementation of the specific mitigation requirements described in the 
    FEIS and USFS/BLM ROD.
    
    Environmental Consultations, Review, and Permit Requirements
    
        BPA reviewed the status of all permits and licenses required for 
    the Newberry Project, consulted with CEE to satisfy area-wide, state, 
    and local environmental plans and programs, and developed a Mitigation 
    Action Plan MAP to assure that all environmental requirements are 
    addressed and that all practicable means to avoid, minimize, or 
    mitigate environmental impacts have been adopted. It implements the 
    specific mitigation requirements described in the FEIS and USFS/BLM 
    ROD. Development of the Newberry Project will be consistent with 
    environmental policies established by NEPA and the Oregon Energy 
    Facility Siting Council (EFSC), and will be consistent with the 
    requirements of the Council's Power Plan.
    
    Monitoring and Enforcement
    
        The MAP (Attachment 2) for the Newberry Project requires 
    implementation of mitigation measures necessary to reduce the 
    environmental impacts identified in the FEIS. The USFS, BLM, and BPA 
    all have responsibility for monitoring the progress of the Newberry 
    Project and ensuring that these measures are taken as appropriate. The 
    USFS and BLM responsibilities are detailed in the USFS/BLM ROD. 
    (Attachment 1). BPA will continue to monitor the Newberry Project 
    through its environmental oversight program. The Power Purchase and 
    Billing Credits Agreements stipulate the penalties for noncompliance 
    with these measures.
    
    Decision
    
        Upon consideration of the entire record, BPA has decided to execute 
    a Power Purchase Agreement with CE Newberry, Inc., execute a Billing 
    Credits Generation Agreement with EWEB, and provide wheeling services 
    for transmission of energy from the Newberry Project to EWEB's system.
    
        Issued in Portland, Oregon on September 16, 1994.
    John. S. Robertson,
    Deputy Administrator.
    [FR Doc. 94-26537 Filed 10-25-94; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Published:
10/26/1994
Department:
Bonneville Power Administration
Entry Type:
Uncategorized Document
Action:
Notice of Record of Decision.
Document Number:
94-26537
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: October 26, 1994