98-28575. Public Utility District No. 1 of Chelan County, Washington; Notice of Scoping Meetings and Project Facilities Tour Pursuant to the National Environmental Policy Act of 1969 for an Applicant Prepared Environmental Assessment  

  • [Federal Register Volume 63, Number 206 (Monday, October 26, 1998)]
    [Notices]
    [Page 57116]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-28575]
    
    
    
    [[Page 57116]]
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Project No. 637]
    
    
    Public Utility District No. 1 of Chelan County, Washington; 
    Notice of Scoping Meetings and Project Facilities Tour Pursuant to the 
    National Environmental Policy Act of 1969 for an Applicant Prepared 
    Environmental Assessment
    
    October 20, 1998.
        The Commission's regulations allow applicants the option of 
    preparing their own Environmental Assessment (EA) for hydropower 
    projects, and filing the EA with their application as part of an 
    alternative licensing procedure.\1\ On July 6, 1998 the Commission 
    approved the use of an alternative licensing procedure in the 
    preparation of a new license application for Public Utility District 
    No. 1 of Chelan County's (Chelan PUD), Lake Chelan Project, No. 637.
    ---------------------------------------------------------------------------
    
        \1\ 81 FERC para. 61,103 (1997).
    ---------------------------------------------------------------------------
    
        The alternative procedures include provisions for the distribution 
    of an initial information package, and for the cooperative scoping of 
    environmental issues and needed studies. On October 5, 1998, Chelan PUD 
    distributed their initial information package which included an initial 
    consultation document (ICD) and Scoping Document 1 (SD1).\2\ Three 
    public meetings will be held to discuss these documents.
    ---------------------------------------------------------------------------
    
        \2\ Copies of these documents can be obtained by calling Rosana 
    Sokolowski at 509-663-8121 or via the Chelan PUD web site located at 
    http://www.chelanpud.org/relicense.
    ---------------------------------------------------------------------------
    
    ICD Meeting and Project Tour
    
        Chelan PUD will hold a public meeting to discuss their ICD on 
    November 18, 1998. In this meeting, Chelan PUD will give an overview of 
    the existing project facilities and operation, discuss what is 
    currently known about environmental resources at the project, and 
    discuss how those resources are currently being managed. A project 
    facilities tour will also be conducted on the same day. The tour will 
    include stops at the dam, powerhouse, and the lower end of the project 
    bypassed reach.
        The times and locations of the ICD meeting and project facilities 
    tour are:
    
    Initial Information Meeting
    
    November 18, 1998, 10:00 am to 1:00 pm, Carvel Resort, 322 West Woodin 
    Avenue, Chelan, WA 98816, (509) 682-2582
    
    Project Facilities Tour
    
    November 18, 1998, 2:00 pm to 5:00 pm, Meet at north side of the 
    project dam (for more information call Gregg Carrington at (509) 663-
    8121)
    
    Scoping Meetings
    
        Chelan PUD will hold public scoping meetings on November 18 and 19, 
    1998, pursuant to the National Environmental Policy Act (NEPA) of 1969. 
    At the scoping meetings, Chelan PUD will: (1) summarize the 
    environmental issues tentatively identified for analysis in the EA; (2) 
    outline any resources they believe would not require a detailed 
    analysis; (3) identify reasonable alternatives to be addressed in the 
    EA; (4) solicit from the meeting participants all available 
    information, especially quantitative data, on the resources at issue; 
    and (5) encourage statements from experts and the public on issues that 
    should be analyzed in the EA.
        Although Chelan PUD's intent is to prepare an EA, there is the 
    possibility that an Environmental Impact Statement (EIS) will be 
    required. Nevertheless, this meeting will satisfy the NEPA scoping 
    requirements, irrespective of whether an EA or EIS is issued by the 
    Commission.
        The times and locations of the scoping meetings are:
    
    Evening Scoping Meeting
    
    November 18, 1998, 6:00 pm to 9:00 pm, Caravel Resort, 322 West Woodin 
    Avenue, Chelan, WA 98816, (509) 682-2582
    
    Morning Scoping Meeting
    
    November 19, 1998, 10:00 am to 1:00 pm, Caravel Resort, 322 West Woodin 
    Avenue, Chelan, WA 98816, (509) 682-2582
    
        All interested individuals, organizations, and agencies are invited 
    and encouraged to attend any or all of the meetings to assist in 
    identifying and clarifying the scope of environmental issues that 
    should be analyzed in the EA.
    
    Scoping Meeting Procedures
    
        The meetings will be conducted according to the procedures used at 
    Commission scoping meetings. Because this meeting will be a NEPA 
    scoping meeting under the APEA process, the Commission does not intend 
    to conduct a NEPA scoping meeting after Chelan PUD's application and EA 
    are filed with the Commission. Instead, Commission staff will attend 
    the meetings on November 18 and 19, 1998.
    
    Commenting Deadline
    
        Both scoping meetings will be recorded by a stenographer, and the 
    transcripts will become part of the formal record of the proceedings 
    for this project. Those who choose not to speak during the scoping 
    meetings may instead submit written comments on the project. Written 
    comments should be mailed or e-mailed to: Mr. Gregg Carrington, Public 
    Utility District No. 1 of Chelan County, Washington, P.O. Box 1231, 
    Wenatchee, WA 98807-1231, gregg@chelanpud.org.
        All correspondence should be postmarked no later than January 19, 
    1999. Comments should show the following caption on the first page: 
    Scoping Comments, Lake Chelan Hydroelectric Project, Project No. 637.
        For further information please contact Gregg Carrington of Chelan 
    PUD at (509) 663-8121 or Vince Yearick of the Commission at (202) 291-
    3073.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-28575 Filed 10-23-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
10/26/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-28575
Pages:
57116-57116 (1 pages)
Docket Numbers:
Project No. 637
PDF File: