03-27140. Hazard Mitigation Planning and Hazard Mitigation Grant Program  

  • Start Preamble

    AGENCY:

    Federal Emergency Management Agency (FEMA), Emergency Preparedness and Response Directorate, Department of Homeland Security.

    ACTION:

    Interim final rule.

    SUMMARY:

    This rule clarifies the date that local mitigation plans will be required as a condition of receiving project grant funds under the Pre-Disaster Mitigation (PDM) program. In addition, we are taking the opportunity to correct cross references in our regulations to address areas of inconsistency regarding the planning requirement in the Fire Management Assistance Grant Program and Public Assistance Eligibility that should have been addressed previously.

    DATES:

    Effective Date: October 28, 2003. Comment Date: We will accept written comments through December 29, 2003.

    ADDRESSES:

    Please send written comments to the Rules Docket Clerk, Office of the General Counsel, Federal Emergency Management Agency, 500 C Street, SW., Room 840, Washington DC 20472, (facsimile) 202-646-4536, or (email) rules@fema.gov.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Karen Helbrecht, Program Planning Branch, Mitigation Division, Federal Emergency Management Agency, 500 C Street, SW., Washington DC, 20472, 202-646-3358, (facsimile) 202-646-4127, or (email) karen.helbrecht@dhs.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    On February 26, 2002, FEMA published an interim final rule at 67 FR 8844 implementing section 322 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act or the Act), 42 U.S.C. 5165, enacted under section 104 of the Disaster Mitigation Act of 2000, (DMA 2000) Public Law 106-390. This identified the Start Printed Page 61369requirements for State, tribal, and local mitigation plans necessary for Hazard Mitigation Grant Program (HMGP) project funding. On October 1, 2002, FEMA published a change to that rule at 67 FR 61512, extending the date that the planning requirements take effect. This rule stated that for disasters declared on or after November 1, 2004, State Mitigation Plans will be required in order to receive non-emergency Stafford Act assistance, and local mitigation plans will be required in order to receive HMGP project grants.

    However, the date that local mitigation plans will be required for the Pre-Disaster Mitigation program as a condition of project grant funding was left at November 1, 2003. The intent was to make grants and technical assistance available in fiscal year 2003 to assist State and local governments to develop mitigation plans and implement mitigation projects during the first year of the competitive grant program. However, because the application period for the competitive PDM program will not close until October 6, 2003, the project grants will not be awarded until after November 1, 2003. The intent of this rule change is to clarify that the November 1, 2003 effective date for the planning requirement will apply only to PDM grant funds awarded under any Notice of funding opportunity issued after that date. Essentially, for PDM grant funds made available in fiscal year 2004 and beyond, local governments must have an approved mitigation plan in order to receive a project grant under the PDM program.

    In addition, this rule updates the planning requirement identified in 44 CFR part 204, Fire Management Assistance Grant Program as well as part 206, subpart H, Public Assistance Eligibility. The changes bring these sections into conformity with the existing planning rule, 44 CFR part 201.

    FEMA received many thoughtful comments, and intends to address them all prior to finalizing the rule. However, in the interest of expediting these minor clarifying and conforming changes, FEMA is issuing another interim final rule. FEMA encourages comments on this interim final rule, and will make every effort to involve all interested parties, including those who commented on the original interim final planning rules, prior to the development of the Final Rule.

    Administrative Procedure Act Statement.

    In general, FEMA publishes a rule for public comment before issuing a final rule, under the Administrative Procedure Act, 5 U.S.C. 533 and 44 CFR 1.12. The Administrative Procedure Act, however, provides an exception from that general rule where the agency for good cause finds the procedures for comment and response contrary to the public interest.

    This interim final rule clarifies the date that local governments, as well as a tribe applying as a sub-applicant, must have a mitigation plan as a condition of receiving FEMA PDM project grant assistance. This interim final rule clarifies that the plan requirement applies only to PDM project grants awarded under any Notice of funding opportunity issued after November 1, 2003. The Notice of Availability of Funding (NOFA) for the fiscal year 2003 PDM program was not published until July 7, 2003, making it difficult to make grant awards by November 1, 2003. In order to make timely awards for the fiscal year 2003 PDM program, it is essential that the clarification of the effective date of the planning requirement be made effective as soon as possible.

