-
Start Preamble
AGENCY:
Coast Guard, DOT.
ACTION:
Temporary final rule.
SUMMARY:
The Coast Guard is temporarily changing the drawbridge operation regulations that govern the William T. Morrisey Boulevard Bridge, at mile 0.0, across Dorchester Bay at Boston, Massachusetts. This temporary change to the drawbridge operation regulations will allow the bridge to remain in the closed position from November 1, 2001 through May 10, 2002. This action is necessary to facilitate necessary maintenance at the bridge.
DATES:
This rule is effective from November 1, 2001 through May 10, 2002.
ADDRESSES:
Comments and material received from the public, as well as documents indicated in this preamble as being available in the docket, are part of docket (CGD01-01-142) and are available for inspection or copying at the First Coast Guard District, Bridge Branch Office, 408 Atlantic Avenue, Boston, Massachusetts, 02110, 7 a.m. to 3 p.m., Monday through Friday, except Federal holidays.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Mr. John McDonald, Project Officer, First Coast Guard District, (617) 223-8364.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
Regulatory Information
On September 11, 2001, we published a notice of proposed rulemaking (NPRM) entitled Drawbridge Operation Regulations; Dorchester Bay, Massachusetts, in the Federal Register (66 FR 47123). We received no comments in response to the notice of proposed rulemaking. No public hearing was requested and none was held. Pursuant to 5 U.S.C. 553, good cause exists for making this regulation effective in less than 30 days after publication in the Federal Register. The Coast Guard discussed the bridge closure with the members of the only marine facility, the Dorchester Yacht Club, effected by this change in operating regulations prior to publication of the notice of proposed rulemaking and no objections were received.
The NPRM specified that we anticipated that the final rule would become effective less than 30 days following publication. Any delay encountered in this regulation's effective date would be unnecessary and contrary to the public interest since immediate action is needed to perform this project during the winter months when there have been few requests to open the bridge.
Background and Purpose
The William T. Morrisey Boulevard Bridge, at mile 0.0, across Dorchester Bay has a vertical clearance of 12 feet at mean high water and 22 feet at mean low water. The existing regulations at 33 CFR 117.597 require the draw to open on signal from April 16 through October 14; except that, the draw need not open for vessel traffic from 7:30 a.m. to 9 a.m. and from 4:30 p.m. to 6 p.m. except on Saturdays, Sundays, or holidays observed in the locality. From October 15 through April 15, the draw shall open on signal if at least twenty-four hours notice is given.
The bridge owner, the Metropolitan District Commission (MDC), asked the Coast Guard to temporarily change the drawbridge operation regulations to allow the bridge to remain in the closed position from November 1, 2001 through May 10, 2002, to facilitate rehabilitation construction at the bridge. The bridge owner and the Coast Guard contacted all known waterway users to advise them of the proposed closure. No objections or negative comments were received in response to this proposal.
Discussion of Comments and Changes
The Coast Guard received no comments in response to the notice of proposed rulemaking and as a result, no changes have been made to this final rule.
Regulatory Evaluation
This rule is not a “significant regulatory action” under section 3(f) of Executive Order 12866 and does not require an assessment of potential costs and benefits under section 6(a)(3) of that Order. The Office of Management and Budget has not reviewed it under that Order. It is not “significant” under the regulatory policies and procedures of the Department of Transportation (DOT) (44 FR 11040; February 26, 1979). This conclusion is based on the fact that the only marine facility affected by this rule has agreed to the closure period for the bridge.
Small Entities
Under the Regulatory Flexibility Act (5 U.S.C. 601-612) we considered whether this rule would have a significant economic impact on a substantial number of small entities. “Small entities” comprises small businesses, not-for profit organizations that are independently owned and operated and are not dominant in their fields, and governmental jurisdictions with populations less than 50,000.
The Coast Guard certifies under 5 U.S.C. 605(b) that this rule will not have a significant economic impact on a substantial number of small entities. This conclusion is based on the fact that the only marine facility affected by this rule has agreed to the closure period for the bridge.Start Printed Page 54141
Collection of Information
This rule calls for no new collection of information under the Paperwork Reduction Act of 1995 (44 U.S.C. 3501-3520).
