97-28580. Williston Basin Interstate Pipeline Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 62, Number 209 (Wednesday, October 29, 1997)]
    [Notices]
    [Pages 56156-56157]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-28580]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-36-000]
    
    
    Williston Basin Interstate Pipeline Company; Notice of Request 
    Under Blanket Authorization
    
    October 23, 1997.
        Take notice that on October 17, 1997, Williston Basin Interstate 
    Pipeline Company (Williston Basin), 200 North Third Street, Suite 300, 
    Bismarck, North Dakota 58501, filed in Docket No. CP98-36-000 a request 
    pursuant to Sections 157.205 and 157.211 of the Commission's 
    Regulations under the Natural Gas Act (18 CFR 157.205, 157.211) for 
    authorization to construct and operate new metering and associated 
    appurtenant facilities in Big Horn County, Wyoming, for use in 
    providing delivery of transportation service to KCS Mountain Resources, 
    Inc. (KCS), under Williston Basin's blanket certificate issued in 
    Docket Nos. CP82-487-000, et al., pursuant to Section 7 of the Natural 
    Gas Act, all as more fully set forth in the request that is on file 
    with the Commission and open to public inspection.
        Williston Basin states that KCS has requested the installation of 
    metering facilities to allow Williston Basin to make deliveries of up 
    to 7,500 Mcf per day to KCS to be used at its gas processing plant and 
    for KCS to provide gas service to a local distribution company.
        Williston Basin states that the facilities to be constructed will 
    consist of a new four-inch meter run, meter, SCADA communication 
    equipment and miscellaneous piping, gauges and valves, all of which 
    will be installed within the existing buildings or within the existing 
    fenced metering station. Williston Basin estimates the cost of the 
    proposed metering facilities to be $59,000, and that the actual cost of 
    the facilities is 100% reimbursable by KCS.
        Williston Basin states that in addition to the facilities mentioned 
    above, Williston Basin will be installing approximately 12 feet of 
    additional six-inch piping to connect its system at the intersection of 
    its 10-inch Manderson Lateral and its 12-inch Worland-Cabin Creek 
    Yellow Line to effectuate the delivery of gas to KCS. Williston Basin 
    states that this construction will occur entirely on existing pipeline 
    right-of-way within a concrete-enclosed underground valve box and no 
    ground disturbance will occur. Williston Basin proposes to complete and 
    report such construction under Section 157.208(a) of the Commission's 
    Regulations.
        Williston Basin states that it will provide natural gas 
    transportation deliveries to KCS under Rate Schedules FT-1 and/or IT-1 
    of Williston Basin's FERC Gas Tariff, Second Revised Volume No. 1, and 
    that Williston Basin's FERC Gas tariff does not prohibit the addition 
    of new delivery points. Williston Basin also states that the addition 
    of the proposed facilities will have no significant effect on its peak 
    day or annual requirements and capacity has been determined to exist on 
    the Williston Basin system to serve this natural gas market. Williston 
    Basin
    
    [[Page 56157]]
    
    further states that the volumes to be delivered will be within the 
    contractual entitlements of the customer.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 97-28580 Filed 10-28-97; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
10/29/1997
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
97-28580
Pages:
56156-56157 (2 pages)
Docket Numbers:
Docket No. CP98-36-000
PDF File:
97-28580.pdf