    In addition, this rule brings the mitigation planning requirements for the Fire Management Assistance Grant Program, and FEMA's Public Assistance Program into conformity with 44 CFR part 201. FEMA believes it is contrary to the public interest to delay the benefits of this rule. In accordance with the Administrative Procedure Act, 5 U.S.C. 553(d)(3), we find good cause for the interim final rule to take effect immediately upon publication in the Federal Register in order to meet the needs of States, tribes, and communities by clarifying the effective date for planning requirements under 44 CFR part 201. Therefore, FEMA finds that prior notice and comment on this rule would not further the public interest. FEMA actively encourages, solicits, and will consider comments on this interim final rule from interested parties, as well as those submitted on the original interim final planning rule, in preparing the final rule. For these reasons, FEMA believes there is good cause to publish an interim final rule.

    National Environmental Policy Act

    44 CFR 10.8(d)(2)(ii) excludes this rule from the preparation of an environmental assessment or environmental impact statement, where the rule relates to actions that qualify for categorical exclusion under 44 CFR 10.8(d)(2)(iii), such as the development of plans under this section.

    Executive Order 12866, Regulatory Planning and Review

    FEMA has prepared and reviewed this rule under the provisions of Executive Order 12866, Regulatory Planning and Review. Under Executive Order 12866, 58 FR 51735, Oct. 4, 1993, a significant regulatory action is subject to OMB review and the requirements of the Executive Order. The Executive Order defines “significant regulatory action” as one that is likely to result in a rule that may:

    (1) Have an annual effect on the economy of $100 million or more or adversely affect in a material way the economy, a sector of the economy, productivity, competition, jobs, the environment, public health or safety, or State, local, or tribal governments or communities;

    (2) Create a serious inconsistency or otherwise interfere with an action taken or planned by another agency;

    (3) Materially alter the budgetary impact of entitlements, grants, user fees, or loan programs or the rights and obligations of recipients thereof; or

    (4) Raise novel legal or policy issues arising out of legal mandates, the President's priorities, or the principles set forth in th[e] Executive [O]rder.

    The purpose of this rule is to clarify the date by which State, tribal, and local governments have to prepare or update their plans to meet the criteria identified in 44 CFR part 201. This interim final rule clarifies that local governments must have a mitigation plan approved in order to receive a project grant through the PDM program under any Notice of funding opportunity issued after November 1, 2003, in fiscal year 2004 and beyond. As such, the rule itself will not have an effect on the economy of more than $100,000,000.

    Therefore, this rule is not a significant regulatory action and is not an economically significant rule under Executive Order 12866. The Office of Management and Budget (OMB) has reviewed this rule under Executive Order 12866.

    Executive Order 12898, Environmental Justice

    Environmental Justice is incorporated into policies and programs under Executive Order 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, 59 FR 7629, Feb. 16, 1994. The Executive Order requires each Federal agency to conduct its programs, policies, and activities that substantially affect human health or the environment, in a manner that ensures that those programs, policies, and activities do not have the effect of excluding persons from program participation, denying persons program benefits, or subjecting persons to discrimination because of their race, color, or national origin. Start Printed Page 61370

    No action that FEMA can anticipate under the final rule will have a disproportionately high or adverse human health and environmental effect on any segment of the population. This rule extends the date for development or update of State and local mitigation plans in compliance with 44 CFR part 201. Accordingly, the requirements of Executive Order 12898 do not apply to this interim final rule.

    Paperwork Reduction Act of 1995

    This new interim final rule simply clarifies the date by which States and communities have to comply with the planning requirements, and clarifies which FEMA programs are affected by these requirements. The changes do not affect the collection of information; therefore, no change to the request for the collection of information is necessary. In summary, this interim final rule complies with the provisions of the Paperwork Reduction Act of 1995 (44 U.S.C. 3506(c)(2)(A)).