Federalism
We have analyzed this rule under Executive Order 13132 and have determined that this rule does not have implications for federalism under that Order.
Unfunded Mandates Reform Act
The Unfunded Mandates Reform Act of 1995 (2 U.S.C. 1531-1538) governs the issuance of Federal regulations that require unfunded mandates. An unfunded mandate is a regulation that requires a State, local, or tribal government or the private sector to incur direct costs without the Federal Government's having first provided the funds to pay those unfunded mandate costs. This rule will not impose an unfunded mandate.
Taking of Private Property
This rule will not effect a taking of private property or otherwise have taking implications under Executive Order 12630, Governmental Actions and Interference with Constitutionally Protected Property Rights.
Civil Justice Reform
This rule meets applicable standards in sections 3(a) and 3(b)(2) of Executive Order 12988, Civil Justice Reform, to minimize litigation, eliminate ambiguity, and reduce burden.
Protection of Children
We have analyzed this rule under Executive Order 13045, Protection of Children from Environmental Health Risks and Safety Risks. This rule is not an economically significant rule and does not concern an environmental risk to health or risk to safety that may disproportionately affect children.
Environment
The Coast Guard considered the environmental impact of this rule and concluded that under figure 2-1, paragraph (32)(e) of Commandant Instruction M16475.1C, this rule is categorically excluded from further environmental documentation because promulgation of changes to drawbridge regulations have been found to not have a significant effect on the environment. A written “Categorical Exclusion Determination” is not required for this final rule.
Indian Tribal Governments
This final rule does not have tribal implications under Executive Order 13175, Consultation and Coordination with Indian Tribal Governments, because it does not have substantial direct effect on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes.
Energy Effects
We have analyzed this rule under Executive Order 13211, Actions Concerning Regulations That Significantly Affect Energy Supply, Distribution, or Use. We have determined that it is not a “significant energy action” under that order because it is not a “significant regulatory action” under Executive Order 12866 and is not likely to have a significant adverse effect on the supply, distribution, or use of energy. It has not been designated by the Administrator of the Office of Information and Regulatory Affairs as a significant energy action. Therefore, it does not require a Statement of Energy Effects under Executive Order 13211.
Start List of SubjectsList of Subjects in 33 CFR Part 117
- Bridges
Regulations
For the reasons set out in the preamble, the Coast Guard amends 33 CFR part 117 as follows:
Start PartPART 117—DRAWBRIDGE OPERATION REGULATIONS
End Part Start Amendment Part1. The authority citation for part 117 continues to read as follows:
End Amendment Part[Suspended]2. From November 1, 2001 through May 10, 2002, § 117.597 is suspended.
End Amendment Part Start Amendment Part3. From November 1, 2001 through May 10, 2002, § 117.T602 is temporarily added to read as follows:
End Amendment PartDorchester Bay.The draw of the William T. Morrisey Boulevard Bridge, mile 0.0, at Boston, need not open for the passage of vessel traffic.
Dated: October 12, 2001.
G.N. Naccara,
Rear Admiral, U.S. Coast Guard, Commander, First Coast Guard District.
[FR Doc. 01-26994 Filed 10-25-01; 8:45 am]
BILLING CODE 4910-15-U
Document Information
- Effective Date:
- 11/1/2001
- Published:
- 10/26/2001
- Department:
- Coast Guard
- Entry Type:
- Rule
- Action:
- Temporary final rule.
- Document Number:
- 01-26994
- Dates:
- This rule is effective from November 1, 2001 through May 10, 2002.
- Pages:
- 54140-54141 (2 pages)
- Docket Numbers:
- CGD01-01-142
- RINs:
- 2115-AE47: Drawbridge Regulations
- RIN Links:
- https://www.federalregister.gov/regulations/2115-AE47/drawbridge-regulations
- Topics:
- Bridges
- PDF File:
- 01-26994.pdf
- CFR: (2)
- 33 CFR 117.597
- 33 CFR 117.T602