2024-24967. Federal Railroad Administration Accident/Incident Investigation Policy for Gathering Information and Consulting With Stakeholders; Correction
Table 1—Total Costs of the Direct Final Rule
[2023 Dollars] *
Year Total stakeholder costs Total government costs Total costs Discounted 7% Discounted 3% Discounted 2% 1 $97,922 $19,753 $117,675 $117,675 $117,675 $117,675 2 97,922 10,541 108,463 101,367 105,304 106,336 3 97,922 10,541 108,463 94,736 102,237 104,251 4 97,922 10,541 108,463 88,538 99,259 102,207 5 97,922 10,541 108,463 82,746 96,368 100,203 6 97,922 10,541 108,463 77,333 93,561 98,238 7 97,922 10,541 108,463 72,273 90,836 96,312 8 97,922 10,541 108,463 67,545 88,190 94,424 9 97,922 10,541 108,463 63,126 85,622 92,572 10 97,922 10,541 108,463 58,997 83,128 90,757 Total 979,220 114,622 1,093,842 824,336 962,180 1,002,975 Note: This table and some others throughout this analysis may not sum due to rounding. * All figures are presented in a 2023 base year unless otherwise noted.