    Executive Order 13132, Federalism

    Executive Order 13132, Federalism, dated August 4, 1999, sets forth principles and criteria to which agencies must adhere in formulating and implementing policies that have federalism implications, that is, regulations that have substantial direct effects on the States, or on the distribution of power and responsibilities among the various levels of government. Federal agencies must closely examine the statutory authority supporting any action that would limit the policymaking discretion of the States, and to the extent practicable, must consult with State and local officials before implementing any such action.

    FEMA reviewed this rule under Executive Order 13132 and concluded that the rule has no federalism implications as defined by the Executive Order. FEMA has determined that the rule does not significantly affect the rights, roles, and responsibilities of States, and involves no preemption of State law nor does it limit State policymaking discretion.

    FEMA will continue to evaluate the planning requirements and work with interested parties as the planning requirements of 44 CFR part 201 are implemented. In addition, we actively encourage and solicit comments on this interim final rule from interested parties, and will consider them in preparing the final rule.

    Executive Order 13175, Consultation and Coordination with Indian Tribal Governments

    FEMA has reviewed this interim final rule under Executive Order 13175, which became effective on February 6, 2001. In this review, no “tribal implications” as defined in Executive Order 13175 were found because it will not have a substantial direct effect on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes. Moreover, the interim final rule does not impose substantial direct compliance costs on tribal governments, nor does it preempt tribal law, impair treaty rights or limit the self-governing powers of tribal governments.

    Congressional Review of Agency Rulemaking.

    FEMA sent this interim final rule to the Congress and to the General Accounting Office under the Congressional Review of Agency Rulemaking Act, Public Law 104-121. The rule is not a “major rule” within the meaning of that Act. It is an administrative action to extend the time State and local governments have to prepare mitigation plans required by Section 322 of the Stafford Act, as enacted in DMA 2000.

    The rule will not result in a major increase in costs or prices for consumers, individual industries, Federal, State, or local government agencies, or geographic regions. It will not have “significant adverse effects” on competition, employment, investment, productivity, innovation, or on the ability of United States-based enterprises to compete with foreign-based enterprises.

    In compliance with section 808(2) of the Congressional Review of Agency Rulemaking Act, 5 U.S.C. 8(2), for good cause we find that notice and public procedure on this interim final rule are impracticable, unnecessary, or contrary to the public interest. In order to make timely awards for the fiscal year 2003 PDM program, it is essential that the clarification of the effective date of the planning requirement be made effective as soon as possible. Accordingly, this interim final rule is effective on October 28, 2003.

    Start List of Subjects

    List of Subjects in 44 CFR Part 201, Part 204, and Part 206

    • Administrative practice and procedure
    • Disaster assistance
    • Grant programs
    • Mitigation planning
    • Reporting and record keeping requirements
    End List of Subjects Start Amendment Part

    Accordingly, FEMA amends 44 CFR Parts 201, 204, and 206 as follows:

    End Amendment Part Start Part

    PART 201—MITIGATION PLANNING

    End Part Start Amendment Part

    1. The authority citation for part 201 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Robert T. Stafford Disaster Relief and Emergency Assistance Act, 42 U.S.C. 5121-5206; Reorganization Plan No. 3 of 1978, 43 FR 41943, 3 CFR, 1978 Comp., p. 329; E.O. 12127, 44 FR 19367, 3 CFR, 1979 Comp., p. 376; E.O. 12148, 44 FR 43239, 3 CFR, 1979 Comp., p. 412; and E.O. 12673, 54 FR 12571, 3 CFR, 1989 Comp., p. 214.

    End Authority Start Amendment Part

    2. Section 201.6(a)(2) is revised to read as follows:

    End Amendment Part
    Local Mitigation Plans.
    * * * * *

    (a) * * *

    (2) Local governments must have a mitigation plan approved pursuant to this section in order to receive a project grant through the Pre-Disaster Mitigation (PDM) program under any Notice of funding opportunity issued after November 1, 2003. The PDM program is authorized under § 203 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act, 42 U.S.C. 5133. PDM planning grants will continue to be made available to local governments after this time to enable them to meet the requirements of this section.

    * * * * *
    Start Part

    PART 204—FIRE MANAGEMENT ASSISTANCE GRANT PROGRAM

    End Part Start Amendment Part

    3. The authority citation for part 204 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Robert T. Stafford Disaster Relief and Emergency Assistance Act, 42 U.S.C. 5121-5206; Reorganization Plan No. 3 of 1978, 43 FR, 41943, 3 CFR, 1978 Comp., p. 329; E.O. 12127, 44 FR 19367, 3 CFR, 1979 Comp., p. 376; E.O. 12148, 44 FR 43239, 3 CFR, 1979 Comp., p 412; and E.O. 12673, 54 FR 12571, 2 CFR, 1989 Comp., p. 214.

    End Authority Start Amendment Part

    4. Revise the definition of Hazard mitigation plan in § 204.3 to read as follows:

    End Amendment Part
    Definitions used throughout this part.
    * * * * *

    Hazard mitigation plan. A plan to develop actions the State, local, or tribal government will take to reduce the risk to people and property from all hazards. The intent of hazard mitigation planning under the Fire Management Assistance Grant Program is to identify wildfire hazards and cost-effective mitigation alternatives that produce Start Printed Page 61371long-term benefits. We address mitigation of fire hazards as part of the State's comprehensive Mitigation Plan, described in 44 CFR part 201.

    * * * * *
    Start Amendment Part

    5. Revise § 204.51(d)(2) to read as follows:

    End Amendment Part
    Application and approval procedures for a fire management assistance grant.
    * * * * *

    (d) * * *

    (2) Hazard Mitigation Plan. As a requirement of receiving funding under a fire management assistance grant, a State, or tribal organization, acting as Grantee, must:

    (i) Develop a Mitigation Plan in accordance with 44 CFR part 201 that addresses wildfire risks and mitigation measures; or

    (ii) Incorporate wildfire mitigation into the existing Mitigation Plan developed and approved under 44 CFR part 201 that also addresses wildfire risk and contains a wildfire mitigation strategy and related mitigation initiatives.

    Start Part

    PART 206—FEDERAL DISASTER ASSISTANCE FOR DISASTERS DECLARED ON OR AFTER NOVEMBER 23, 1988.

    End Part Start Amendment Part

    6. The authority citation for part 206 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Robert T. Stafford Disaster Relief and Emergency Assistance Act, 42 U.S.C. 5121-5206; Reorganization Plan No. 3 of 1978, 43 FR 41943, 3 CFR, 1978 Comp., p. 329; E.O. 12127, 44 FR 19367, 3 CFR, 1979 Comp., p. 376; E.O. 12148, 44 FR 43239, 3 CFR, 1979 Comp., p. 412; and E.O. 12673, 54 FR 12571, 3 CFR, 1989 Comp., p. 214.

    End Authority Start Amendment Part

    7. Revise § 206.226(b) to read as follows:

    End Amendment Part
    Restoration of damaged facilities.
    * * * * *

    (b) Mitigation planning. In order to receive assistance under this section, as of November 1, 2004, the State must have in place a FEMA approved State Mitigation Plan in accordance with 44 CFR part 201.

    * * * * *
    Start Signature

    Dated: October 22, 2003.

    Michael D. Brown,

    Under Secretary, Emergency Preparedness and Response, Department of Homeland Security.

    End Signature End Supplemental Information

    [FR Doc. 03-27140 Filed 10-27-03; 8:45 am]

    BILLING CODE 9110-13-P

Document Information

Published:
10/28/2003
Department:
Federal Emergency Management Agency
Entry Type:
Rule
Action:
Interim final rule.
Document Number:
03-27140
Pages:
61368-61371 (4 pages)
RINs:
1660-AA17: Hazard Mitigation Planning and Hazard Mitigation Grant Program
RIN Links:
https://www.federalregister.gov/regulations/1660-AA17/hazard-mitigation-planning-and-hazard-mitigation-grant-program
Topics:
Administrative practice and procedure, Disaster assistance, Grant programs, Reporting and recordkeeping requirements, Reporting and recordkeeping requirements
PDF File:
03-27140.pdf
CFR: (4)
44 CFR 201.6
44 CFR 204.3
44 CFR 204.51
44 CFR 206.226